ILLINOIS POLLUTION CONTROL BOARD
August
9,
1990
IN
THE MATTER OF:
PETITION OF
THE
CITY OF
)
AS 90-1
JACKSONVILLE FOR ADJUSTED
)
(Adjusted Standard)
STANDARD FROM
35
ILL.
ADM.
CODE SECTION 306.305(b)
OPINION AND ORDER OF THE BOARD
(by J. Anderson):
This matter comes before the Board upon the filing
of
a
petition for an adjusted standard by the City of Jacksonville
(“Jacksonville”).
Jacksonville
seeks relief from
the
disinfection requirement
for post—first
flush flows
that
is
contained in
35
Ill.
Adm.
Code 306.305(b).
PROCEDURAL HISTORY
On January 31,
1990, Jacksonville
filed its petition
for an
adjusted standard and a motion requesting
leave
to file
a limited
number of
copies of
the appendices
to its petition.
On February
22,
1990,
the Board issued an order accepting Jacksonville’s
adjusted standard petition and directing
it
to comply with the
with the publication requirement contained
in 35
Ill.
Adm.
Code
106.711.
The Board also directed the Illinois Environmental
Protection Agency
(“Agency”)
to file a response to
the petition
in accordance with
35
Ill. Adm. Code 106.714.
On March
8,
1990,
the Board issued a second order granting Jacksonville’s motidn
requesting
leave
to file
a limited number of copies of
the
appendices
to its petition.
On March
31,
1990,
the Agency filed
its response, suPporting the adjusted standard.
No hearing
was
held.
BACKGROUND
The City of Jacksonville
is located
in the central part of
Morgan County,
Illinois, approximately
35 miles west
of
Springfield.
The City owns and operates
a wastewater
treatment
plant
(“WWTP”)
that employs approximately
10 full—time employees
and serves approximately 20,083 residents.
The plant processes
a
maximum of
15 million gallons per day and discharges
into
the
Mauvaise Terre Creek
(“Creek”),
a tributary of the Illinois
River.
The
~T?
consists of
an activated sludge process,
including
an.
influent pump station,
grit
removal facilities,
a
primary clarifier,
contact
stabilization biological
trear:r~ent
facilities,
final clarifiers,
chlorination facilities,
aerobic
and anaerobic sludge dicestion
facilities, and grit and
sludoe
storage
tanks.
At present, Jackscnville’s WWTP does
nct have
the
canaciry to handle the combined
se~~eroverflows
(“CSOs)
that
occur
during
heavy
precipitation.
This
results
in
much
of CSOs
being
discharged
to
the
Cree
untreated.
1
1!.-—
13
—2—
In
late 1983, Jacksonville
and the Village of
South
Jacksonville
(“South Jacksonville”) submitted
a Facilities
Planning Area Study to the Agency.*
The study proposed treatment
facilities
that would comply with
the Board’s CSO regulations.
After
the plan was approved, Jacksonville conducted additional
flow monitoring and sampling.
It then submitted
a Basis of
Design
for
c~TWTPand CSO improvements
to the Agency
in July of
1987.
On November
2,
1988,
the Agency approved the final Basis
of Design for
the improvements.
Jacksonville then submitted
the
final design
to the Agency on January
12,
1989.
The Agency
approved the design on May
10,
1989.
Jacksonville has continued
to investigate CSO treatment alternatives,
however, because
the
subsequent construction and annual operating cost estimates
for
the proposed project were much higher than the original estimates
and because Jacksonville lacked
the financial
resources
to
construct the project as originally planned.
Discussions between
Jacksonville and the Agency are ongoing regarding the appropriate
scope of Jacksonville’s CSO treatment
facility improvements.
Concurrent with the above actions, Jacksonville,
South
Jacksonville, and the Agency were negotiating
a consent decree
to
establish enforceable effluent limitations and compliance
schedules
for the WWTP and CSO facility improvements.
Pursuant
to the consent decree, Jacksonville agreed
to improve
its WWTP,
and South Jacksonville agreed
to cease using
its WWTP and
to
connect
its sewer collection system to Jacksonville’s WWTP.
