ILLINOIS POLLUTION CONTROL BOARD
December 21, 2000
IN THE MATTER OF:
)
)
PROPOSED NEW 35 ILL. ADM. CODE 217,
)
R01-9
SUBPART W, THE NOX TRADING
)
(Rulemaking - Air)
PROGRAM FOR ELECTRICAL GENERATING )
UNITS, AND AMENDMENTS TO
)
35 ILL. ADM. CODE 211 AND 217
)
Adopted Rule. Final Order.
OPINION AND ORDER OF THE BOARD (by R.C. Flemal):
By today’s order the Board adopts regulations to implement a nitrogen oxides (NOx)
1
emissions trading program applicable to large fossil fuel electrical generating units (EGUs).
The purpose of the program is to reduce NOx emissions using market-based trading controls.
The program applies to emissions that occur during the period of May 1 to September 30 of
each calendar year beginning in 2004.
Illinois and 21 other states are under order of the United States Environmental
Protection Agency (USEPA) and the Clean Air Act Amendments of 1990 (CAAA) (42 U.S.C.
§§ 7401
et seq.
(1990)) to reduce overall NOx emissions. In pertinent part, Illinois is under
federal directive to cap its emissions from large EGUs at 30,701 tons of NOx per ozone
season. The purpose of this cap is to reduce atmospheric contamination, most specifically for
ozone.
2
The Illinois General Assembly has found that an emissions trading program is a cost-
effective means of reducing NOx emissions (415 ILCS 5/9.9(a)(3) (1998 State Bar Edition,
1999 Supp.)). Further, the Illinois General Assembly has directed the Board to adopt
regulations implementing such a program (415 ILCS 5/9.9(b) (1998 State Bar Edition, 1999
Supp.)). The Board’s action today is in response to that directive.
1
Nitrogen oxides consist of compounds of nitrogen and oxygen. The ratio of oxygen to
nitrogen in these compounds ranges from .5 to 2.5. The term NOx is conventionally used for
this group of compounds.
2
Ozone is produced in the lower levels of the atmosphere when NOx or volatile organic
compounds react with oxygen in the presence of sunlight. Controlling NOx is accordingly a
method for controlling ozone.
2
PROCEDURAL HISTORY
The Illinois Environmental Protection Agency (Agency) filed a proposal in this matter
with the Board on July 11, 2000. The filing was pursuant to Section 28.5 of the
Environmental Protection Act (Act) (415 ILCS 5/28.5 (1998)), which provides for “fast-track”
adoption of certain regulations necessary for compliance with the CAAA.
The Board moved the Agency’s proposal to first notice on July 13, 2000. See
In re
Proposed New 35 Ill. Adm. Code 217, Subpart W, the NOx Trading Program for Electrical
Generating Units, and Amendments to 35 Ill. Adm. Code 211 and 217 (July 13, 2000), R01-9.
First-notice publication occurred in the Illinois Register, Vol. 24, August 4, 2000, at 11473
and 11493.
The Board held public hearings in Springfield, Illinois, on August 28 and 29, 2000, and
in Chicago, Illinois, on September 26, 2000, before Board Hearing Officer Catherine Glenn.
3
The Agency presented various management and technical staff as witnesses. Stakeholder
testimony was presented by Tony Shea on behalf of ABB Energy Ventures and Grand Prairie
Energy (Exh. 30; Tr.2 at 12-22); Joseph N. Darguzas on behalf of EnviroPower, L.L.C.
(Exh. 31; Tr.2 at 23-29); Michael Menne on behalf of Ameren Corporation (Exh. 32; Tr.2 at
30-63, 223-230); Brian Urbaszewski on behalf of the American Lung Association of
Metropolitan Chicago, The Illinois Environmental Council, The Environmental Law and
Policy Center, and The Illinois Public Interest Research Group (Exh. 34; Tr.2 at 77-114);
Lenny DePuis on behalf of Dominion Generation (Exh. 35; Tr.2 at 115-141); J. Derek
Furstenwerth on behalf of Reliant Energy, Incorporated (Exh. 37 and 38; Tr.2 at 147-166);
Scott Miller and Kent Wanninger on behalf of Midwest Generation EME, LLC (Exh. 38; Tr.2
at 167-182); Mary Schoen on behalf of Enron Corporation (Exh. 40; Tr.2 at 184-222); and
Aric Diericx on behalf of Dynegy Midwest Generation (Exh. 41; Tr.2 at 232-239).
The record in this matter closed on October 13, 2000, as provided for at Section 28.5(l)
of the Act. 415 ILCS 5/28.5(l) (1998). Ten public comments were filed: Dynegy Midwest
Generation (PC 1); EnviroPower (PC 2 and PC 8); the Agency (PC 3); Office of Public
Utilities, City of Springfield (PC 4); Ameren Corporation (PC 5); Midwest Generation EME,
LLC (PC 6); Enron Corp (PC 7); Environmental Law and Policy Center (PC 9); and Chicago
Department of Environment (PC 10).
On November 16, 2000, the Board adopted its second notice opinion and order, and
sent this matter to the Joint Committee on Administrative Rules (JCAR) for its consideration.
In re
Proposed New 35 Ill. Adm. Code 217, Subpart W, the NOx Trading Program for
Electrical Generating Units, and Amendments to 35 Ill. Adm. Code 211 and 217 (July 13,
2000), R01-9. On December 12, 2000, JCAR voted a certificate of no objection.
3
The transcripts of the hearing will be cited as “Tr.1 at ___” and “Tr.2 at ___” for the
Springfield and Chicago hearings, respectively. Exhibits admitted at hearing will be cited as
“Exh.___ at ___.”
3
REGULATORY FRAMEWORK
Federal Actions/Requirements
Requirement for Attainment of the Ozone National Ambient Air Quality Standard
The State of Illinois has the primary responsibility under the CAAA for ensuring that
all National Ambient Air Quality Standards (NAAQS) are met in the State. This includes the
NAAQS for ozone. 42 U.S.C. § 7407(a) (1990). Currently there are two areas of the State
that do meet the one-hour ozone NAAQS. These areas are the Chicago and Metro-East ozone
nonattainment areas (NAA).
4
In addition, Illinois is required to control emissions that “contribute significantly to
nonattainment in, or interfere with maintenance [of NAAQS] by, any other State.…” 42
U.S.C. § 7410(a)(2)(D) (1990).
The USEPA has determined that emissions of NOx from EGUs located in the State of
Illinois contribute to nonattainment of the ozone NAAQS in the Chicago and Metro-East
NAAs, as well as in NAAs located outside of the State of Illinois. For this reason, USEPA
requires that Illinois submit a State Implementation Plan (SIP) addressing the emissions of NOx
from EGUs.
NOx SIP Call
On October 27, 1998, the USEPA promulgated a document titled “Finding of
Significant Contribution and Rulemaking for Certain States in the Ozone Transport Assessment
Group Regions for Purpose of Reducing Regional Transport of Ozone.” 63 Fed. Reg. 57,356
(October 27, 1998). This document, and the requirements it imposes on states, is commonly
known as the “NOx SIP Call”.
The NOx SIP Call requires that Illinois, along with other states located east of the
Mississippi, develop plans to limit NOx emissions to a specified budget. The final state-wide
budget for Illinois is 270,560 tons per budget year from several categories of emissions
sources, including large EGUs.
5
65 Fed. Reg. 11,222 (March 2, 2000). If a state fails to
adopt a plan acceptable to USEPA, USEPA will impose its own plan.
4
The terms “Metro-East NAA” and “Chicago NAA” are used in existing Board regulations to
refer to the two ozone nonattaiment areas in Illinois. See 35 Ill. Adm. Code Parts 218 and
219. The same terms will be used herein. It is to be noted, however, that in portions of the
instant record these areas are referred to by the Agency respectively as the “Metro-East/St.
Louis NAA” and the “Lake Michigan NAA.” See Statement of Reasons at 4. The Agency
assures the Board that there is no intended regulatory consequence in this use of alternate
terminology. Tr.1 at 235-6.
5
Proposals for regulations to implement non-EGU portions of the NOx SIP Call are currently
before the Board in regulatory dockets R01-11 (addressing cement kilns) and R01-17. A
4
Illinois is not required under the NOx SIP Call to control any particular source at any
particular level, as long as the State meets its final state-wide budget. As the Agency observes,
however, as a practical matter controls on EGUs are necessary to meet the state-wide budget.
Statement at 27.
6
The NOx SIP Call also suggests, but does not require, that states adopt a “cap and
trade” strategy for the control of NOx emissions from EGUs. However, the Illinois General
Assembly has determined that the Illinois NOx SIP Call is to be met using the “cap and trade”
system as outlined in the NOx SIP Call. 415 ILCS 5/9.9 (1998 State Bar Edition, 1999
Supp.); also see below.
Under the NOx SIP Call, USEPA has determined that the NOx emissions budget (
i.e.
,
cap) for large EGUs in Illinois is 30,701 tons during the ozone season.
7
An emission
allowance is a permit to emit one ton of NOx. Thus, pursuant to the NOx SIP Call, Illinois’
large EGUs are allocated 30,701 allowances annually. The trading rules promulgated by the
various states are to include methods of allocating those allowances among each state’s
emitters, within limits allowed in the NOx SIP Call. Because the emission budgets in a given
state and the total allocations in the aggregate of affected states are capped, the allocations do
not affect the total NOx emissions from EGUs, but only the distribution of the emissions.
Exh. 40 at 2.
Action in Federal Court
The NOx SIP Call was challenged before the U.S. Court of Appeals for the D.C.
Circuit. See Michigan v. EPA, 213 F.3d 663 (D.C. Cir. 2000). That court subsequently
stayed the effective date of the NOx SIP Call rule. Michigan v. EPA, No. 98-1497, (D.C.
Cir. May 25, 1999) (order granting stay). However, on March 3, 2000, the court upheld most
of the NOx SIP Call rule. Michigan v. EPA, 213 F.3d 663 (D.C. Cir. 2000).
8
On
September 20, 2000, and October 20, 2000, a total of three
writs of certiorari
were filed in the
Supreme Court. See Michigan v. EPA, U.S., Nos. 00-445, 00-632, 00-633. As of this date,
the Supreme Court has not indicated whether it intends to hear the appeals. Other NOx-related
court actions are also pending.
9
proposal to impose NOx controls on EGUs prior to the May 31, 2004 effective date of the
instant proposal is also currently before the Board in docket R01-16.
6
The Agency’s Statement of Reasons filed July 11, 2000, will be cited as “Statement at ___.”
7
The ozone season is defined as May 1 through September 30.
8
The court reversed and remanded for further consideration the inclusion of portions of
Missouri and Georgia in the rule, and reversed the inclusion of Wisconsin in the rule because
USEPA had not made a showing that sources in Wisconsin significantly contributed to
nonattainment or interfered with maintenance of the NAAQS in any other State. Neither of
these changes affects today’s proposed action.
9
These include American Trucking Association v. EPA, 175 F.3d 1027 (D.C. Cir. 1999)
involving the 8-hour ozone air quality standard, and Appalachian Power Company v. EPA,
Case No. 99-1268 (D.C. Circuit) involving NOx budget allocations.
5
In light of this on-going litigation, the Board has considered whether actions other than
that taken today would be appropriate. The Board, of course, must base its action on the
current status of the law, and not on any prospective outcome of a court action. Inasmuch as
the Board believes that the law requires that we adopt the instant regulations, we do so today.
We will revisit our decision if a change in the law requires.
State Actions/Requirements
Section 9.9 of the Act (Nitrogen oxides trading system)
The Illinois General Assembly in 1999 adopted new Section 9.9 of the Act titled
“Nitrogen oxides trading system.”
