ILLINOIS POLLUTION CONTROL
    BOARD
    May 10,
    1990
    CENTRALIA
    ENVIRONMENTAL
    SERVICES,
    INC.,
    Petitioner,
    )
    PCB
    89—170
    (Permit
    Appeal)
    v.
    ILLINOIS
    ENVIRONMENTAL
    PROTECTION
    AGENCY,
    Respondent.
    INTERIM OPINION
    AND
    ORDER OF THE BOARD
    (by N.
    Nardulli):
    This matter comes before the Board on a petition for review
    filed October 23,
    1989 by Centralia Environmental Services,
    Inc.
    (CESI)
    in which CESI contests the Illinois Environmental Protection
    Agency’s
    (Agency) denial of a supplemental development
    permit
    and
    an operating permit for Area IV of CESI’s landfill site.
    Hearings
    were held on December 18,
    19,
    20,
    27, and
    28 of 1989
    at which
    no
    members
    of the public attended.
    STATEMENT
    OF
    FACTS
    CESI’s regional
    pollution
    control
    facility
    is
    located
    on
    a
    forty
    acre
    parcel
    of
    land
    near
    Centralia,
    Illinois
    in
    Marion
    County.
    The site was initially permitted for development as a non-
    regional pollution control facility on February
    9,
    1984.
    (Agency
    Record at 147-57.)
    The development permit was issued to Industrial
    Salvage,
    Inc.
    and John Prior,
    president,
    as
    owner and operator.
    (~.)
    Progressive development of the site was to occur throughout
    six portions of the site designated
    as Areas
    I through VI.
    ~
    at
    34-40.)
    In
    the development
    permit,
    the Agency
    imposed
    the
    condition that, prior to obtaining any operating permits for Areas
    I through IV,
    a registered professional engineer must certify that
    at
    least ten feet of clay with
    a maximum permeability
    of lxlO
    -7
    cm/sec exists at the bottom and sidewalls
    of the Area.
    (Id.
    Ex.
    2 at 147—50.)
    In
    1986,
    the development permit was transferred
    to Jackson
    County Landfill,
    Inc.
    d/b/a/ Industrial Services Inc.
    as operator.
    The development permit was modified to allow site development
    as
    a regional pollution control facility.
    Also in 1986,
    an operating
    111-Ill

    2
    permit was issued for Area
    I to Industrial Salvage,
    Inc.
    as owner
    and Jackson County Landfill,
    Inc. d/b/a Industrial Services,
    Inc.
    as
    operator.
    (~.
    Ex.
    8
    at 674—90.)
    Area
    I
    was permitted
    for
    disposal
    of
    municipal
    waste
    and
    non-hazardous
    special
    waste;
    however,
    the disposal
    of
    special wastes which would
    yield fluid
    when subjected to the “paint filter test” was prohib~.ted. Jackson
    County Landfill
    Inc.
    received
    a supplemental permit to allow the
    “retrofitting”
    of
    a
    leachate
    collection
    system
    so
    that
    liquid
    special
    waste could
    be accepted
    at
    the site.
    After
    failure
    to
    obtain
    Agency
    approval
    of
    the
    leachate
    collection
    system,
    the
    operator obtained
    a
    supplemental permit allowing
    for the removal
    of the leachate system.
    On January
    28,
    1988,
    CESI purchased
    the business
    assets of
    Jackson County
    Landfill,
    Inc.
    (Id.
    at
    937.)
    CESI
    submitted
    an
    application
    for
    transfer
    of
    all
    existing
    permits
    and
    for
    an
    operating permit for Areas
    II and
    III.
    (Id.
    Ex.
    28
    at 835-959.)
    At that time, the Agency and William T. Schmidt, president of CESI,
    discussed the need to investigate the alleged unauthorized disposal
    of waste
    in Area
    II
    and the need
    for remedial action
    to address
    allegations by
    a
    former employee that waste had been disposed
    of
    below grade
    in a
    50 feet by 500
    feet section located
    in Areas III
    and IV.
    (This area will be referred to as the “investigation area”
    or
    “reinediation
    area”.)
    (Id.
    at
    835—36,
    868—69,
    and
    883.)