Section VII.C of the consent decree requires Jacksonville
to
design and construct the CSO project according
to
a compliance
schedule set forth therein.
People of the State of
Illinois
v.
~~yof
Jacksonville and Village of South Jacksonville,
No.
89—
CH—2
(Ill.
Cir.
Ct.
7th Car.,
February 22,
1989).
The consent
decree also requires Jacksonville
to reevaluate
the proposed CSO
project
to
reduce costs without compromising environmental
protection by either complying with the Board’s CSO regulations
or
by petitioning
the Board
for
relief
from the regulations.
It
was agreed
that any such evaluation would
not
hinder the progress
of the
CSO
project.
Jacksonville has already constructed several improvements
to
its wastewater
collection system to reduce CSO.
Originally,
the
collection system contained
six CSOs; however,
four
CSOs have
been closed and only
two remain.**
One active CSO
is located at
an abandoned NWTP adjacent
to
the existing Jacksonville
WWTP,
and
*
South Jacksonville
is located directly south
of
Jacksonville
and has
a population of aoprcxinately 3,346 residents.
It
owns
and operates
a WWTP consisting
ci two parallel stabilization
lagoons.
**
An additional CSO exists between
the South Jacksonville and
Jacksonville wastewater
collection systems.
This CSO
will
be
eliminated as part
Of
South Jacksonville’s compliance project
pursuant
to the consent decree.
I
I
1
-
I
—3—
the other active CSO
is located at
an abandoned WWTP on the
Southeast side of Jacksonville.
Untreated wastewater
is
discharged from these
two CSO5
to the Creek when the Jacksonville
WWTP reaches hydraulic capacity.
Jacksonville
is
currently
constructing
the
WWTP improvements
pursuant
to
the
consent
decree
with
the
Agency,
at
a
projected
cost
of ten million dollars.
Jacksonville’s ~WT?
improvements
consist of
the following:
modification of the screen channel and
influent
pump
station,
improvement
of
the
aerated
grit
basin,
construction of
a grit and solids handling system,
an upgrade of
the primary clarifier system, expansion of the aeration capacity,
conversion of
the activated sludge process from contact
stabilization to the complete mix process, installation
of
new
secondary clarifiers,
provision of postaeration when necessary,
replacement of
the primary sludge pumps, construction
of
a new
secondary sludge pump station, construction of
a new anaerobic
digester and control building,
and construction
of buildings
for
laboratory, maintenance, and chlorination control equipment.
As previously stated,
Jacksonville is
in the desicin stage of
its CSO project.
The proposed CSO treatment facility will
collect
the combined flow at
the two existing overflow points and
pump
it
to overflow treatment facilities adjacent
to the
Jacksonville WWTP.
The CSO project,
as currently designed, will
consist of pumping stations,
force mains, first flush storage
tanks, primary clarifiers, and chlorine contact basins.
In
implementing
the proposed CSO improvements,
Jacksonville will
be
providing
full treatment and disinfection
for all dry weather
flows and the first
flush of
a twelve—month recurrence
storm,
as
well as primary treatment
for a volume of CSO equal
to ten times
the average dry weather
flow,
as required by Board regulations.
The only difference
between the proposed CSO project
arid the
Board
regulations
is
that Jacksonville
is proposing not
to
chlorinate
CSO beyond the first
flush.
This petition represents Jacksonville’s decision,
pursuant
to
the consent
decree,
to seek an adjustment
to the CSO
regulations
to eliminate
the disinfection requirements for post—
first flush
flows.
REGULATORY
FRAME;cOREK
The
Board’s
CSO
regulations
are
contained
in
35
Ill.
Adm.
Code
306.
They
were
amended
in
RSl—l7,
51
?CB 383, March
24,
1983.
Section
306.305
provides
as
follows:
Section
306.305
Treatment
oi Overflows and Bypasses
All
combined
sewer
overflows
and
treatment
plant
bypasses
shall
be
given
sufficient
treatment
to
prevent
collution,
or
the vioiation of appl~caolewater
stanciarcs unless an
except ion has been granted by
the Soard pursuant
to Subpart
D.