10
415 ILCS 5/9.9 (1998 State Bar Edition, 1999 Supp.). In
Section 9.9 the General Assembly finds “that reducing emissions of NOx in the State helps the
State to meet the national ambient air quality standard for ozone” (415 ILCS 5/9.9(a)(2) (1998
State Bar Edition, 1999 Supp.)) and “that emissions trading is a cost effective means of
obtaining reductions of NOx emissions.” 415 ILCS 5/9.9(a)(3) (1998 State Bar Edition, 1999
Supp.). Further, Section 9.9 directs that “the Board shall adopt regulations to implement an
interstate NOx trading program.” 415 ILCS 5/9.9(b) (1998 State Bar Edition, 1999 Supp.).
Section 9.9 also requires that the Illinois NOx emissions trading program be “as
provided for in 40 CFR Part 96.” 415 ILCS 5/9.9(b) (1998 State Bar Edition, 1999 Supp.).
Part 96 is the portion of the NOx SIP Call, which contains the federal NOx emissions trading
program. Tr.1 at 255-258.
Section 9.9(d) further directs the Board to address specific issues in adopting
regulations to implement the NOx trading program. These issues are that the Board shall:
1.
assure that the economic impact and technical feasibility of NOx
emissions reductions under the NOx Trading Program are considered
relative to the traditional regulatory control requirements in the State for
EGUs and non-EGUs;
2.
provide that emission units, as defined in Section 39.5(1) of this Act,
may opt into the NOx Trading Program;
3.
provide for voluntary reductions of NOx emissions from emission units,
as defined in Section 39.5(1) of this Act, not otherwise included under
paragraph (c) or (d)(2) of this Section to provide additional allowances to
EGUs and non-EGUs to be allocated by the Agency. The regulations
shall further provide that such voluntary reductions are verifiable,
quantifiable, permanent, and federally enforceable;
10
On August 19, 1999, Governor Ryan signed Section 9.9 into law as Pub. Act 91-0631.
6
4.
provide that the Agency allocate to non-EGUs allowances that are
designated in the rule, unless the Agency has been directed to transfer
the allocations to another unit subject to the requirements of the NOx
Trading Program, and that upon shutdown of a non-EGU, the unit may
transfer or sell the NOx allowances that are allocated to such unit; and
5.
provide that the Agency shall set aside annually a number of allowances,
not to exceed 5% of the total EGU trading budget, to be made available
to new EGUs.
A.
Those EGUs that commence commercial operation, as defined in
40 CFR Section 96.2, at a time that is more than half way
through the control period in 2002 shall return to the Agency any
allowances that were issued to it by the Agency and were not
used for compliance in 2003.
B.
The Agency may charge EGUs that commence commercial
operation, as defined in 40 CFR Section 96.2, on or after
January 1, 2003, for the allowances it issues to them.
415 ILCS 5/9.9(d) (1998 State Bar Edition, 1999 Supp.).
The Board has reviewed today’s regulations, and finds that they comply with the
requirements of Section 9.9(d).
BACKGROUND
Proposal Development
Today’s action is the most recent in a long series of actions designed to achieve
compliance with CAAA regulations in the State of Illinois. Since the 1980s, Illinois has
pursued strategies to control ground-level ozone, and has had significant, but not complete,
success as measured by decreases in the number of recorded violations of the ozone one-hour
NAAQS. Tr.1 at 40.
Beginning in 1998, following issuance of the NOx SIP Call, the Agency commenced
regular meetings with persons interested in development of the instant rules. Members of the
affected industries and environmental groups were included in the meetings. Statement at 36-
37.
Scope and Affected Facilities
The geographic region subject to the NOx Trading Program for EGUs is the entire
State of Illinois. There are approximately 100 existing EGUs within this region, all of which
are expected to be affected by the proposed regulations. Statement at 20. The regulations also
7
will affect any new EGUs (
i.e.
, those that commenced operation on or after January 1, 1995)
that serve a generator greater than 25 megawatts, or any unit with a maximum design heat
input that is greater than 250 mmbtu/hr and that has the potential to use more than 50% of the
“potential electrical output capacity.” See Section 217.754.
Implementation Date
At first notice the date for full implementation of the NOx trading program was May 1,
2003. This date was part of the original NOx SIP Call and is included in Section 9.9 of the
Act. However, on August 30, 2000, the D.C. Circuit Court of Appeals issued an order
extending the deadline for full implementation to May 31, 2004. See Michigan v. EPA, No.
98-1497 (D.C. Cir. 2000).
At hearing the Agency filed a motion to amend its proposal to incorporate the May 31,
2004 implementation date ordered by the Court of Appeals. See Exh. 33. In its second-notice
opinion and order the Board granted that motion, and amended the proposal accordingly.
11
NOx TRADING PROGRAM
Mandatory Provisions
Much of the NOx trading program adopted today is mandatory, in that Section 9.9 of
the Act requires a trading program compatible with 40 C.F.R. Part 96. States that participate
in the trading program of Part 96 have limited discretion in adopting their programs. Part 96
limits state discretion to assure that the principal parts of the NOx trading program will be
standard in all affected states. Exh. 25 at 5. In today’s regulations these mandatory provisions
are effectuated via incorporation by reference. See Section 217.104 and 217.754(a).
Among the mandatory provisions are provisions relating to management of NOx
accounts, including the structure of accounts, account flow control, banking of allowances, and
the responsibilities of account representatives. The mandatory provisions also included
elements related to monitoring and reporting of NOx emissions.
The Board will not review here in further detail the mandatory provisions of the NOx
trading program. The Board directs interested persons to the NOx SIP Call for specific
details.
Optional Provisions
Part 96 provides for a small amount of flexibility in the tailoring of individual state
programs. Today’s regulations employ that flexibility in four areas, as follows:
11
In re
Proposed New 35 Ill. Adm. Code 217, Subpart W, the NOx Trading Program for
Electrical Generating Units, and Amendments to 35 Ill. Adm. Code 211 and 217
(November 16, 2000), R01-9, p. 7.
8
1.
whether to allow low-emitting NOx emission units to opt out of the trading
system;
2.
whether to allow smaller emission units to opt in to the federal trading program;
3.
whether to allow credit for early reduction emissions; and
4.
various details for allocating the State’s total NOx allowances among the State’s
EGUs.
Each of these issues is discussed below.
“Opt-Out” Provision
Part 96 provides that a state program may allow low-emitting units to opt out of the
trading program, provided several conditions are met. This provision is incorporated into the
instant regulations at Section 217.754(c). The “opt-out” provision is limited to units that are
fueled by natural gas or fuel oil and that have the potential to emit 25 tons or less of NOx
during the May-September control period. There are additional requirements regarding
operating hours, methods of emissions calculations, record keeping, and reporting. See
Section 217.754(c)(1)(C)-(F). “Opt-out” units are otherwise exempted from the rest of the
NOx trading provisions.
“Opt-In” Provision
Part 96 also provides that a state program may allow certain emissions sources that are
not otherwise included into the trading program to elect to participate in the trading program.
The “opt-in” provisions are included in the instant regulations at Sections 217.774 to 217.782.
The provisions are limited to operating fossil fuel-fired stationary boilers, combustion turbines,
or combined cycle systems. See Section 217.774(a). “Opt-in” provisions in state law must
comport with the parallel provisions in Part 96, and they so do in the instant regulations.
“Opt-in” units must also comply with the NOx SIP Call regulations of 40 C.F.R. Part 75.
Early Emission Reduction Credit (ERC)
The NOx SIP Call includes a Compliance Supplement Pool consisting of allowances
available to states’ emission sources in the first years of the trading program. States have some
discretion in how these allowances may be distributed. The Agency has recommended that
these allowances be used to bankroll an Early Emission Reduction Credit (ERC). See Section
217.770. The Board agrees.
EGUs earn allowances from the ERC pool by reducing emissions earlier than otherwise
required. The NOx SIP Call currently provides that early reductions must occur in the 2001
and 2002 control periods, and that the allowances so earned must be used in the 2003 and 2004
9
control periods. 63 Fed. Reg. 57,529 – 57,530 (October 27, 1998). However, in its Motion
to Amend (Exh. 33), the Agency proposed including 2003, in addition to 2001 and 2002, as a
control period year in which the early reductions must occur. Exh. 33 at 4. The Agency
explains that the D.C. Circuit Court of Appeals’ order on August 30, 2000, did not address
whether the dates regarding the control periods for ERCs should be adjusted. However, the
Agency’s preliminary contact with USEPA suggests that USEPA, in response to the
August 30, 2000 ruling, will allow ERCs to be earned in the 2003 control period. The Board
has accordingly incorporated this concept in Section 217.770.
The Agency also noted in its Motion to Amend that the USEPA has preliminarily
indicated that ERCs may only be used in the 2004 control period. Exh. 33 at 4. The Agency
has accordingly recommended that the proposal be modified to allow ERCs to be used not only
in 2004, but also in any years authorized by USEPA. PC 3 at 15. The Board today adopts
that provision. See Section 217.770.
Allocation of NOx Allowances
“Fixed/Flex” Allocation
The NOx SIP Call allows State latitude to determine how to allocate allowances among
emitters. Pursuant to the USEPA emissions budget for Illinois, NOx emissions from all
Illinois EGUs are capped at 30,701 tons per ozone season. Tr.1 at 100. This is the total
Illinois NOx allocation for large EGUs. Tr.1 at 100. It is much less than current emissions.
12
Thus, any allocation system by necessity requires existing EGUs to significantly decrease their
emissions. It also requires that new EGUs use “clean” technologies.
The Agency negotiated with affected sources to try to create a balanced approach to
allocating the limited number of allowances. PC 3 at 8. The Agency’s approach, which the
Board adopts today, is termed a “fixed/flex” allocation scheme. Initially, the large percentage
of allowances is allocated to existing emitters based on historical emission rates. The list of
existing emitters is presented at Part 217.Appendix F. As time progresses, the allocations
“flex” to accommodate changes in the identity and mix of EGUs as older EGUs are phased out
or modified, and as new EGUs come on line as replacements or additions to the total EGU
population. See Section 217.762.
In the years 2004, 2005, and 2006, the sources listed in proposed Part 217.Appendix F
will receive the number of allowances listed in column 7 of Appendix F. The total allocations
in column 7 amount to 95% of the 30,701 total allowances. The remaining 5% are set aside
for new EGUs that are not included in Part 217.Appendix F.
For the years 2007 and 2008, the EGUs in Appendix F will receive approximately 80%
of the allowances specified in column 7. See 217.Appendix F, column 8. Additionally, 2%
12
On average, existing EGUs in Illinois will have to reduce emissions about 74%. Exh. 27 at
6.
10
will be set aside for new EGUs, and the remaining allowances will be reserved for flexible
allocation based on the formula in Section 217.762. At this stage some of the EGUs that were
“new” for the purposes of the earlier allocations will begin to quality for and draw their
allocations from the “flex” portion of the NOx budget.
In 2009 and 2010, the procedures above will be repeated, except that both the “fixed”
and “flex” portions of the allocations are 50% of the budget, reserving 2% for a new source
set-aside. Starting with 2011, allowances will be allocated to all existing EGUs (those in
Appendix F and those that rolled into the flex portion) on the basis of average control period
heat input.
New Source Set-Aside
Section 9.9(d)(5) of the Act provides that the NOx trading program shall include a
provision that the Agency “set aside annually a number of allowances, not to exceed 5% of the
total EGU trading budget, to be made available to new EGUs.” See 415 ILCS 5/9.9(d)(5)
(1998 State Bar Edition, 1999 Supp.). Today’s regulations incorporate this provision at
Section 217.768, “New Source Set-Asides for ‘New’ Budget EGUs.” Among other things, the
provision allows that each new source set-aside will be allocated allowances equal to 5% of the
EGU trading budget in 2004, 2005, and 2006. See Section 217.768(c)(1). Beginning in 2007,
new source set-asides will be allocated allowances equal to 2% of the 2007 trading budget.