    Existing
    permits were
    transferred
    to CESI
    and CESI
    obtained
    an
    operating
    permit
    for
    Areas
    II
    and
    III
    on
    March
    21,
    1988.
    In
    granting CESI’s
    permit,
    the Agency
    required that CESI
    conduct
    a
    remedial investigation of the 50 feet by 500 feet suspect area and
    to submit
    a plan of action
    for the Agency’s approval.
    Also,
    the
    Agency
    imposed the condition that
    “in the
    event that
    the boring
    program
    reveals
    waste
    has
    been
    disposed
    of
    ‘below
    grade’,
    no
    operating
    permits
    for additional
    areas
    of this
    landfill will be
    issued by the Agency until
    an Agency approved remedial action
    is
    satisfactorily
    implemented
    pursuant
    to
    an
    issued
    supplemental
    development
    permit.”
    (Permit
    No.
    l987-299-SP
    condition
    no.
    2(c) ii.)
    On June
    14,
    1988,
    CESI
    submitted
    a plan of action which was
    approved
    by
    the
    Agency.
    (Agency Record
    at
    1017-27.)
    The plan
    provided for the excavation of above-grade waste in the reinediatiori
    area and the reburial of that waste on other permitted sections of
    the site.
    After the removal process began
    in August of
    1988, the
    Agency
    requested
    that
    CESI
    aid
    in
    exploring
    allegations
    that
    hazardous wastes had been disposed of in the area by setting aside
    any drums encountered in the excavation process.
    Twelve drums were
    set aside
    for Agency
    inspection.
    Analysis
    of
    one
    of
    the drums
    revealed
    the
    presence
    of
    organic
    solvents,
    including
    toluene,
    ethylbenzene and substituted benzenes.
    (k~.
    at 537-42.)
    In October of
    1988,
    CESI contacted the Agency to discuss the
    waste
    removal
    process
    and boring
    program
    for
    the
    investigation
    area.
    CESI
    indicated
    that
    it
    was
    likely
    that
    waste
    had been
    i
    i
    i
    -
    1 2

    3
    deposited
    below
    permitted
    levels and sought permission
    to remove
    the waste.
    The Agency agreed that the waste should be removed but
    also
    informed
    CESI
    that
    backfilling was not
    to
    occur until
    the
    boring program was completed.
    However,
    on October
    5,
    1988,
    CESI
    began filling the excavation area with recompacted clay. Following
    completion
    of
    the
    backfilling,
    borings
    were
    conducted
    in
    the
    investigation
    area.
    The
    borings
    did
    not encounter
    any waste;
    however,
    groundwater
    was
    encountered
    within
    a
    few
    feet
    of
    the
    surface of several borings.
    CESI submitted a
    report
    detailing
    the
    results
    of
    the
    investigation.
    On
    June
    29,
    1989,
    CESI
    submitted
    a
    supplemental
    development
    permit
    application
    to
    the
    Agency.
    On September
    21,
    1989,
    CESI
    submitted
    an
    addendum
    to
    the
    application
    seeking
    to
    strike
    condition
    no.
    2(c)ii
    from
    the
    supplemental
    permit
    (Permit
    No.
    1987-
    299—SP).
    On
    September
    27,
    1989,
    the
    Agency
    denied
    CESI’s
    application
    and
    motion
    to
    strike
    .
    On
    August
    25,
    1989,
    CESI
    submitted
    an
    application
    for
    an
    operating
    permit
    for Area
    IV.
    (Agency
    Record
    at
    1425-65.)
    On
    October
    6,
    1989,
    the
    Agency
    denied
    CESI’s application.
    In the instant matter,
    CESI
    appeals
    from
    the
    Agency’s
    denial
    of
    both
    the supplemental development permit and the
    operating
    permit
    applications.
    By
    order
    of
    the
    hearing
    officer,
    simultaneous
    briefs
    were
    due
    to
    be
    filed
    no later
    than January
    16,
    1990.
    While
    the Agency
    timely
    filed
    its
    brief,
    CESI
    failed
    to
    comply with
    the January
    deadline.
    On March
    8,
    1990,
    the Board entered an order directing
    CESI
    to
    explain the delay and to
    file
    a motion for extension
    of
    time to file its brief.
    CESI filed its motion stating that it
    had
    been unable to timely file its brief because the transcripts were
    not prepared and requesting
    an
    extension
    to
    April
    19,
    1990
    to
    file
    its brief.