II
-‘+~
1
‘~‘-‘
•1
Sufficient
treatment shall consist
of the following:
a)
All
dry
weather
flows, and the
first flush of storm
flows
as
determined by
the Agency,
shall
meet
the
applicable
effluent
standards;
and
b)
Additional
flows,
as determined
by the Agency but not
less than ten times average dry weather
flow for the
design year,
shall
receive
a minimum of
primary
treatment and disinfection with adequate
retention time;
and
C)
Flows
in excess of those described in subsection
(b)
shall be
treated,
in whole or
in part,
to the extent
necessary
to
prevent
accumulations
of
sludge deposits,
floating
debris
and
solids
in accordance with
35
Ill.
Adm.
Code
302.203,
and
to
prevent
depression
of
oxygen
levels;
or
d)
Compliance
with
a
treatment
program
authorized
by
the
Board
in
an
exception
granted
pursuant
to
Subpart
D.
As
can
be
seen
in
suhsection(d) above, Subpart
D of
35 Ill.
Adm.
Code
306
allows
a discharger
to file a petition for
exception
from
the
treatment
requirements
contained
in
35
Ill.
Adm.
Code
306.305.
Because
35
Ill.
Adm.
Code
306.373
states that
the
Board
shall
not
accept
a
petition
for
exception
after
January
1,
1986, however, Jacksonville has decided to use the Board’s
adjusted
standard
procedure
pursuant
to
28.1
of
the
Act
to obtain
an
“exception”
from
the
Board’s CSO treatment
requirements.
Section
28.1
of
the
Act
authorizes
the
Board
to
grant
adjusted
standards
if
a
petitioner
carl
justify
such
an
adjustment.
Section
28.1(b)
applies
if
the
level
of
justification
needed
for
an
adjusted
standard
can
be
found
in
the
rule
from
which
the
adjustment
is
sought
(i.e.
the
rule
of
general
applicability).
If
the
rule
of
general
applicability
does
not
contain
a
specific
level
of
justification,
however,
Section
28.1(c)
of
the
Act
sets
forth
the
burden
of
proof
that
a
petitioner
must
meet
in
order
to
obtain
an
adjusted
standard.
While
not
necessarily
quantified,
the
substantive
provisions
in
the
Subpart
D
exception
procedures
do
express, cumulatively,
the
levels
of
justification
required
to
support
an
exception
to
the rules
of general applicability.
While
the deadline has
passed
for the filing of petitions pursuant
to the procedural
mechanisms
in Subpart
D,
the justification requirements contained
in
the rule remain
in effect.
The adjusted standard provisions
of Section
28.1 of
the Act were enacted
after the Board had
created
the
CSO
exception
procedure
and,
in
fact,
reflect
many
aspects of
the CSO exception ~rocedure.
Section 28.1 authorizes
petitions
for what are now called adjusted standards,
including
CSO ‘exceptions”,
and the Board has adopted the required
procedures
that now may be used
in
lieu
of
the discontinued CSO
II
!~.-
1 .‘~O
—5—
exception procedures.
Thus,
because
the level
of justification
here
is contained in the rule of general applicability,
Section
28.1(b)
applies, and Jacksonville quite properly utilized the
substantive requirements
in Subpart
D to justify
its proposed
adjusted standard.
PROPOSED ADJUSTED STANDARD
As previously
stated, Jacksonville requests
that the Board
grant
it
an adjustment
from the disinfection
requirement imposed
by Section 306.305(b).
This adjustment would allow Jacksonville
not
to chlorinate
the post—first flush CSO produced by
a twelve—
month recurrence storm.
In other words,
Jacksonville
is asking
for relief after
it
fully treats and disinfects all dry weather
and first
flush
flows of
a one—year recurrence storm and after
it
provides primary treatment
to additional
flows
of ten times
the
average dry weather
flow.
Jacksonville proposes the following adjusted standard
in its
petition:
The
City
of
Jacksonville
is
granted
an
adjustment
to
the disinfection requirement
of
35
Ill.
Ad.
Code 306.305(b).