See Section 217.768(c)(2).
The NOx SIP Call also contains a 5% set-aside provision for the first three control
seasons, followed by a 2% provision for the control periods thereafter. 63 Fed. Reg. 57,471.
However, USEPA left it up to individual states’ discretion whether to adopt a set-aside
provision, including the size of the set-aside. 63 Fed. Reg. 57,471.
Both at hearing and in public comment, some representatives of new EGUs expressed
concern that a new source set-aside of 5%, which later decreases to 2%, is insufficient for their
needs. Tr.2 at 14; PC 8 at 5-8; PC 10 at 3. Some participants recommend that the Board
maintain the statutory maximum of 5%. PC 8 at 9; Tr.2 at 16, 157. Some participants also
suggest the Agency seek legislative approval to increase the 5% maximum. Tr.2 at 16.
At hearing, the Agency explained the rationale for decreasing the 5% maximum to 2%
in 2007. The Agency first noted that those EGUs that are eligible for the new source set-aside
allocation are those EGUs that began operation on or after January 1, 1995. Tr.1 at 84.
Therefore, when the implementation date occurs (May 31, 2004), roughly a decade’s worth of
new EGUs will get their allocations from this set-aside. Tr.2 at 84. However, the demand for
allowances from the set-aside will begin to decrease as of the year 2007, when the new EGUs
start drawing allowances from the flex portion of the NOx budget. Thus, beginning in 2007,
when the set-aside is set at the 2% maximum, the Agency anticipates that there will be fewer
new sources that apply for the allowances from the set-aside. Tr.1 at 84. The Agency also
noted in its prefiled testimony that the new source set-aside allocations follow the levels
suggested in the NOx SIP Call. Exh. 25 at 15.
11
Additionally, some participants argue that the set-aside provision unduly favors the
existing EGUs over the new EGUs because the existing EGUs are guaranteed the “fixed”
allocations, and the new EGUs can only access the allocations available in the new source set-
aside; they contend that these are not enough to meet the projected demand. Tr.2 at 153-154;
PC 8 at 8-12. However, existing EGUs note that even with the fixed allocations, they will
incur great costs to comply with the new Subpart W. PC 5 at 4. Namely, they will be forced
to achieve great control levels due to the projected oversubscription in allowances. PC 5 at 4.
Other participants contend that the Agency’s allocation system is equitable, and should
be adopted by the Board,
e.g.
, PC 5 at 3, PC 6 at 3-4. They note that the Agency developed
the proposal only after extensive efforts to reach out to all interested parties, and that no
stakeholder was hindered from presenting its point of view. PC 5 at 3.
The Board concludes that the allocation system proposed by the Agency is fair and
reasonable. Additionally, the 5% change to 2% is consistent with the USEPA’s suggested
set-aside provision. Accordingly, the Board retains these provisions in today’s regulations.
Energy Efficiency/Renewable Energy Set-Aside
The American Lung Association
et al.
(Exh. 34 at 6-7; Tr.2 at 91-93), the
Environmental Law and Policy Center (PC 9), the Chicago Department of Environment (PC
10), and Enron Corp. (PC 7), each recommended that the Board provide a set-aside for energy
efficiency and renewable energy measures.
The Board believes that measures to increase energy efficiency are admirable and
needed. Similarly, the Board believes that reliable, cost-effective renewable energy needs to
be aggressively developed. However, the Board is not convinced that the set-aside provision is
an appropriate or productive method to achieve these ends, particularly in light of the limited
number of emission allowances available in Illinois.
Charges for Allowances
Section 217.768(k) contains a provision that imposes a market-rate fee on allowances
awarded to EGUs that start operations after January 1, 2004. Several participants have
contended that this provision should be deleted or significantly modified,
e.g.,
Tr.2 at 17-18;
PC 8 at 17.
The Agency notes that charging for allowances is allowed under Section 9.9. PC 3 at
13-14. Additionally, Section 9.9(i)(2) of the Act authorizes the Agency to disburse the
proceeds of the NOx allowances sales pro-rata to the EGUs that were not given allowances
from the new source set-aside. See 415 ILCS 5/9.9(i)(2) (1998 State Bar Edition, 1999
Supp.). The Board appreciates the participants’ concerns regarding the fees charged for the
allowances for the new source set-aside allowances. However, the Board will not deviate from
the Act’s provisions in this matter.
12
Upon review of all the comments, the Board agrees with the basic system proposed by
the Agency, and adopts it today for second notice. Today’s proposal incorporates minor
technical changes to the rules.
ECONOMIC AND TECHNICAL CONSIDERATION
Section 27(a) of the Act requires that in promulgating regulations, the Board “shall take
into account . . . the technical feasibility and economic reasonableness of measuring or
reducing the particular type of pollution.” 415 ILCS 5/27(a) (1998). Exh. 27 at 3 & 9-10;
Tr.1 at 105-106 and 249-252; Tr.2 at 36; Exh. 32 at 5. The Agency used the information
contained in the Alternative Control Techniques (ACT) documents
13
published by the USEPA
as background information. Further, the Agency relied on the information contained in the
USEPA’s Regulatory Impact Analysis for the NOx SIP Call (63 Fed. Reg. 57,356), the
proposed Federal Implementation Plan (FIP) (63 Fed. Reg. 56,394), and USEPA’s proposed
findings on various petitions filed under Section 126 of the CAAA (65 Fed. Reg. 2,674) to
support its proposal. Exh. 27 and PC 3 at 19-20.
The USEPA’s analysis of the cost impact of the NOx SIP Call on large EGUs involved
the determination of the “cost effectiveness,” which is measured as the cost in dollars per ton
of NOx reduced, of various alternative NOx control levels. USEPA chose a NOx control level
of 0.15 lbs. per mmbtu to be highly cost effective for reducing emissions from large EGUs.
63 Fed. Reg. 57,399 – 57,402. Based on this control level, the USEPA determined the
average cost effectiveness for NOx control on a region wide (23 jurisdictions) basis to be
$1,468 per ton of NOx. USEPA notes that for large EGUs the average cost effectiveness of
$1,468 per ton of NOx is consistent with the range of cost effectiveness for various control
measures. 63 Fed. Reg. 57,401.
Although the Agency relies on the USEPA’s cost analysis to support its proposal, the
Agency performed its own cost impact analysis. The Agency determined the cost effectiveness
to be $1,486 per ton of NOx. Exh. 27 at 10. In addition, the U.S. Department of Energy also
made a separate analysis of the cost impact of the NOx SIP Call and found the cost
effectiveness to be $1,460 per ton of NOx. Exh. 27 at 10. All three analyses included trading
in their assessments.
Ameren and Dynegy Midwest Generation expressed concerns regarding the Agency’s
compliance cost estimates. They assert that the costs of NOx control for their units would be
much higher than the USEPA estimate. Ameren testified that it would cost Ameren $130
million ($8,784 per ton of NOx) to come into compliance with the proposed regulation. Tr.2
at 36 and Exh. 32 at 5. They also noted that the incremental cost of reducing NOx emissions
from a control level of 0.25 lbs per mmbtu (0.25 rule) to the proposed control level of 0.15 lbs
13
USEPA has published two ACT documents concerning control of NOx emissions from
utility boilers and gas turbines. These documents contain detailed description of the sources of
NOx emissions, various emissions control techniques and their costs.
13
per mmbtu would be $100 million. Dynegy Midwest Generation also stated that the Agency
has underestimated the compliance cost. They noted that the incremental cost of reducing NOx
from a control level of 0.25 lbs per mmbtu to the proposed control level of 0.15 lbs per mmbtu
for Dynegy Midwest Generation would be $7,339 per ton of NOx over a five-year period or
$4,582 per ton of NOx over a ten-year period. Exh. 41 at 6-7.
The Board believes that a principle factor that should be considered in determining the
economic impact of the proposed regulations is the flexibility afforded to the affected entities to
participate in a trading program to determine their compliance alternatives. As the Agency
notes, the USEPA determined that NOx control level of 0.15 lbs per mmbtu to be highly cost
effective in the realm of a trading program. The instant regulations do not require all affected
units to reduce NOx emissions by using control options. An affected unit may comply with the
NOx emissions limitation either by using control options or by purchasing the necessary
allowances to cover its emissions. Each affected source has to make a determination as to the
compliance option based on a number of factors such as the type of boiler, existing control
technology, cost of additional control, amount of emissions reductions, etc.
The Board recognizes that the cost of emissions control varies from unit to unit, as
illustrated in Ameren’s comments. PC 5, Attachment 2. Although the cost of achieving
compliance for a specific unit may exceed the average cost effectiveness determined by
USEPA, the Board believes that the economic impact of the proposed regulations must be
evaluated in terms of the overall cost imposed by the trading program. Regarding the affected
sources’ cost estimates, the Board agrees with the Agency that the use of incremental costs
between two levels of NOx control to show that the cost effectiveness of NOx control is
significantly higher is inappropriate. Any comparison of compliance costs of two different
control levels should consider differential costs between the two levels with respect to the base
line emissions. PC 3 at 21. Moreover, the Board notes that the evaluation of even the
differential costs is not relevant in this proceeding since the instant regulations address only
one NOx control level (0.15 lbs per mmbtu) which the USEPA has determined to be highly
cost effective.
In light of the above, the Board finds that the USEPA’s determination of average cost
effectiveness of $1,468 per ton of NOx for large EGUs to be reasonable. Further, the Board
finds that the proposed trading program provides flexibility to the affected sources to achieve
compliance at lower costs. The Board also notes that the average cost effectiveness of NOx
control for large EGUs is similar to the cost effectiveness of various VOC control measures
adopted by this Board pursuant to the CAAA. In addition, the Board finds that technically
feasible control technologies are available for reducing NOx emissions from large EGUs.
CONCLUSION
Pursuant to federal law, large EGUs in Illinois are required to significantly reduce
emissions of NOx during the ozone season. Faced with this circumstance, Illinois has sought,
within the parameters allowed us by federal and State law, to find an equitable and economic
method of bringing about that reduction.
14
The Board appreciates the extensive effort undertaken by various stakeholders in this
matter to inform both the Agency and us regarding their interests. We believe that the instant
regulations strike an appropriate balance among these various interests, and for this reason we
today adopt them.
ORDER
The Clerk is directed to cause publication in the
Illinois Register
of the following
amendments to the Board’s air regulations at 35 Ill. Adm. Cope 211 and 217.