    On March 22,
    1990,
    the
    Board
    entered
    an order directing
    CESI
    to
    file
    its
    brief
    no
    later than April
    2,
    1990,
    denying
    the
    Agency’s
    request
    to
    decide
    the
    case
    without
    CESI’s
    brief
    and
    allowing
    the
    Agency
    to
    file
    a
    reply brief.
    CESI
    filed
    its brief
    on April 3,
    1990 with a letter stating that it was CESI’s intention
    to
    file
    the
    brief
    on
    April
    2,
    1990
    by
    flying
    to
    Chicago
    and
    personally delivering the brief.
    CESI stated that
    it was unable
    to
    do
    so
    because
    the
    pilot
    refused
    to
    fly
    due
    to
    bad
    weather
    conditions.
    Although CESI should have filed a motion to file its
    brief instanter setting forth the reasons for the one-day delay in
    filing
    its brief and requesting that the
    Board accept the brief
    instanter,
    the
    Board
    accepts
    the
    late
    filing
    of
    CESI’s
    brief
    because the letter sets
    forth the
    reasons
    for failing
    to timely
    file the brief and because the one-day delay
    in filing
    is minimal
    and
    apparently
    unavoidable.
    Supplemental Development Permit
    In its section 39(a)
    letter, the Agency gave three reasons for
    denying
    CESI’s
    application
    for
    a
    supplemental
    development
    permit.
    (Agency Record
    at 1494-96.)
    First,
    the Agency stated that “n)o
    111—Il 3

    4
    hydrogeologic justification has been provided demonstrating that
    the one proposed additional groundwater monitoring well is adequate
    (and
    properly
    located)
    to
    detect any
    groundwater contamination
    resulting from filling the trench in Area IV with waste.”
    (j~.at
    1494.)
    The Agency noted that “g)iven
    the fact that the procedures
    for determining the extent of the waste filling in the trench area
    were not carried out
    in accordance with the plan approved by the
    Agency nor the instructions given by the Agency,
    the groundwater
    monitoring
    needs
    to be designed
    to deal with
    the potential
    that
    waste was disposed directly on top of the bedrock and that leachate
    from this waste may have contaminated the groundwater.”
    (~c~.)
    The
    second
    reason
    given
    by
    the
    Agency
    in
    denying
    CESI’s
    application
    is
    that
    “CESI’s
    application
    suggests
    that
    the
    possibility of groundwater contamination by organic
    compounds
    is
    not of concern and therefore proposes to construct the additional
    well using PVC and to omit organics as monitoring parameters for
    the
    groundwater.
    The possibility of
    organic contamination
    is of
    substantial
    concern
    and
    consequently
    the
    groundwater
    must
    be
    monitored for organics..
    Constructing monitoring wells
    of PVC
    is
    not acceptable
    for purposes of conducting such monitoring.”
    (~?i.
    at 1495.)
    The final reason stated in the Agency’s denial letter is that
    “pursuant
    to
    35 Ill.
    Adrn.
    Code 807.661,
    an annual evaluation of
    the trust fund serving as the instrument of financial assurance for
    closure/post—closure care should have been submitted to the Agency
    by February 23,
    1989.
    Also,
    documentation of an annual payment of
    the trust fund should have been submitted by March 25,
    1989.
    The
    Agency has not received either of these submittals.”
    (u.)
    Operating Permit for Area IV
    The
    Agency
    gave
    five
    reasons
    for
    denying
    CESI’s
    application
    for
    an
    operating
    permit.
    First,
    the
    Agency
    stated
    that
    the
    boring
    logs
    and
    permeability
    tests
    provided
    with
    the
    application
    were
    not
    adequate
    to
    demonstrate
    the
    presence
    of
    the
    clay
    liner
    with
    a
    minimum
    thickness
    of
    10
    feet
    and
    a
    maximum
    permeability
    of
    lxl0
    -
    7
    cm/sec
    required
    by
    condition
    no.
    6
    of
    Permit
    No.
    l987-l94-Sp
    because:
    (1) the location of boring no.
