ILLINOIS POLLUTION CONTROL BOARD
March 8, 1990
BURLINGTON NORTHERN RAILROAD
)
COMPANY,
Petitioner,
v.
)
PCB 90—34
(Provisional Variance)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
ORDER OF THE BOARD
(3.
Marlin):
This matter comes before the Board upon receipt of an Agency
Recommendation dated March 7, 1990. The recommendation refers to
a request from Petitioner, Burlington Northern Railraod Company
for a 30 day provisional variance from the 90—day on—site
limitations for hazardous wastes set forth in 35 Iii. Adm. Code
722.134(b)
*
Upon receipt of the request the Agency issued its
recommendation, concluding that the hazardous wastes must remain
on—site for longer than 90 days due to unforeseen, temporary and
uncontrollable circumstances and failure to grant the requested
30—day provisional variance would impose an arbitrary or
unreasonable hardship on Petitioner.
Having received the Agency Recommendation, the Board hereby
grants Petitioner a provisional variance from 35 Iii. Adm. Code
722.134(b) from March 12, 1990 to April 11, 1990
IT IS SO ORDERED.
.1, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, e eby certify than e above Order was adopted on
the
_______
day of _____________________________, 1990, by a
vote of
7—O
Control Board
109—295