This adjustment
is
conditioned
upon
the
construction
of
CSO
facilities
sufficient
to
provide
(1)
full
treatment and disinfection
of
all dry weather
flows
and
the
first
flush
of
a
twelve—month
recurrence
storm
(except
for
November
1
through
April
30
during
which
the
City’s
seasonal
disinfection
exemption
applies),
and
(2)
primary treatment,
but no disinfection,
of
additional
flows of
ten
times
the average dry
weather
flow.
TECHNICAL FEASIBILITY AND ECONOMIC REASONABLENESS
Jacksonville states
that
its proposed adjusted standard
is
primarily
justified
by
the
fact
that
it
is technologically
infeasible
to chlorinate post—first
flush CSOs.
Jacksonville
claims that
there are
four
reasons why the installation of post—
first
flush chlorination facilities
to disinfect
the treated CSO
effluent
is technologically
infeasible.
First, Jacksonville
states that
it
is difficult
to achieve and maintain the required
fecal coliform reduction rates and residual chlorine
levels on a
consistent basis because
the CSO facility effluent fluctuates
significantly
in terms
of
flow,
suspended solids,
and fecal
coliform concentration.
Second,
because CSOs occur
intermittently and vary
in
rate,
volume,
and duration,
Jacksonville argues that
it
is difficult
to accurately adjust the
chlorine flow rate to reduce
fecal coliform levels without
discharging effluent
with
excessive
residual chlorine
concentration.
Third,
Jncksonv~lle
states
that
the
variationn
in
total
suspended solids, organic and
inorganic
comuounds,
and
11
-~
—•
1
-‘~
I
—b
—
fecal coliform concentrations affect the chlorine demand of
the
wastewater and that
the problem
is exacerbated by the fact that
there is
a fifteen minute time delay before the effect of
a
chlorine flow adjustment
is
seen.
Finally, Jacksonville argues
that,
even
if appropriate chlorine levels can
be maintained,
chlorination cannot disinfect many of
the fecal coliforms
entering
the chlorine contact basin because
the primary
clarification process
is not designed to allow all
the solids to
settle out
of the CSO effluent.
As
a result,
the chlorine cannot
penetrate beyond the surface of the remaining suspended solids to
neutralize
the coliform contained therein.
The protected
fecal
coliforms are then released when
the materials disintegrate
downstream.
Jacksonville also claims that the proposed adjusted standard
is economically reasonable.
Jacksonville retained Casler,
Houser
& Hutchison,
Inc., Consulting Engineers
(“CHH”)
to consider
design alternatives
for CSO improvements.
Jacksonville states
that total cost
for full compliance with the Board’s regulations
will be $8,525,000.
The annualized capital
cost and annualized
operations and maintenance costs will be $1,001,722 and $98,000,
respectively.
The eliminatiorl
of disinfection
at
the CSO
facilities,
however, would
save Jacksonville $627,000
in capital
costs and $12,000
in annual operating and maintenance costs,
for
a cost
savings
off approximately eight percent of
the equivalent
annual project
cost.
ENVIRONMENTAL IMPACT
In addition
to arguing
that compliance with the regulations
is
technically infeasible,
costly,
and,
at best, only marginally
beneficial, Jacksonville also maintains that there will be
no
adverse environmental impact resulting from the discharge.
In
reviewing the environmental impact of eliminating disinfection,
CHH analyzed the fecal coliform levels downstream of
the
discharge point and concluded that
the levels exceed the 200 per
100 milliliter
(“ml”)
fecal
coliforni water quality standard of
35
Ill.
Adm.
Code 302.209.
Evidently,
the stream gauging station
downstream from Jacksonville,
at Merritt,
Illinois has recorded
fecal coliform levels
that ranged from
90 per
100 ml
to 140,000
per 100 ml*.
The data represents
the combined impact of
Jacksonville’s CSOs and the direct runoff from non—point sources
because
the above readings were taken when
no other CSO
facilities
were
in service.
When CHH modeled
this data,
it found
that,
at the time
of
the highest
fecal colifor:n levels,
Jacksonville’s
CSOs
contributed
a~proximately
97,000
per
100
ml
and the direct
runoff contributed aDDroximately 43,000
per
100
ml.
CHH
also
discovered
that
Jacksonville’s
fecal
coliform
contribution
will drop over 73,000
per
100
ml
if
the proposed CSO
*
Jacksonville,
in
its
Adjusted
Standard
Petition,
incorrectly
cites
the
fecal coliform levels
as
ranging
from
90
to 140,000
mg,1?.