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE B: AIR POLLUTION
CHAPTER I: POLLUTION CONTROL BOARD
SUBCHAPTER c: EMISSION STANDARDS AND LIMITATIONS FOR
STATIONARY SOURCES
PART 211
DEFINITIONS AND GENERAL PROVISIONS
SUBPART A: GENERAL PROVISIONS
Section
211.101
Incorporations by Reference
211.102
Abbreviations and Conversion Factors
SUBPART B: DEFINITIONS
Section
211.121
Other Definitions
211.122
Definitions (Repealed)
211.130
Accelacota
211.150
Accumulator
211.170
Acid Gases
211.210
Actual Heat Input
211.230
Adhesive
211.240
Adhesion Promoter
211.250
Aeration
211.270
Aerosol Can Filling Line
211.290
Afterburner
211.310
Air Contaminant
211.330
Air Dried Coatings
211.350
Air Oxidation Process
211.370
Air Pollutant
211.390
Air Pollution
211.410
Air Pollution Control Equipment
15
211.430
Air Suspension Coater/Dryer
211.450
Airless Spray
211.470
Air Assisted Airless Spray
211.474
Alcohol
211.479
Allowance
211.484
Animal
211.485
Animal Pathological Waste
211.490
Annual Grain Through-Put
211.495
Anti-Glare/Safety Coating
211.510
Application Area
211.530
Architectural Coating
211.550
As Applied
211.560
As-Applied Fountain Solution
211.570
Asphalt
211.590
Asphalt Prime Coat
211.610
Automobile
211.630
Automobile or Light-Duty Truck Assembly Source or Automobile or Light-
Duty Truck Manufacturing Plant
211.650
Automobile or Light-Duty Truck Refinishing
211.660
Automotive/Transportation Plastic Parts
211.670
Baked Coatings
211.680
Bakery Oven
211.685
Basecoat/Clearcoat System
211.690
Batch Loading
211.695
Batch Operation
211.696
Batch Process Train
211.710
Bead-Dipping
211.730
Binders
211.750
British Thermal Unit
211.770
Brush or Wipe Coating
211.790
Bulk Gasoline Plant
211.810
Bulk Gasoline Terminal
211.820
Business Machine Plastic Parts
211.830
Can
211.850
Can Coating
211.870
Can Coating Line
211.890
Capture
211.910
Capture Device
211.930
Capture Efficiency
211.950
Capture System
211.970
Certified Investigation
211.980
Chemical Manufacturing Process Unit
211.990
Choke Loading
211.1010
Clean Air Act
211.1050
Cleaning and Separating Operation
16
211.1070
Cleaning Materials
211.1090
Clear Coating
211.1110
Clear Topcoat
211.1130
Closed Purge System
211.1150
Closed Vent System
211.1170
Coal Refuse
211.1190
Coating
211.1210
Coating Applicator
211.1230
Coating Line
211.1250
Coating Plant
211.1270
Coil Coating
211.1290
Coil Coating Line
211.1310
Cold Cleaning
211.1312
Combined Cycle System
211.1316
Combustion Turbine
211.1320
Commence Commercial Operation
211.1324
Commence Operation
211.1328
Common Stack
211.1330
Complete Combustion
211.1350
Component
211.1370
Concrete Curing Compounds
211.1390
Concentrated Nitric Acid Manufacturing Process
211.1410
Condensate
211.1430
Condensible PM-10
211.1465
Continuous Automatic Stoking
211.1467
Continuous Coater
211.1470
Continuous Process
211.1490
Control Device
211.1510
Control Device Efficiency
211.1515
Control Period
211.1520
Conventional Air Spray
211.1530
Conventional Soybean Crushing Source
211.1550
Conveyorized Degreasing
211.1570
Crude Oil
211.1590
Crude Oil Gathering
211.1610
Crushing
211.1630
Custody Transfer
211.1650
Cutback Asphalt
211.1670
Daily-Weighted Average VOM Content
211.1690
Day
211.1710
Degreaser
211.1730
Delivery Vessel
211.1750
Dip Coating
211.1770
Distillate Fuel Oil
211.1780
Distillation Unit
17
211.1790
Drum
211.1810
Dry Cleaning Operation or Dry Cleaning Facility
211.1830
Dump-Pit Area
211.1850
Effective Grate Area
211.1870
Effluent Water Separator
211.1875
Elastomeric Materials
211.1880
Electromagnetic Interference/Radio Frequency (EMI/RFI) Shielding Coatings
211.1885
Electronic Component
211.1890
Electrostatic Bell or Disc Spray
211.1900
Electrostatic Prep Coat
211.1910
Electrostatic Spray
211.1920
Emergency or Standby Unit
211.1930
Emission Rate
211.1950
Emission Unit
211.1970
Enamel
211.1990
Enclose
211.2010
End Sealing Compound Coat
211.2030
Enhanced Under-the-Cup Fill
211.2050
Ethanol Blend Gasoline
211.2070
Excess Air
211.2080
Excess Emissions
211.2090
Excessive Release
211.2110
Existing Grain-Drying Operation (Repealed)
211.2130
Existing Grain-Handling Operation (Repealed)
211.2150
Exterior Base Coat
211.2170
Exterior End Coat
211.2190
External Floating Roof
211.2210
Extreme Performance Coating
211.2230
Fabric Coating
211.2250
Fabric Coating Line
211.2270
Federally Enforceable Limitations and Conditions
211.2285
Feed Mill
211.2290
Fermentation Time
211.2300
Fill
211.2310
Final Repair Coat
211.2330
Firebox
211.2350
Fixed-Roof Tank
211.2360
Flexible Coating
211.2365
Flexible Operating Unit
211.2370
Flexographic Printing
211.2390
Flexographic Printing Line
211.2410
Floating Roof
211.2420
Fossil Fuel
211.2425
Fossil Fuel-Fired
211.2430
Fountain Solution
18
211.2450
Freeboard Height
211.2470
Fuel Combustion Emission Unit or Fuel Combustion Emission Source
211.2490
Fugitive Particulate Matter
211.2510
Full Operating Flowrate
211.2530
Gas Service
211.2550
Gas/Gas Method
211.2570
Gasoline
211.2590
Gasoline Dispensing Operation or Gasoline Dispensing Facility
211.2620
Generator
211.2610
Gel Coat
211.2630
Gloss Reducers
211.2650
Grain
211.2670
Grain-Drying Operation
211.2690
Grain-Handling and Conditioning Operation
211.2710
Grain-Handling Operation
211.2730
Green-Tire Spraying
211.2750
Green Tires
211.2770
Gross Heating Value
211.2790
Gross Vehicle Weight Rating
211.2810
Heated Airless Spray
211.2815
Heat Input
211.2820
Heat Input Rate
211.2830
Heatset
211.2850
Heatset Web Offset Lithographic Printing Line
211.2870
Heavy Liquid
211.2890
Heavy Metals
211.2910
Heavy Off-Highway Vehicle Products
211.2930
Heavy Off-Highway Vehicle Products Coating
211.2950
Heavy Off-Highway Vehicle Products Coating Line
211.2970
High Temperature Aluminum Coating
211.2990
High Volume Low Pressure (HVLP) Spray
211.3010
Hood
211.3030
Hot Well
211.3050
Housekeeping Practices
211.3070
Incinerator
211.3090
Indirect Heat Transfer
211.3110
Ink
211.3130
In-Process Tank
211.3150
In-Situ Sampling Systems
211.3170
Interior Body Spray Coat
211.3190
Internal-Floating Roof
211.3210
Internal Transferring Area
211.3230
Lacquers
211.3250
Large Appliance
211.3270
Large Appliance Coating
19
211.3290
Large Appliance Coating Line
211.3310
Light Liquid
211.3330
Light-Duty Truck
211.3350
Light Oil
211.3370
Liquid/Gas Method
211.3390
Liquid-Mounted Seal
211.3410
Liquid Service
211.3430
Liquids Dripping
211.3450
Lithographic Printing Line
211.3470
Load-Out Area
211.3480
Loading Event
211.3490
Low Solvent Coating
211.3500
Lubricating Oil
211.3510
Magnet Wire
211.3530
Magnet Wire Coating
211.3550
Magnet Wire Coating Line
211.3570
Major Dump Pit
211.3590
Major Metropolitan Area (MMA)
211.3610
Major Population Area (MPA)
211.3620
Manually Operated Equipment
211.3630
Manufacturing Process
211.3650
Marine Terminal
211.3660
Marine Vessel
211.3670
Material Recovery Section
211.3690
Maximum Theoretical Emissions
211.3695
Maximum True Vapor Pressure
211.3710
Metal Furniture
211.3730
Metal Furniture Coating
211.3750
Metal Furniture Coating Line
211.3770
Metallic Shoe-Type Seal
211.3790
Miscellaneous Fabricated Product Manufacturing Process
211.3810
Miscellaneous Formulation Manufacturing Process
211.3830
Miscellaneous Metal Parts and Products
211.3850
Miscellaneous Metal Parts and Products Coating
211.3870
Miscellaneous Metal Parts or Products Coating Line
211.3890
Miscellaneous Organic Chemical Manufacturing Process
211.3910
Mixing Operation
211.3915
Mobile Equipment
211.3930
Monitor
211.3950
Monomer
211.3960
Motor Vehicles
211.3965
Motor Vehicle Refinishing
211.3970
Multiple Package Coating
211.3980
Nameplate Capacity
211.3990
New Grain-Drying Operation (Repealed)
20
211.4010
New Grain-Handling Operation (Repealed)
211.4030
No Detectable Volatile Organic Material Emissions
211.4050
Non-Contact Process Water Cooling Tower
211.4055
Non-Flexible Coating
211.4065
Non-Heatset
211.4070
Offset
211.4090
One Hundred Percent Acid
211.4110
One-Turn Storage Space
211.4130
Opacity
211.4150
Opaque Stains
211.4170
Open Top Vapor Degreasing
211.4190
Open-Ended Valve
211.4210
Operator of a Gasoline Dispensing Operation or Operator of a Gasoline
Dispensing Facility
211.4230
Organic Compound
211.4250
Organic Material and Organic Materials
211.4260
Organic Solvent
211.4270
Organic Vapor
211.4290
Oven
211.4310
Overall Control
211.4330
Overvarnish
211.4350
Owner of a Gasoline Dispensing Operation or Owner of a Gasoline Dispensing
Facility
211.4370
Owner or Operator
211.4390
Packaging Rotogravure Printing
211.4410
Packaging Rotogravure Printing Line
211.4430
Pail
211.4450
Paint Manufacturing Source or Paint Manufacturing Plant
211.4470
Paper Coating
211.4490
Paper Coating Line
211.4510
Particulate Matter
211.4530
Parts Per Million (Volume) or PPM (Vol)
211.4550
Person
211.4590
Petroleum
211.4610
Petroleum Liquid
211.4630
Petroleum Refinery
211.4650
Pharmaceutical
211.4670
Pharmaceutical Coating Operation
211.4690
Photochemically Reactive Material
211.4710
Pigmented Coatings
211.4730
Plant
211.4740
Plastic Part
211.4750
Plasticizers
211.4770
PM-10
211.4790
Pneumatic Rubber Tire Manufacture
21
211.4810
Polybasic Organic Acid Partial Oxidation Manufacturing Process
211.4830
Polyester Resin Material(s)
211.4850
Polyester Resin Products Manufacturing Process
211.4870
Polystyrene Plant
211.4890
Polystyrene Resin
211.4910
Portable Grain-Handling Equipment
211.4930
Portland Cement Manufacturing Process Emission Source
211.4950
Portland Cement Process or Portland Cement Manufacturing Plant
211.4960
Potential Electrical Output Capacity
211.4970
Potential to Emit
211.4990
Power Driven Fastener Coating
211.5010
Precoat
211.5030
Pressure Release
211.5050
Pressure Tank
211.5060
Pressure/Vacuum Relief Valve
211.5061
Pretreatment Wash Primer
211.5065
Primary Product
211.5070
Prime Coat
211.5080
Primer Sealer
211.5090
Primer Surfacer Coat
211.5110
Primer Surfacer Operation
211.5130
Primers
211.5150
Printing
211.5170
Printing Line
211.5185
Process Emission Source
211.5190
Process Emission Unit
211.5210
Process Unit
211.5230
Process Unit Shutdown
211.5245
Process Vent
211.5250
Process Weight Rate
211.5270
Production Equipment Exhaust System
211.5310
Publication Rotogravure Printing Line
211.5330
Purged Process Fluid
211.5340
Rated Heat Input Capacity
211.5350
Reactor
211.5370
Reasonably Available Control Technology (RACT)
211.5390
Reclamation System
211.5410
Refiner
211.5430
Refinery Fuel Gas
211.5450
Refinery Fuel Gas System
211.5470
Refinery Unit or Refinery Process Unit
211.5480
Reflective Argent Coating
211.5490
Refrigerated Condenser
211.5500
Regulated Air Pollutant
211.5510
Reid Vapor Pressure
22
211.5530
Repair
211.5550
Repair Coat
211.5570
Repaired
211.5580
Repowering
211.5590
Residual Fuel Oil
211.5600
Resist Coat
211.5610
Restricted Area
211.5630
Retail Outlet
211.5650
Ringelmann Chart
211.5670
Roadway
211.5690
Roll Coater
211.5710
Roll Coating
211.5730
Roll Printer
211.5750
Roll Printing
211.5770
Rotogravure Printing
211.5790
Rotogravure Printing Line
211.5810
Safety Relief Valve
211.5830
Sandblasting
211.5850
Sanding Sealers
211.5870
Screening
211.5890
Sealer
211.5910
Semi-Transparent Stains
211.5930
Sensor
211.5950
Set of Safety Relief Valves
211.5970
Sheet Basecoat
211.5980
Sheet-Fed
211.5990
Shotblasting
211.6010
Side-Seam Spray Coat
211.6025
Single Unit Operation
211.6030
Smoke
211.6050
Smokeless Flare
211.6060
Soft Coat
211.6070
Solvent
211.6090
Solvent Cleaning
211.6110
Solvent Recovery System
211.6130
Source
211.6140
Specialty Coatings
211.6145
Specialty Coatings for Motor Vehicles
211.6150
Specialty High Gloss Catalyzed Coating
211.6170
Specialty Leather
211.6190
Specialty Soybean Crushing Source
211.6210
Splash Loading