    7
    (monitoring well)
    is not
    given
    on
    the sketch showing the location of the test probes;
    (2)
    the surface elevations of the probes are not provided on the boring
    logs;
    (3) the brown sandy clay found between 7 and 10 feet of depth
    of boring ST-4 has not been tested for permeability; and
    (4) boring
    logs nos. 9—11 of the remedial action report dated October 31, 1988
    show porous materials within
    ten
    feet
    of the top
    of
    the
    liner.
    (Id.
    at 1504.)
    Secondly,
    the Agency stated that
    a
    September
    25,
    1989
    pre—
    operational
    inspection
    performed
    by
    the
    Agency
    revealed
    the
    following deficiencies:
    (1) material deposited on top of the clay
    liner
    in
    the
    eastern
    quarter
    of
    Area
    IV
    so
    that
    no
    visual
    1 11
    -
    1
    1

    5
    inspection could be
    made;
    and
    (2)
    failure to
    construct drainage
    controls and haul roads
    in accordance with the plans included in
    Permit No.
    1984—3—DE.
    (Id.
    at 1504—05.)
    Thirdly,
    pursuant
    to
    35
    Ill.
    Adm Code
    807.661,
    the Agency
    stated that CESI failed to submit an annual evaluaticin of the trust
    fund
    serving
    as
    the
    instrument
    of
    financial
    assurance
    for
    closure/post-closure
    care by
    the requisite date
    of February
    23,
    1989 and failed to submit documentation of an annual payment to the
    trust fund by March
    25, 1989.
    (~.
    at 1505.)
    Fourthly,
    the Agency
    stated
    that
    CESI
    had
    not
    obtained
    a
    supplemental development permit as required by condition no. 2(c)ii
    of
    Permit
    No.
    1987-299-SP
    for the remedial area
    and,
    therefore,
    could not obtain an operating permit for Area IV.
    (Id.)
    Lastly,
    the
    Agency
    stated
    that
    t’since
    Area
    IV
    is
    an
    integral
    part of this facility,
    an operating permit for it cannot be issued
    until
    the
    existing
    problems
    of
    Areas
    I,
    II
    and
    III
    have
    been
    remediated.
    These problems
    include
    the
    increased
    potential
    for
    erosion, run—off, leachate migration and groundwater contamination
    caused by over—filling and over—steepening the slopes of Areas
    I,
    II and III.
    (Id.)
    DISCUSSION
    Before
    reaching
    the
    substantive
    merits
    of
    this
    permit
    review, the Board must address a preliminary issue raised by CESI
    regarding
    the Agency’s denial
    statements.
    Of
    the
    eight “denial
    reasons” given by the Agency,
    only two are supported by reference
    to a specific section of the regulations which may be violated
    if
    the permits were granted.
    (Agency Record
    at
    1494-96,
    1504-06.)
    Three
    of the
    “denial
    reasons”
    refer
    to violations
    of conditions
    imposed in previous permits.
    The remaining three “denial reasons”
    do
    not refer
    to
    any section
    of
    the Act or
    regulations
    or other
    previously imposed permit conditions.
    CESI asserts that the permit
    denial letters issued by the Agency
    fail to meet the requirements
    of
    section
    39(a)
    of theAct
    and
    are,
    therefore,
    “defective
    and
    invalid
    as a matter of statute.”
    (CESI
    Brief at
    23.)
    The Agency
    responds that the “deficiencies are stated with sufficient detail
    to inform
    CESI
    of their basis” and, therefore,
    are in compliance
    with section 39(a)
    of the Act.
    (Agency Reply Brief at
    18.)
    Section 39(a) of the Act requires that, within 90 days1 of the
    filing of the application,
    the Agency provide the applicant with
    a
    detailed
    statement
    of
    the
    reasons
    for
    denying
    the
    permit
    application.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111
    1/2,
    par.
    1039(a).)
    This
    90—day
    period
    is
    extended
    to
    180
    days
    when
    the
    application
    is
    for
    a
    permit to develop
    a
    landfill.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111
    1/2,
    par.