It
-~--
1
-‘
project
is completed without disinfection beyond the first
flush.
Based on the above information, Jacksonville argues that
although the proposed CSO project’s dry weather and first flush
flows, as well as
the primary treatment
of additional
flows,
will
significantly reduce
fecal
coliform levels,
the chlorination of
the post—first
flush
flows
will
not
create
any
significant
additional
reductions
in light
of
the technical difficulties with
chlorination beyond the first
flush.
Jacksonville
also
states
that
chlorination
may
have
a
negative impact on the Creek because of
the difficulty
to achieve
the required fecal coliform reduction rates and residual chlorine
levels on
a consistent basis.
Evidently,
the inability
to
accurately
adjust
the
chlorine
rate
results
in
either
too
little
chlorine,
making
disinfection
even
more
ineffective,
or
excess
chlorine, which may harm the Creek
by having
a negative effect on
certain
aquatic
wildlife.
Jacksonville
argues
that
elimination
of
the
chlorination
requirement,
on
the other hand,
should
increase
the
health
and
diversity
of
some
fish
populations
in
the
Creek.
As
for
the
hul-nan
health
risks,
Jacksonville
surveyed
forty
local
residents
in
1988
to
determine
how
the
Creek
is
used.
The
results
indicate
that
there
is
little or
no primary contact
use
of
the Creek.
Specifically, the survey indicates that no one
uses the Creek as a source of personal drinking
or non—potable
wash water, and only
a limited number of people use the Creek
for
crop irrigation, livestock watering,
or
for recreational purposes
such as fishing or swimming.
In support of
its contention
that
there
is little primary contact
use
of the Creek, Jacksonville
also completed a Site Access Point Survey which indicates
that
the majority
off the access points adjacent
to the Creek provide
little access to the general public.
Based on the above,
Jacksonville concludes
that chlorination would
not significantly
reduce the health risks of primary contact activities
in the
Creek because even existing CSOs do not appear to have a
significant impact on stream use given
the minimal primary
contact uses especially during
arid after CSOs.
Finally, Jacksonville argues that although
no CSO
improvement can make the Creek
safe
for primary contact use,
the
proposed CSO project, even without chlorination, will
significantly improve
the Creek’s water quality.
In
support
of
this contention, Jacksonville Doints
to the CSO Report that
indicates
that
the proposed CSO project will significantly
decrease
the frequency and total volume of CSOs.
The project
will reduce the average number
of annual overflow events from
21
to
3.9, and the total yearly overflow from 46.2 million gallons
to 764,000 gallons.
The project will also allow natural
processes
to eliminate
unnatural bottom deoosi:s, minimize or
eliminate
odors,
arid curtail me c~scnar-~eor r~oat~ngmater:al
through
the
two CSOs.
11
•‘~
-
-
1
‘+
~
CONSISTENCY WITH FEDERAL LAW
35 Ill.
Adm.
Code 306.305 implements Section
13
of
the
Illinois Environmental Protection Act
(“Act”),
Ill.
Rev.
Stat.
1989,
oh.
111+,
par.
1013,
and the Board’s water quality
standards that were developed pursuant
to the federal Clean Water
Act,
33 U.S.C.
1251 et
sea.
No corresponding federal
regulation
exists.
Moreover,
federal regulations exempt discharges from CSO
systems from federal treatment requirements.
As
a result,
CSO
treatment facilities are regulated by the states rather than the
federal authorities.
Therefore,
this proposal does
not conflict
with federal
law.
AGENCY RECOMMENDATION
The Agency supports Jacksonville’s petition
for an adjusted
standard based on
its view that the chlorination of the excess
flows up
to ten times
the dry weather flow
is
a technically
infeasible and an economically unreasonable method to accomplish
disinfection.
Specifically,
the Agency states that any benefits
derived
from chlorination of
the excess flows beyond the first
flush are substantially outweighed by the significant additional
costs associated with an additional chlorination system.