211.6230
Stack
211.6250
Stain Coating
211.6270
Standard Conditions
23
211.6290
Standard Cubic Foot (scf)
211.6310
Start-Up
211.6330
Stationary Emission Source
211.6350
Stationary Emission Unit
211.6355
Stationary Gas Turbine
211.6360
Stationary Reciprocating Internal Combustion Engine
211.6370
Stationary Source
211.6390
Stationary Storage Tank
211.6400
Stencil Coat
211.6410
Storage Tank or Storage Vessel
211.6420
Strippable Spray Booth Coating
211.6430
Styrene Devolatilizer Unit
211.6450
Styrene Recovery Unit
211.6470
Submerged Loading Pipe
211.6490
Substrate
211.6510
Sulfuric Acid Mist
211.6530
Surface Condenser
211.6540
Surface Preparation Materials
211.6550
Synthetic Organic Chemical or Polymer Manufacturing Plant
211.6570
Tablet Coating Operation
211.6580
Texture Coat
211.6590
Thirty-Day Rolling Average
211.6610
Three-Piece Can
211.6620
Three or Four Stage Coating System
211.6630
Through-the-Valve Fill
211.6650
Tooling Resin
211.6670
Topcoat
211.6690
Topcoat Operation
211.6695
Topcoat System
211.6710
Touch-Up
211.6720
Touch-Up Coating
211.6730
Transfer Efficiency
211.6750
Tread End Cementing
211.6770
True Vapor Pressure
211.6790
Turnaround
211.6810
Two-Piece Can
211.6830
Under-the-Cup Fill
211.6850
Undertread Cementing
211.6860
Uniform Finish Blender
211.6870
Unregulated Safety Relief Valve
211.6880
Vacuum Metallizing
211.6890
Vacuum Producing System
211.6910
Vacuum Service
211.6930
Valves Not Externally Regulated
211.6950
Vapor Balance System
24
211.6970
Vapor Collection System
211.6990
Vapor Control System
211.7010
Vapor-Mounted Primary Seal
211.7030
Vapor Recovery System
211.7050
Vapor-Suppressed Polyester Resin
211.7070
Vinyl Coating
211.7090
Vinyl Coating Line
211.7110
Volatile Organic Liquid (VOL)
211.7130
Volatile Organic Material Content (VOMC)
211.7150
Volatile Organic Material (VOM) or Volatile Organic Compound (VOC)
211.7170
Volatile Petroleum Liquid
211.7190
Wash Coat
211.7200
Washoff Operations
211.7210
Wastewater (Oil/Water) Separator
211.7230
Weak Nitric Acid Manufacturing Process
211.7250
Web
211.7270
Wholesale Purchase - Consumer
211.7290
Wood Furniture
211.7310
Wood Furniture Coating
211.7330
Wood Furniture Coating Line
211.7350
Woodworking
211.7400
Yeast Percentage
211.Appendix A
Rule into Section Table
211.Appendix B
Section into Rule Table
AUTHORITY: Implementing Sections 9, 9.1, 9.9, and 10 and authorized by Sections 27 and
28.5 of the Environmental Protection Act [415 ILCS 5/9, 9.1, 9.9, 10, 27 and 28.5].
SOURCE: Adopted as Chapter 2: Air Pollution, Rule 201: Definitions, R71-23, 4 PCB 191,
filed and effective April 14, 1972; amended in R74-2 and R75-5, 32 PCB 295, at 3 Ill. Reg. 5,
p. 777, effective February 3, 1979; amended in R78-3 and 4, 35 PCB 75 and 243, at 3 Ill.
Reg. 30, p. 124, effective July 28, 1979; amended in R80-5, at 7 Ill. Reg. 1244, effective
January 21, 1983; codified at 7 Ill. Reg. 13590; amended in R82-1 (Docket A) at 10 Ill. Reg.
12624, effective July 7, 1986; amended in R85-21(A) at 11 Ill. Reg. 11747, effective June 29,
1987; amended in R86-34 at 11 Ill. Reg. 12267, effective July 10, 1987; amended in R86-39 at
11 Ill. Reg. 20804, effective December 14, 1987; amended in R82-14 and R86-37 at 12 Ill.
Reg. 787, effective December 24, 1987; amended in R86-18 at 12 Ill. Reg. 7284, effective
April 8, 1988; amended in R86-10 at 12 Ill. Reg. 7621, effective April 11, 1988; amended in
R88-23 at 13 Ill. Reg. 10862, effective June 27, 1989; amended in R89-8 at 13 Ill. Reg.
17457, effective January 1, 1990; amended in R89-16(A) at 14 Ill. Reg. 9141, effective May
23, 1990; amended in R88-30(B) at 15 Ill. Reg. 5223, effective March 28, 1991; amended in
R88-14 at 15 Ill. Reg. 7901, effective May 14, 1991; amended in R91-10 at 15 Ill. Reg.
15564, effective October 11, 1991; amended in R91-6 at 15 Ill. Reg. 15673, effective October
14, 1991; amended in R91-22 at 16 Ill. Reg. 7656, effective May 1, 1992; amended in R91-24
25
at 16 Ill. Reg. 13526, effective August 24, 1992; amended in R93-9 at 17 Ill. Reg. 16504,
effective September 27, 1993; amended in R93-11 at 17 Ill. Reg. 21471, effective December 7,
1993; amended in R93-14 at 18 Ill. Reg. 1253, effective January 18, 1994; amended in R94-12
at 18 Ill. Reg. 14962, effective September 21, 1994; amended in R94-14 at 18 Ill. Reg. 15744,
effective October 17, 1994; amended in R94-15 at 18 Ill. Reg. 16379, effective October 25,
1994; amended in R94-16 at 18 Ill. Reg. 16929, effective November 15, 1994; amended in
R94-21, R94-31 and R94-32 at 19 Ill. Reg. 6823, effective May 9, 1995; amended in R94-33
at 19 Ill. Reg. 7344, effective May 22, 1995; amended in R95-2 at 19 Ill. Reg. 11066,
effective July 12, 1995; amended in R95-16 at 19 Ill. Reg. 15176, effective October 19, 1995;
amended in R96-5 at 20 Ill. Reg. 7590, effective May 22, 1996; amended in R96-16 at 21 Ill.
Reg. 2641, effective February 7, 1997; amended in R97-17 at 21 Ill. Reg. 6489, effective May
16, 1997; amended in R97-24 at 21 Ill. Reg. 7695, effective June 9, 1997; amended in R96-17
at 21 Ill. Reg. 7856, effective June 17, 1997; amended in R97-31 at 22 Ill. Reg. 3497,
effective February 2, 1998; amended in R98-17 at 22 Ill. Reg.11405, effective June 22, 1998;
amended in R01-09 at ____ Ill. Reg. ________, effective ____________________.
BOARD NOTE: This Part implements the Illinois Environmental Protection Act as of July 1,
1994.
Section 211.102
Abbreviations and Conversion Factors
a)
Abbreviations used in this Part include the following:
ASTM
American Society for Testing and Materials
bbl
barrels (42 gallons)
btu
British thermal units (60
o
F)
btu/hr
btu per hour
o
C
degrees Celsius or centigrade
CAAPP
Clean Air Act Permit Program
cm
centimeters
cu in
cubic inches
EGU
Electrical Generating Unit
o
F
degrees Fahrenheit
FIP
Federal Implementation Plan
ft
feet
ft
2
square feet
ft
3
cubic feet
g
grams
gpm
gallons per minute
g/mole
grams per mole
gal
gallons
hp
horsepower
hr
hours
in
inch
o
K
degrees Kelvin
26
kcal
kilocalories
kg
kilograms
kg/hr
kilograms per hour
kPa
kilopascals; one thousand newtons per square meter
kW
kilowatt
l
liters
l/sec
liters per second
lbs
pounds
lbs/day
pounds per day
lbs/hr
pounds per hour
lbs/gal
pounds per gallon
lbs/yr
pounds per year
LEL
lower explosive limit
m
meters
m
2
square meters
m
3
cubic meters
mg
milligrams
Mg
Megagrams, metric tons or tonnes
ml
milliliters
min
minutes
MJ
megajoules
mmbtu
million British thermal units
mmbtu/hr
million British thermal units per hour
mmHg
millimeters of mercury
MTE
maximum theoretical emissions
MWe
megawatt of electricity
MW
megawatt; one million watts
MW-hr
megawatt per hour
NDO
natural draft opening
No
x
nitrogen oxides
peoc
potential electrical output capacity
ppm (vol)
parts per million
ppmv
parts per million by volume
ppmvd
parts per million by volume dry
psi
pounds per square inch
psia
pounds per square inch absolute
psig
pounds per square inch gauge
PTE
potential to emit
RACT
reasonably available control technology
scf
standard cubic feet
scm
standard cubic meters
sec
seconds
SIP
State Implementation Plan
TTE
temporary total enclosure
sq cm
square centimeters
27
sq in
square inches
T
short ton (2,000 lbs)
ton
short ton (2,000 lbs)
TPY
tons per year
USEPA
United States Environmental Protection Agency
VOC
volatile organic compounds
VOL
volatile organic liquids
VOM
volatile organic materials
b)
The following conversion factors have been used in this Part:
English
Metric
1 gal
3.785 1
1,000 gal
3,785 1 or 3.785 m
3
1 psia
6.897 kPA (51.71 mmHg)
2.205 lbs
1 kg
32
o
0
o
C (273.15
o
K)
1 bbl
159.0 l
1 cu in
16.39 ml
1 lb/gal
119,800 mg/l
1 lb/mmbtu 1.548 kg/MW-hr
1 lb/T
0.500 kg/Mg
1 ton
0.907 Mg
1 T
0.907 Mg
mmbtu/hr
0.293 MW
(Source: Amended at ____ Ill. Reg. ________, effective ____________________)
Section 211.479
Allowance
“Allowance” means an authorization to emit up to one ton of NO
x
during the control period of
a specified year or any year thereafter under 35 Ill. Adm. Code 217 and 40 CFR 96.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.1312
Combined Cycle System
“Combined Cycle System” means a system comprised of one or more combustion turbines,
heat recovery steam generators, and steam turbines configured to improve overall efficiency of
electricity generation or steam production.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
28
Section 211.1316
Combustion Turbine
“Combustion Turbine” means an enclosed fossil or other fuel-fired device that is comprised of
a compressor, a combustor, and a turbine, and in which the flue gas resulting from the
combustion of fuel in the combustor passes through the turbine, rotating the turbine.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.1320
Commence Commercial Operation
For purposes of allocation of allowances as described in 35 Ill. Adm. Code 217, “commence
commercial operation” means, with regard to an EGU that serves a generator, to have begun
to produce steam, gas, or other heated medium used to generate electricity for sale or use,
including test generation. Such date shall remain the unit’s date of commencement of
operation even if the EGU is subsequently modified, reconstructed or repowered.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211. 1324
Commence Operation
For purposes of allocation of allowances as described in 35 Ill. Adm. Code 217, “commence
operation” means with regard to a stationary boiler, combustion turbine, or combined cycle
system to have begun any mechanical, chemical, or electronic process, including, start-up of
the unit’s combustion chamber. Such date shall remain the unit’s date of commencement of
operation even if the unit is subsequently modified, reconstructed, or repowered.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.1328
Common Stack
“Common stack” means a single flue through which emissions from two or more units are
exhausted.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.1515
Control Period
For purposes of 35 Ill. Adm. Code 217, “control period” means the period beginning May 1
of a year and ending on September 30 of the same year, inclusive, except that in 2004,
“control period” means May 31 through September 30.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
29
Section 211.2080
Excess Emissions
“Excess emissions” means any tonnage of NO
x
emitted by a NO
x
budget unit during a control
period that exceeds the NO
x
allowances available for compliance deduction for the unit and for
a control period.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.2420
Fossil Fuel
“Fossil fuel” means natural gas, petroleum, coal, or any form of solid, liquid, or gaseous fuel
derived from such material.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.2425
Fossil Fuel-Fired
“Fossil fuel-fired” means the combustion of fossil fuel, alone or in combination with any other
fuel, where fossil fuel actually combusted comprises or is projected to comprise more than 50
percent of the annual heat input on a btu basis during any year.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.2620
Generator
“Generator” means a device that produces electricity.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.2815
Heat Input
“Heat input” means the product of the gross heating value of the fuel and the amount of fuel
combusted in a combustion device. Heat input does not include the heat derived from
preheated combustion air, recirculated flue gases, or exhaust from other sources.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.2820
Heat Input Rate
“Heat input rate” means the amount of heat input used by a combustion device, divided by its
operating time (in hrs).