    1039(a).)
    ii 1—i 15

    6
    Section
    39(a)
    provides
    that
    “(such
    statements
    shall
    include,
    but
    are
    not
    limited
    to
    the
    following:
    (1)
    the
    sections
    of
    the
    Act
    which
    may be violated if the permit were granted;
    (2) the provisions
    of
    the regulations, promulgated under this Act, which may be violated
    if the permit were granted;
    (3) the specific type of
    information,
    if
    any,
    which the Agency deems the applicant fail~d to provide;
    (and
    (4)
    a
    statement
    of
    specific
    reasons why the
    Act and
    the
    regulations might not be met
    if the permit were granted.”
    (~.)
    If the Agency fails to act within the specified time period,
    the
    applicant may deem the permit issued.
    (~.
    The language of section 39(a) clearly requires that the Agency
    specifically
    set
    forth
    the
    applicable
    sections
    of
    the Act
    and
    regulations
    upon
    which
    it
    based
    its
    denial.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111
    1/2,
    par.
    1039(a); City
    of Metropolis
    v.
    IEPA,
    PCB 90—8
    (February
    22,
    1990).)
    The Board’s review of the plain language
    of section
    39(a)
    and the denial statements
    issued in this matter
    supports
    the
    conclusion
    that
    the
    Agency
    has
    failed
    to
    comply
    with
    the requirements of the Act.
    The
    “section
    39(a)
    denial
    statement
    requirements”
    are
    consistent with the Act’s mandate that the Agency issue
    a permit
    upon
    proof
    by
    the applicant
    that its
    facility will
    not cause
    a
    violation
    of the Act or regulations.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111 1/2, par. 1039(a).)
    The intent of section 39(a)
    is to require
    the
    Agency
    to
    issue
    its
    decision
    in
    a
    timely
    manner
    with
    information sufficient for the applicant to determine the bases for
    the
    Agency’s
    determination.
    (City
    of Metropolis v.
    IEPA,
    PCB 90—
    8
    (February
    22,
    1990).)
    The
    sole
    issue
    before
    the
    Board
    in
    a
    permit
    review
    is
    whether
    the
    applicant
    has
    proven
    that
    the
    application,
    as
    submitted
    to
    the
    Agency,
    demonstrates
    that
    no
    violation of the Act and regulations would occur if the permit were
    granted.
    (Joliet Sand
    & Gravel v.
    IPCB,
    163 Ill. App.
    3d 830,
    516
    N.E.2d 955,
    958
    (3d Dist.
    1987).)
    “The burden of proof
    is placed
    upon the applicant,
    (in a permit appeal review before the Board,
    to demonstrate that the reasons
    for denial detailed by the Agency
    are inadequate to support a finding that permit issuance will cause
    a violation of the Act or Board rules.”
    (Technical Services Co~
    Inc.
    v.
    IEPA,
    PCB 81-105 at
    2 (November
    5,
    1981).)
    In order for
    an
    applicant
    to
    adequately
    prepare
    its
    case
    in
    a
    permit
    review
    before
    the
    Board
    the
    applicant
    must
    be
    given
    notice
    of what evidence it needs to establish its case.
    The requirement
    that the Agency provide the applicant with the specific sections
    of
    the
    Act
    and
    regulations
    which
    support
    permit
    denial
    is
    consistent with the statutory framework of the Act which requires
    that the Agency
    render its initial permit decision and the Board
    render
    its
    permit
    review
    decision
    within
    specified
    time
    periods.
    This
    streamlined
    process
    requires
    that
    the
    applicant
    be
    provided
    with
    the
    specific
    information
    upon
    which
    the
    Agency
    based
    its
    permit denial
    so that the applicant may prepare his case with an
    eye toward
    the
    issue
    on review,
    i.e.,
    whether the applicant has
    ii 1—i l(

    7
    demonstrated
    that no
    violation
    of
    the Act
    or
    regulations would
    occur
    if
    the
    permit
    were
    granted.
    Principles of fundamental fairness require that an applicant
    be
    given
    notice
    of
    the
    statutory
    and
    regulatory
    bases
    for
    permit
    denial.
    Fundamental
    fairness
    would
    be
    violated
    if
    the
    Board
    were
    to
    supply
    this
    missing
    information
    on
    its
    own
    initiative
    at
    the
    permit-review level.
    Such action by the Board would be not only
    inconsistent
    with
    the
    plain
    language
    of
    section
    39(a),
    but
    would
    also
    require
    that
    the
    applicant
    anticipate
    what
    the
    Board
    will
    construe
    as
    the
    statutory
    and
    regulatory
    bases
    for
    the
    Agency’s
    permit denial.