The
Agency even goes
so far
as to state
that
it has no reason
to
believe chlorination
of the flows beyond the first flush will
produce any quantitative or qualitative benofits or have
a
significant impact
on the fecal coliform levels
in the Creek.
Although the Agency disagrees with Jacksonville’s assertion
that
there
is
no substantial primary contact uses
in certain areas on
the Creek,
it notes
that there
is
no evidence
that
the activities
occur when there are CSOs during heavy precipitation.
The Agency suggests that Jacksonville’s proposed adjusted
standard language be amended, however, because
it conditions
the
adjusted standard on full compliance with
the remaining
provisions of
35
Ill.
Adm.
Code 306.305(b).
The Agency notes
that
such a conditional standard
is meaningless because,
by its
own
terms,
the
adjusted
standard
pertains
only
to
the
disinfection requirement
for post—first
flush flows
and not
to
the other requirements of Section 306.305.
Thus,
the Agency
proposes
that
the following adjusted standard language be used:
The
City
off
Jacksonville
is
granted
an
adjustment
to
the disinfection
requirement
of
35
Ill.P~dm. Code
306.305(b).
This
adjustment
allows
the
City
of
Jacksonville
to
discharge
combined sewer
overflows after
the first
flush
without disinfecting
such flows.
BOARD DISCUSSION
Based on the information before
it,
the Board
finds
that
Jacksonville
has made
a sufficient showing
of economic
unreasonableness,
technical
infeasibility,
and negligible
I l-’---1-’~-’-
—9—
environmental impact
to
justify an adjusted standard.
Specifically, Jacksonville has shown
that the disinfection of
flows beyond the first
flush
is technologically infeasible,
costly, and will have
a marginal environmental benefit,
if not
a
negative impact,
on the
receiving stream.
The technological
difficulties arise from the fact that CSOs occur
intermittently
and vary
in terms of
rate,
volume,
duration,
total suspended
solids,
inorganic and organic compounds, and fecal coliform
concentration.
These factors,
in
turn,
affect the chlorine
demand of the water and make
it difficult
to maintain the
required fecal coliform reduction rates,
residual chlorine
levels, and an accurate chlorine flow rate.
Even
if appropriate
chlorine levels can be maintained,
chlorination cannot disinfect
many of
the
fecal coliforms entering
the chlorine contact basin
because the primary clarification process
is not
designed to allow all the solids
to settle out of the CSO
effluent.
Finally,
the Board notes
that
the accompanying order will
contain the Agency’s proposed adjusted standard language rather
than Jacksonville’s.
As the Agency correctly points out,
it
is
unnecessary for the Board
to specify that its grant
of relief
is
conditioned upon Jacksonville’s full compliance with the
remaining provisions of
35
Ill.
Adm.
Code 306.305(b)
because the
adjusted standard, by its own
terms, pertains only
to the post—
first
flush flow desinfection requirement
in 35
Ill.
Adm.
Code
306.305(b).
This Opinion constitutes the Board’s findings of
fact and
conclusions of
law in this matter.
ORDER
Pursuant
to the authority of Section
28.1 of the
Environmental Protection
Act,
the Board here by adopts
the
following adjusted standard.
This standard becomes effective on
the date of this order.
The City of Jacksonville
is granted an adjustment
to the
disinfection requirement
of
35
Ill.
Adm. Code 306.305(b).
This adjustment allows the City of Jacksonville
to discharge
combined sewer overflows
after
the first
flush without
disinffecting such flows.
Section
41 of
the Illinois Environmental Protection Act,
Ill.
Rev.
Stat.
1989,
ch.
lll~,
ear.
1041,
provides
for appeal
of
final orders
of
the Board within
35 days.
The Rules
off
the
Supreme Court of Illinois establish filing requirements.
IT
IS SO ORDERED.
Board
Member
J.
Dumelle
concurred.
11 -‘--1
-‘~~
I,
Dorothy
M. Gunn, Clerk of
the Illinois Pollution Control
Board,
hereby certif~that the a~pveOpinion and Order was
adopted on the
5~—
day of
~
,
1990,
by
a vote
of
~-~7
.
Dorothy
M.
G/unn, Clerk
Illinois Pc~lutionControl Board
ii 4
14
(~