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
30
Section 211.3980
Nameplate Capacity
“Nameplate capacity” means the maximum electrical generating output (in MWe) that a
generator can sustain over a specified period of time when not restricted by seasonal or other
deratings as measured in accordance with the United States Department of Energy standards.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.4960
Potential Electrical Output Capacity
“Potential electrical output capacity” means the MWe capacity rating for the units which shall
be equal to 33% of the maximum design heat input capacity of the steam generating unit.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 211.5580
Repowering
For purposes of 35 Ill. Adm. Code 217, Subpart W, “repowering” means the conversion or
replacement of an existing budget EGU, as identified in Appendix F, with a technology
capable of controlling NO
x
and other combustion emissions simultaneously with improved
boiler or generation efficiency and with waste reduction, or any other replacement generation
technology as determined by the Illinois Environmental Protection Agency. Repowering shall
be considered a control technology for purposes of 35 Ill. Adm. Code 217.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE B: AIR POLLUTION
CHAPTER I: POLLUTION CONTROL BOARD
SUBCHAPTER c: EMISSION STANDARDS AND LIMITATIONS FOR
STATIONARY SOURCES
PART 217
NITROGEN OXIDES EMISSIONS
SUBPART A: GENERAL PROVISIONS
Section
217.100
Scope and Organization
217.101
Measurement Methods
217.102
Abbreviations and Units
217.103
Definitions
217.104
Incorporations by Reference
SUBPART B: NEW FUEL COMBUSTION EMISSION SOURCES
31
Section
217.121
New Emission Sources
SUBPART C: EXISTING FUEL COMBUSTION EMISSION SOURCES
Section
217.141
Existing Emission Sources in Major Metropolitan Areas
SUBPART K: PROCESS EMISSION SOURCES
Section
217.301
Industrial Processes
SUBPART O: CHEMICAL MANUFACTURE
Section
217.381
Nitric Acid Manufacturing Processes
SUBPART V: ELECTRIC POWER GENERATION
Section
217.521
Lake of Egypt Power Plant
SUBPART W: NO
x
TRADING PROGRAM FOR ELECTRICAL
GENERATING UNITS
Section
217.750
Purpose
217.752
Severability
217.754
Applicability
217.756
Compliance Requirements
217.758
Permitting Requirements
217.760
NO
x
Trading Budget
217.762
Methodology for Calculating NO
x
Allocations for Budget Electrical Generating
Units (EGUs)
217.764
NO
x
Allocations for Budget EGUs
217.768
New Source Set-Asides for “New” Budget EGUs
217.770
Early Reduction Credits for Budget EGUs
217.774
Opt-In Units
217.776
Opt-In Process
217.778
Budget Opt-In Units: Withdrawal from NO
x
Trading Program
217.780
Opt-In Units: Change in Regulatory Status
217.782
Allowance Allocations to Budget Opt-In Units
APPENDIX A
Rule into Section Table
APPENDIX B
Section into Rule Table
APPENDIX C
Compliance Dates
APPENDIX D
Non-Electrical Generating Units
APPENDIX F
Allowances for Electrical Generating Units
32
AUTHORITY: Implementing Sections 9.9 and 10 and authorized by Sections 27 and 28.5 of
the Environmental Protection Act (Ill. Rev. Stat. 1981, ch. 111 ½, pars. 1010 and 1027) [415
ILCS 5/9.9, 10, 27, and 28.5].
SOURCE: Adopted as Chapter 2: Air Pollution, Rule 207: Nitrogen Oxides Emissions, R71-
23, 4 PCB 191, April 13, 1972, filed and effective April 14, 1972; amended at 2 Ill. Reg. 17,
p. 101, effective April 13, 1978; codified at 7 Ill. Reg. 13609; amended in R01-9 at _____ Ill.
Reg. ____, effective ____________________.
SUBPART A: GENERAL PROVISIONS
Section 217.100
Scope and Organization
a)
This Part sets standards and limitations for emission of oxides of nitrogen from
stationary sources.
b)
Permits for sources subject to this Part may be required pursuant to 35 Ill. Adm.
Code 201.
c)
Notwithstanding the provisions of this Part the air quality standards contained in
35 Ill. Adm. Code 243 may not be violated.
d)
This Part is divided into Subparts which are grouped as follows:
1)
Subpart A: General Provisions;
2)
Subparts B-J: Fuel Combustion Sources and Incinerators;
3)
Subparts K-M: Process Emission Sources;
4)
Subparts N-End: Industry and Site-specific rules.
ed)
These rules have been grouped for convenience of the public; the scope of each
is determined by its language and history.
(Source: Amended at ____ Ill. Reg. ________, effective ____________________)
Section 217.101
Measurement Methods
Measurement of nitrogen oxides shall be according to:
a)
The the phenol disulfonic acid method, 36 Fed. Reg. 15, 718 40 CFR 60,
Appendix A, Method 7. (1999); and
33
b)
Continuous emissions monitoring pursuant to 40 CFR 75 (1999); and
c)
Determination of Nitrogen Oxides Emissions from Stationary Sources
(Instrumental Analyzer Procedure), 40 CFR 60, Appendix A, Method 7E
(1999).
(Source: Amended at ____ Ill. Reg. ________, effective ____________________)
Section 217.102
Abbreviations and Units
a)
The following abbreviations are used in this Part:
btu
British thermal unit (60
o
F)
EGU
Electrical Generating Unit
kg
kilogram
kg/MW-hr
kilograms per megawatt-hour, usually used as an hourly emission
rate
lb
pound
NO
x
Nitrogen Oxides
lbs/mmbtu
pounds per million btu, usually used as an hourly emission rate
Mg
megagram or metric tonne
mmbtu
million British thermal units
mmbtu/hr
million British thermal units per hour
MWe
megawatt of electricity
MW
megawatt; one million watts
MW-hr
megawatt-hour
peoc
potential electrical output capacity
ppm
parts per million
ppmv
parts per million by volume
T
English ton
b)
The following conversion factors have been used in this Part:
English
Metric
2.205 lb
1 kg
1 T
0.907 Mg
1 lb/T
0.500 kg/Mg
Mmbtu/hr
0.293 MW
1 lb/mmbtu 1.548 kg/MW-hr
(Source: Amended at ____ Ill. Reg. ________, effective ____________________)
34
Section 217.104
Incorporations by Reference
The following materials are incorporated by reference. These incorporations do not include
any later amendments or editions.
a)
The the phenol disulfonic acid method as published in 36 Fed. Reg. 15, 718, 40
CFR 60, Appendix A, Method 7. (1999);
b)
40 CFR 96, subparts B, D, G and H (1999);
c)
40 CFR 96.1 through 96.3, 96.5 through 96.7, 96.50 through 96.54, 96.55 (a)
& (b), 96.56 and 96.57 (1999); and
d)
40 CFR 72, 75 & 76 (1999).
(Source: Amended at ____ Ill. Reg. ________, effective ____________________)
SUBPART W: NO
x
TRADING PROGRAM FOR ELECTRICAL GENERATING
UNITS
Section 217.750
Purpose
The purpose of this Subpart is to control the emissions of nitrogen oxides (NO
x
) during the
ozone control period (May 1 through September 30 of each year, except that in 2004, “control
period” means May 31 through September 30) from electrical generating units (EGUs) by
determining source allocations and implementing the NO
x
Trading Program pursuant to 40
CFR 96, as authorized by Section 9.9 of the Act [415 ILCS 5/9.9].
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.752
Severability
If any Section, subsection or clause of this Subpart is found invalid, such finding shall not
affect the validity of this Subpart as a whole or any Section, sentence or clause not found
invalid.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.754
Applicability
a)
The following fossil fuel-fired stationary boilers, combustion turbines or
combined cycle systems are electrical generating units (EGUs) and are subject to
this Subpart:
35
1)
Any unit serving a generator that has a nameplate capacity greater than
25 MWe and produces electricity for sale, excluding those units listed in
Appendix D of this Part.
2)
Any unit with a maximum design heat input that is greater than 250
mmbtu/hr that commences operation on or after January 1, 1999, serving
at any time a generator that has a nameplate capacity of 25 MWe or less
and has the potential to use more than 50% of the potential electrical
output capacity of the unit. Fifty percent of a unit’s potential electrical
output capacity shall be determined by multiplying the unit’s maximum
design heat input by 0.0488 MWe/mmbtu. If the size of the generator is
greater than this calculated number, the unit is an EGU subject to the
provisions of this Subpart.
b)
Those units that meet the above criteria and are subject to the NO
x
Trading
Program emissions limitations contained in this Subpart are budget EGUs.
c)
Low-emitter status: Notwithstanding subsection (a) of this Section, the owner
or operator of a budget EGU under subsection (a) of this Section may elect low-
emitter status by obtaining a permit with federally enforceable conditions
meeting the requirements of subsection (c)(1) of this Section. Starting with the
effective date of such permit, the EGU shall not be a budget EGU and shall be
subject only to the requirements of this subsection (c).