    The Act’s permit provisions do not provide
    for a
    system where
    the applicant
    is given the statutory and regulatory
    bases for permit denial after the applicant has argued the merits
    of that denial.
    A
    review
    of
    the
    separation
    of
    functions
    between
    the Agency and
    the
    Board
    in
    the
    permit
    process
    also
    supports
    the
    Board’s
    determination that it is not allowed to proceed to the substantive
    merits of this permit review absent denial statements that comport
    with the requirements of section 39(a).
    (See generally,
    Landfill,
    Inc.
    v.
    PCB,
    74 Ill.2d 541,
    387 N.E,2d 258, 264
    (1978).)
    Pursuant
    to
    section
    4(g)
    of
    the
    Act,
    the
    Agency
    has
    the
    duty
    to
    administer
    the
    permit
    system.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    ill
    1/2,
    par.
    1004(g).)
    Section
    39
    of
    the Act directs
    the
    Agency
    to
    issue
    permits
    upon
    an
    applicant’s
    proof
    that
    the
    proposed
    facility
    will
    comply
    with
    the
    Act
    and
    regulations,
    and
    authorizes
    the
    imposition
    of special permit conditions necessary to accomplish the purposes
    of
    the
    Act.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    ill
    1/2,
    par.
    1039.)
    Therefore,
    it
    is
    the
    Agency
    with
    its
    technical
    staff
    capable of
    performing
    independent
    investigations
    which
    makes
    the
    initial
    determination
    of
    whether
    to
    issue
    a
    permit.
    (Mathers
    v.
    PCB,
    107
    Ill.
    App.
    3d
    729,
    438 N.E.2d 213,218
    (3d Dist.
    1982).)
    Pursuant
    to
    section
    40
    of
    the
    Act,
    the
    Board,
    sitting
    in
    its
    quasi-judicial
    capacity,
    decides
    whether
    the
    applicant
    has
    proven
    that
    the
    application,
    as
    submitted
    to
    the
    Agency,
    demonstrated
    that
    no
    violation
    of
    the
    Act
    would
    occur
    if
    the
    permit
    were
    granted.
    (Joliet Sand
    & Gravel
    v.
    IPCB,
    163
    Ill.
    App.
    3d
    830,
    516 N.E.2d
    955,
    958
    (3d
    Dist.
    1987)
    .)
    However, the Board does not possess the
    power to issue permits.
    Because the Agency has failed to perform its statutory duty,
    the Board cannot perform its duty
    in
    this
    permit
    review.
    Where
    the
    Agency has failed to support its permit denial by setting forth the
    applicable sections of the Act and regulations,
    the
    Board cannot
    step
    in at the review level and supply this missing information.
    The separation
    of duties does not allow the Board
    to examine the
    record
    in
    an
    attempt
    to
    glean
    and
    deduce
    the
    Agency’s
    intent
    in
    denying
    the
    requested
    permit.
    If
    the
    Board
    were
    to
    “plug
    in”
    a
    section
    of
    the
    Act
    or
    regulations
    to
    support
    an
    Agency
    permit
    denial,
    the
    Board
    would
    exceed
    its
    statutory
    authority
    and
    principles of
    fundarnental fairness would be violated.
    Ill-I 17

    8
    Without this information,
    however,
    the Board cannot perform
    its
    function
    of
    determining
    whether
    the applicant
    has met
    its
    burden of demonstrating that no violation of the Act or regulations
    would
    occur
    if
    the permit
    were
    granted.
    Therefore,
    the Board
    concludes that the instant matter must be reinandedto the Agency
    with directions to supply the statutory and regulatory bases for
    those “denial reasons” not so supported.
    The Board’s decision to
    remand this matter to the Agency to cure the deficiencies
    in
    its
    denial
    statements
    is
    consistent
    with
    action
    taken
    by
    the
    Board
    recently
    in
    City
    of
    Metropolis
    v.
    IEPA,
    PCB
    90-8
    (February
    22,
    1990).)
    In City of Metropolis, the City filed a motion for summary
    judgment prior to hearing based upon the Agency’s failure to cite
    specific
    sections
    of
    the Act and regulations
    in
    support
    of
    its
    permit denial statement.
    (PCB 90-8 at 1.)
    The City asserted that
    because
    the
    denial
    letter
    failed
    to
    meet
    the
    requirements
    of
    section
    39(a),
    the
    Agency
    failed
    to
    meet
    its
    90-day
    statutory
    deadline
    for
    taking
    final
    action
    and,
    therefore,
    the
    permit
    should
    issue by operation of law.
    (Id.)
    The City requested that the Board
    grant summary judgment,
    reverse the permit denial
    and direct the
    Agency to
    issue the permit.
    (Id.)
    As
    in the, instant matter,
    the
    Agency argued that its denial statement sufficiently informed the
    City of the reasons for denial and, therefore, complied with 39(a).
    The
    Board
    denied
    the
    City’s
    motion
    for
    summary
    judgement.
    (~.
    at 2.)
    In so doing, the Board rejected the City’s claim that
    the failure
    to cite the Act and regulations rendered the denial
    statement
    null
    and
    void
    for
    purposes
    of
    meeting
    the
    90-day
    statutory deadline and, consequently, the Board concluded that the
    permit would not issue by operation of
    law.
    (~.)
    However, the
    Board
    also
    found that
    “the language of
    s)ection
    39(a)
    is ‘clear
    that
    the
    Agency
    must
    specifically
    set
    forth
    the
    applicable
    sections
    of the Act and regulations upon which it based its denial.”
    (~.)
    Therefore,
    the
    Board
    ordered the Agency
    to provide
    the missing
    information within 14 days of the date of the Board’s order.
    ~
    In
    City
    of
    Metropolis,
    the
    Board
    refused
    to
    order
    the
    issuance
    of
    a
    permit
    by
    operation
    of
    law
    on
    the
    basis
    of
    the
    Agency’s
    failure to comply with section 39(a)
    .
    While
    the
    Agency’s
    denial
    statement
    did
    not
    comply
    with
    section
    39(a),
    such
    failure
    to comply is not tantamount to a failure to act which would trigger
    the issuance
    of
    a permit by
    operation
    of
    law.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    ill
    1/2,
    par.
    1039(a).)
    However, the Board did require
    that
    the
    Agency
    cure
    the
    defect
    in
    its
    denial
    statement
    by
    directing
    the
    Agency
    to
    provide
    the missing
    information.
    The
    Board’s action
    in City of Metropolis recognizes the principles of
    fundamental
    fairness and the requirements
    of the Act by directing
    the Agency to comply with section 39(a)
    enabling the applicant to
    have before
    it the requisite
    39(a)
    information prior to hearing.
    Although
    no motion
    for summary
    judgement
    was
    filed
    in
    the
    instant matter,
    a similar result
    is reached here by remanding the
    ill-i IS

    9
    matter to the Agency to cure its section 39(a)
    deficiencies.
    By
    remanding
    this matter
    to
    the Agency
    within
    the
    statutory
    time
    period, which has been extended by CESI by the filing of a “Waiver
    of Decision Deadline”,
    the Board has complied with
    the provision
    of section
    40(a) (2)
    of the Act requiring
    a Board decision within
    a
    specified
    time
    period.
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111
    1/2,
    par.
    1040(a) (2).)
    The
    Agency
    is
    directed
    to
    amend
    its
    denial
    statements,
    consistent with
    this opinion,
    within
    28 days
    of the
    date of this order.
    Within
    35 days of the Agency’s action,
    CESI
    may
    either
    file
    an
    amended
    petition
    for
    review
    or
    notify
    the
    Board
    and the Agency
    of its intent to
    stand on
    its original petition.
    CESI
    should
    also
    indicate
    when
    filing
    its petition
    whether
    it
    requests
    a
    hearing
    on
    the
    Agency’s
    amended denial
    statements
    or
    additional briefing.
    IT IS SO ORDERED.
    I,
    Dorothy M.
    Gunn,
    Clerk
    of the Illinois Pollution Control
    Board, hereby certify that the above Order was adopted on the
    /LI~Z-
    day of
    ___________________
    ,
    1990 by a vote of
    7-c
    ~
    /
    Dorothy N.
    Günn, Clerk
    Illinois P9ilution Control
    Board
    Ill—itO

    Back to top