1)
For each control period under this subsection (c), the federally
enforceable permit conditions must:
A)
Restrict the EGU to burning only natural gas, fuel oil, or natural
gas and fuel oil;
B)
Limit the EGU’s potential NO
x
mass emissions for the control
period to 25 tons or less;
C)
Restrict the EGU’s operating hours during the control period to
the number calculated by dividing 25 tons of potential NO
x
mass
emissions by the EGU’s maximum potential hourly NO
x
mass
emissions;
D)
Require that the EGU’s potential NO
x
mass emissions be
calculated by using the monitoring provisions of 40 CFR 75 or, if
the EGU does not rely on these monitoring provisions, by using
the applicable default rate, as follows:
i)
Select the applicable default NO
x
emission rate from one
of the following:
36
0.7 lb/mmbtu for combustion turbines burning natural gas
exclusively during the control period;
1.2 lbs/mmbtu for combustion turbines burning any fuel
oil during the control period;
1.5 lbs/mmbtu for boilers burning natural gas exclusively
during the control period; or
2 lbs/mmbtu for boilers burning any fuel oil during the
control period.
ii)
Multiply the default NO
x
emission rate under subsection
(c)(1)(D)(i) of this Section by the EGU’s unit-specific
maximum rated heat input (mmbtu), which is the higher of
the manufacturer’s maximum rated hourly heat input or
the highest observed hourly heat input. The owner or
operator of the EGU may request in the permit application
required by this subsection (c) that the Agency use a lower
value for the EGU’s maximum rated hourly heat input.
The Agency may approve such lower value if the owner
or operator demonstrates that the maximum hourly heat
input specified by the manufacturer or the highest
observed hourly heat input, or both, are not
representative. The owner or operator must also
demonstrate that such lower value is representative of the
EGU’s current capabilities because modifications have
been made to the EGU that permanently limit the EGU’s
capacity;
E)
Require that the owner or operator of the EGU retain for five
years, at the source that includes the EGU, records demonstrating
that the operating hours restriction, the fuel use restriction, and
the other requirements of the permit related to these restrictions
were met; and
F)
Require that the owner or operator of the EGU report to the
Agency the EGU’s hours of operation (treating any partial hour
of operation as a whole hour of operation), heat input, and fuel
use by type during each control period. This report shall be
submitted by November 1 of each year the EGU elects low-
emitter status.
37
2)
The Agency will notify USEPA in writing of each EGU electing low-
emitter status pursuant to the requirements of subsection (c)(1) of this
Section and when any of the following occurs:
A)
The permit with federally enforceable conditions that includes the
restrictions in subsection (c)(1) of this Section is issued by the
Agency;
B)
Such permit is revised to remove any such restriction;
C)
Such permit includes any such restriction that is no longer
applicable; or
D)
The EGU does not comply with any such restriction.
3)
The EGU shall become a budget EGU, subject to the requirements of
this Subpart if, for any control period under subsection (c) of this
Section, the fuel use restriction or the operating hours restriction under
subsection (c)(1) of this Section is removed from the EGU’s permit or
otherwise becomes no longer applicable, or the EGU does not comply
with the fuel use restriction or the operating hours restriction under
subsection (c)(1) of this Section. Such EGU shall be treated as
commencing operation and, for a unit under subsection (a)(1) of this
Section, commencing commercial operation, on September 30 of the year
prior to the control period for which the fuel use restriction or the
operating hours restriction is no longer applicable or during which the
EGU does not comply with the fuel use restriction or the operating hours
restriction.
4)
The owner or operator of an EGU to which the Agency has ever
allocated allowances may elect low-emitter status. In that case, the
Agency will reduce the EGU trading budget by the number of allowances
corresponding to the amount of NO
x
emissions the EGU is permitted to
emit during the control period as set forth in the EGU’s federally
enforceable state operating permit.
d)
Notwithstanding the provisions in subsection (a) of this Section, sources may
opt-in to the NO
x
Trading Program and will receive allowance allocations
consistent with applicable requirements, if they meet the requirements for a
budget opt-in unit pursuant to Sections 217.774 through 217.782 of this Part.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
38
Section 217.756
Compliance Requirements
All EGUs subject to the requirements of this Subpart must comply with the following:
a)
The requirements of this Subpart and 40 CFR 96 (excluding 40 CFR 96.4(b)
and 96.55(c), and excluding 40 CFR 96, Subparts C, E, and I) as incorporated
by reference in Section 217.104 of this Part.
b)
Permit requirements:
1)
The owner or operator of each source with one or more budget EGUs at
the source must apply for a permit issued by the Agency with federally
enforceable conditions covering the NO
x
Trading Program (“budget
permit”) that complies with the requirements of Section 217.758 of this
Part.
2)
The owner or operator of each budget source and each budget EGU at
the source must operate the budget EGU in compliance with such budget
permit.
c)
Monitoring requirements:
1)
The owner or operator of each budget source and each budget EGU at
the source must comply with the monitoring requirements of 40 CFR 96,
subpart H. The account representative of each budget source and each
budget EGU at the source must comply with those sections of the
monitoring requirements of 40 CFR 96, subpart H, applicable to an
account representative.
2)
The compliance of each budget EGU with the budget emissions
limitation under subsection (d) of this Section shall be determined by the
emissions measurements recorded and reported in accordance with 40
CFR 96, subpart H.
d)
NO
x
requirements:
1)
By November 30 of each year, the allowance transfer deadline, the
account representative of each budget source and each budget EGU at the
source shall hold allowances available for compliance deductions under
40 CFR 96.54 in the budget EGU’s compliance account or the source's
overdraft account. The number of allowances held shall not be less than
the budget EGU’s total tons of NO
x
emissions for the control period,
rounded to the nearest whole ton, as determined in accordance with 40
CFR 96, subpart H, plus any number necessary to account for actual
39
utilization (e.g., for testing, start-up, malfunction, and shut down) under
40 CFR 96.42(e) for the control period.
2)
Each ton of NO
x
emitted in excess of the number of NO
x
allowances held
by the owner or operator for each budget EGU for each control period
shall constitute a separate violation of this Part and the Act.
3)
A budget EGU shall be subject to the monitoring and NO
x
requirements
of subsections (c)(1) and (d)(1) of this Section starting on the later of
May 31, 2004, the date on which the EGU commences OR THE FIRST
DAY OF THE CONTROL SEASON SUBSEQUENT TO THE
CALENDAR YEAR IN WHICH ALL OF THE OTHER STATES
SUBJECT TO THE PROVISIONS OF THE NO
X
SIP CALL (63 Fed.
Reg. 57355 (October 27, 1998)) THAT ARE LOCATED IN USEPA
REGION V OR THAT ARE CONTIGUOUS TO ILLINOIS HAVE
ADOPTED REGULATIONS TO IMPLEMENT NO
X
TRADING
PROGRAMS AND OTHER REQUIRED REDUCTIONS OF NO
X
EMISSIONS PURSUANT TO THE NO
X
SIP CALL, AND SUCH
REGULATIONS HAVE RECEIVED FINAL APPROVAL BY USEPA
AS PART OF THE RESPECTIVE STATES’ SIPS FOR OZONE, OR A
FINAL FIP FOR OZONE PROMULGATED BY USEPA IS
EFFECTIVE. [415 ILCS 5/9.9(f)]
4)
Allowances shall be held in, deducted from, or transferred among
allowance accounts in accordance with this Subpart and 40 CFR 96,
subparts F and G, and Sections 217.774 through 217.782 of this Part.
5)
In order to comply with the requirements of subsection (d)(1) of this
Section, an allowance may not be utilized for a control period in a year
prior to the year for which the allowance is allocated.
6)
An allowance allocated by the Agency or USEPA under the NO
x
Trading
Program is a limited authorization to emit one ton of NO
x
in accordance
with the NO
x
Trading Program. No provision of the NO
x
Trading
Program, the budget permit application, the budget permit, or a retired
unit exemption under 40 CFR 96.5, and no provision of law shall be
construed to limit the authority of the United States or the State to
terminate or limit this authorization.
7)
An allowance allocated by the Agency or USEPA under the NO
x
Trading
Program does not constitute a property right.
8)
Upon recordation by USEPA under 40 CFR 96, subpart F or G, or
Section 217.782 of this Part, every allocation, transfer, or deduction of
an allowance to or from a budget EGU’s compliance account or to or
40
from the overdraft account of the budget source where the budget EGU
is located is deemed to amend automatically, and become a part of, any
budget permit of the budget EGU. This automatic amendment of the
budget permit shall be deemed an operation of law and will not require
any further review.
e)
Recordkeeping and reporting requirements:
1)
Unless otherwise provided, the owner or operator of the budget source
and each budget EGU at the source shall keep on site at the source each
of the documents listed in subsections (e)(1)(A) through (e)(1)(D) of this
Section for a period of five years from the date the document is created.
This period may be extended for cause, at any time prior to the end of
five years, in writing by the Agency or USEPA.
A)
The account certificate of representation of the account
representative for the source and each budget EGU at the source,
all documents that demonstrate the truth of the statements in the
account certificate of representation, in accordance with 40 CFR
96.13, provided that the certificate and documents must be
retained on site at the source beyond such five-year period until
such documents are superseded because of the submission of a
new account certificate of representation changing the account
representative.
B)
All emissions monitoring information, in accordance with 40
CFR 96, subpart H, provided that to the extent that 40 CFR 96,
subpart H provides for a three-year period for recordkeeping, the
three-year period shall apply.
C)
Copies of all reports, compliance certifications, and other
submissions and all records made or required under the NO
x
Trading Program or documents necessary to demonstrate
compliance with the requirements of the NO
x
Trading Program or
with the requirements of this Subpart.
D)
Copies of all documents used to complete a budget permit
application and any other submission under the NO
x
Trading
Program.
2)
The account representative of a budget source and each budget EGU at
the source must submit to the Agency and USEPA the reports and
compliance certifications required under the NO
x
Trading Program,
including those under 40 CFR 96, subparts D and H, and Section
217.774 of this Part.
41
f)
Liability:
1)
No revision of a permit for a budget EGU shall excuse any violation of
the requirements of the NO
x
Trading Program that occurs prior to the
date that the revision to such budget permit takes effect.
2)
Each budget source and each budget EGU shall meet the requirements of
the NO
x
Trading Program.
3)
Any provision of the NO
x
Trading Program that applies to a budget
source (including any provision applicable to the account representative
of a budget source) shall also apply to the owner and operator of such
budget source and to the owner and operator of each budget EGU at the
source.
4)
Any provision of the NO
x
Trading Program that applies to a budget EGU
(including any provision applicable to the account representative of a
budget EGU) shall also apply to the owner and operator of such budget
EGU. Except with regard to the requirements applicable to budget
EGUs with a common stack under 40 CFR 96, subpart H, the owner and
operator and the account representative of one budget EGU shall not be
liable for any violation by any other budget EGU of which they are not
an owner or operator or the account representative.
5)
The account representative of a budget EGU that has excess emissions in
any control period shall surrender the allowances as required for
deduction under 40 CFR 96.54(d)(1).
6)
The owner or operator of a budget EGU that has excess emissions in any
control period shall pay any fine, penalty, or assessment or comply with
any other remedy imposed under 40 CFR 96.54(d)(3) and the Act.
g)
Effect on other authorities. No provision of the NO
x
Trading Program, a budget
permit application, a budget permit, a low-emitter exemption under Section
217.754(c) of this Subpart, or a retired unit exemption under 40 CFR 96.5 shall
be construed as exempting or excluding the owner and operator and, to the
extent applicable, the account representative of a budget source or budget EGU,
from compliance with any other regulation promulgated under the CAA, the
Act, an approved State implementation plan, or a federally enforceable permit.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
42
Section 217.758
Permitting Requirements
a)
Budget permit requirements:
1)
Each source with a budget EGU is required to submit a complete permit
application addressing all applicable NO
x
Trading Program requirements
for a permit meeting the requirements of this Section, applicable to each
budget EGU at the source. Each budget permit (including any draft or
proposed budget permit, if applicable) will contain elements required for
a complete budget permit application under subsection (b)(2) of this
Section.
2)
Each budget permit (including a draft or proposed budget permit, if
applicable) shall contain federally enforceable conditions addressing all
applicable NO
x
Trading Program requirements and shall be a complete
and segregable portion of the source’s entire permit under subsection
(a)(1) of this Section.
3)
No budget permit shall be issued, and no NO
x
allowance account shall be
established for a budget EGU at a source, until the Agency and USEPA
have received a complete account certificate of representation under 40
CFR 96, subpart B, for an account representative of the source and the
budget EGU at the source.
4)
For budget EGUs that commenced operation before November 1, 2003,
and for which a CAAPP permit is not required pursuant to Section 39.5
of the Act, the owner or operator of such unit must submit a budget
permit application meeting the requirements of this Section on or before
November 1, 2003.
5)
For budget EGUs that commenced operation before August 1, 2003, and
for which a CAAPP permit is required pursuant to Section 39.5 of the
Act, the owner or operator of such unit must submit a budget permit
application meeting the requirements of this Section on or before August
1, 2003.
6)
For budget EGUs that are subject to Section 39.5 of the Act and that
commence operation on or after August 1, 2003, and for budget EGUs
not subject to Section 39.5 of the Act and that commence operation on or
after November 1, 2003, the owner or operator of such units must
submit applications for construction and operating permits pursuant to
the requirements of Sections 39 and 39.5 of the Act and 35
Ill.Adm.Code 201 and such applications must specify that they are
applying for budget permits, and must address the budget permit
application requirements of this Section.
43
b)
Budget permit applications:
1)
Duty to apply. The owner or operator of any source with one or more
budget EGUs shall submit to the Agency a complete budget permit
application for the source under subsection (b)(2) of this Section by the
applicable deadline in subsection (a)(4), (a)(5), or (a)(6) of this Section.
The owner or operator of any source with one or more budget EGUs
shall reapply for a budget permit for the source as required by this
Subpart, 35 Ill. Adm. Code 201, and Sections 39 and 39.5 of the Act.
2)
Information requirements for budget permit applications. A complete
budget permit application shall include the following elements
concerning the source for which the application is submitted:
A)
Identification of the source, including plant name. The ORIS
(Office of Regulatory Information Systems) or facility code
assigned to the source by the Energy Information Administration
shall also be included, if applicable;
B)
Identification of each budget EGU at the source. An explanation
of whether each EGU is a budget EGU under Section 217.754 or
217.774 of this Part;
C)
The compliance requirements of Section 217.756 of this Part; and
D)
For each opt-in unit at the source the following certification
statements by the account representative:
i)
“I certify that each unit for which this permit application
is submitted under Section 217.774 of this Part is not a
budget EGU under Section 217.754 of this Part and is not
covered by a retired unit exemption that is in effect under
40 CFR 96.5.”
ii)
If the application is for an initial budget permit, “I certify
that each unit for which this permit application is
submitted under Section 217.774 of this Part, and has
documented heat input for more than 876 hours in the six
months immediately preceding the submission of an
application for an initial budget permit under Section
217.774(d) of this Part.”
3)
An application for a budget permit shall be treated as a modification of
the EGU’s existing federally enforceable permit, if such a permit has
44
been issued for that EGU, and shall be subject to the same procedural
requirements. When the Agency issues a budget permit, it shall be
incorporated into and become part of that EGU’s existing federally
enforceable permit.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.760
NO
x
Trading Budget
The NO
x
trading budget available for allowance allocations for each control period shall be
determined as follows:
a)
The total base EGU trading budget is 30,701 tons per control period subject,
however, to the following:
1)
In 2004 through 2006, 5% of this number shall be allocated to the new
source set-aside under Section 217.768 of this Part, resulting in an EGU
trading budget of 29,166 tons available for allocation per control period;
and
2)
In 2007 and thereafter, 2% of this amount shall be allocated to the new
source set-aside, resulting in an EGU trading budget of 30,087 tons
available for allocation per control period.
b)
The Agency must adjust the total base EGU trading budget available for
allocation in subsection (a) of this Section to remove allowances from budget
EGUs opting to become exempt pursuant to the requirements for low-emitters in
Section 217.754(c)(4) of this Part.
c)
If USEPA adjusts the total base EGU trading budget for any reason, the Agency
will adjust the budget pro rata.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.762
Methodology for Calculating NO
x
Allocations for Budget Electrical
Generating Units (EGUs)
The methodology for calculating the allowances to be allocated to budget EGUs is based on the
following emission rates and heat inputs:
a)
The applicable NO
x
emission rates are as follows:
1)
For budget EGUs listed in Appendix F: 0.15 lb/mmbtu.
45
2)
For budget EGUs not listed in Appendix F: The more stringent of 0.15
lb/mmbtu or the permitted NO
x
emission rate, but not less than 0.055
lb/mmbtu.
b)
Heat input (HI) (in mmbtu/control period) is determined as follows:
1)
The budget EGU’s two highest heat inputs from the control periods four
to six years prior to the year for which the allocation is being made are
averaged. However, for a budget EGU that did not commence
commercial operation at least six years prior to the control period for
which the allocation is being made, the heat inputs for the following
control periods shall be used:
A)
If the budget EGU has heat input for the control period four years
prior to the year for which the NO
x
allocation is being made, but
not for the control periods five and six years prior, the heat input
for that control period four years prior shall be used; or
B)
If the budget EGU has heat inputs for the control periods four
and five years prior to the year for which the NO
x
allocation is
being made, but not for the control period six years prior, the
heat input for the control periods four and five years prior shall
be averaged.
2)
The budget EGU’s heat input in subsection (b)(1) of this Section for the
control period in each year will be determined in accordance with:
A)
40 CFR 75, as incorporated by reference in Section 217.104 of
this Part, if the budget EGU was otherwise subject to its
requirements for the year; or
B)
The best available data reported to the Agency for the budget
EGU if the budget EGU was not subject to the requirements of 40
CFR 75, for the year.
c)
The general equation for determining allowances is:
A=
HI
×
ER
2000
Where:
HI = heat input (in mmbtu/control period) as determined in Section
217.762(b) of this Part.
46
ER = The NO
x
emission rate in lbs/mmbtu as determined in Section
217.762(a) of this Part.
A = allowances of NO
x
/control period.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.764
NO
x
Allocations for Budget EGUs
For each control period, the Agency will allocate the total number of NO
x
allowances in the
trading budget apportioned to budget EGUs under Section 217.760 of this Part. These
allocations will be issued as provided in subsections (a) through (f) of this Section and Section
217.768 for this Part of new sources. Specifically:
a)
In 2004, 2005, and 2006 (or the first three years of the program):
1)
The Agency will allocate to each budget EGU that is listed in Appendix
F of this Part the number of allowances listed in Column 7 of Appendix
F of this Part for that budget EGU, as well as any allowances that are not
allocated from the new source set-aside to budget EGUs in subsection
(a)(2) of this Section. Any such allowances from the new source set-
aside will be allocated to budget EGUs listed in Appendix F of this Part
pursuant to 217.768(j) of this Part.
2)
The Agency will allocate allowances from the new source set-aside to
budget EGUs that commenced commercial operation on or after January
1, 1995, pursuant to Section 217.768 of this Part.
3)
The Agency will report these allocations to USEPA at the time it submits
the SIP.
b)
In 2007 (or the fourth year of the program):
1)
The Agency will allocate to each budget EGU that is listed in Appendix
F of this Part the number of allowances listed in Column 8 of Appendix
F for that budget EGU, and any allowances that are not allocated to
budget EGUs under subsection (b)(2) of this Section will be allocated as
provided in subsection (b)(4) of this Section.
2)
The Agency will apportion to each budget EGU that commenced
commercial operation on or after January 1, 1995, and before May 1,
2003, allowances as calculated in the following equation:
47
()
A=
0.80
××
HI ER
2000
Where:
HI = heat input (in mmbtu/control period) as determined
in Section 217.762(b) of this Part.
ER = the NO
x
emission rate in lbs/mmbtu, as determined
in Section 217.762(a)(2) of this Part.
A = allowances of NO
x
/control period.
3)
Notwithstanding subsection (b)(2) of this Section, if the total number of
allowances determined by subsection (b)(2) of this Section is more than
6,017, which is the number of allowances remaining in the trading
budget after allocations have been made to budget EGUs in subsection
(b)(1) of this Section, the Agency will prorate the number of NO
x
allowances available to budget EGUs pursuant to the criteria in
subsection (b)(2) of this Section so that the total number of allowances
allocated to these budget EGUs does not exceed 6, 017.
4)
If the total number of allowances allocated pursuant to subsection (b)(2)
of this Section is less than 6,017, which is the number of allowances
remaining in the trading budget after allocations have been made to
budget EGUs in subsection (b)(1) of this Section, the Agency will
allocate the remaining allowances to budget EGUs as follows:
A)
For budget EGUs in subsection (b)(1) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(1) of this Part.
B)
For budget EGUs in subsection (b)(2) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(2) of this Part.
5)
The Agency will allocate allowances from the new source set-aside,
pursuant to Section 217.768 of this Part, to budget EGUs that
commenced commercial operation after May 1, 2003 and that have not
operated for the full 2003 control period.
48
6)
The Agency will report these allocations to USEPA by April 1, 2004,
except for allocations from the new source set-aside, which the Agency
will report by May 1, 2007.
c)
In 2008 (or the fifth year of the program):
1)
The Agency will allocate to each budget EGU that is listed in Appendix
F of this Part the number of allowances listed in Column 8 of Appendix
F for that budget EGU, and any allowances that are not allocated to
budget EGUs under subsection (b)(2) of this Section will be allocated as
provided in subsection (b)(4) of this Section.
2)
The Agency will apportion to each budget EGU that commenced
commercial operation on or after January 1, 1995, and before May 1,
2004, allowances as calculated in the following equation:
()
A=
0.80
××
HI ER
2000
Where:
HI = heat input (in mmbtu/control period) as determined
in Section 217.762(b) of this Part.
ER = the NO
x
emission rate in lbs/mmbtu, as determined
in Section 217.762(a)(2) of this Part.
A = allowances of NO
x
/control period.
3)
Notwithstanding subsection (c)(2) of this Section, if the total number of
allowances determined by subsection (c)(2) of this Section is more than
6,017, which is the number of allowances remaining in the trading
budget after allocations have been made to budget EGUs in subsection
(c)(1) of this Section, the Agency will prorate the number of NO
x
allowances available to budget EGUs pursuant to the criteria in
subsection (c)(2) of this Section so that the total number of allowances
allocated to these budget EGUs does not exceed 6,017.
4)
If the total number of allowances allocated pursuant to subsection (c)(2)
of this Section is less than 6,017, which is the number of allowances
remaining in the trading budget after allocations have been made to
budget EGUs in subsection (c)(1) of this Section, the Agency will
allocate the remaining allowances to budget EGUs as follows:
49
A)
For budget EGUs in subsection (c)(1) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(1) of this Part.
B)
For budget EGUs in subsection (c)(2) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(2) of this Part.
5)
The Agency will allocate allowances from the new source set-aside,
pursuant to Section 217.768 of this Part, to budget EGUs that
commenced commercial operation after May 1, 2004 and that have not
operated for the full 2004 control period.
6)
The Agency will report these allocations to USEPA by April 1, 2005,
except for allocations from the new source set-aside, which the Agency
will report by May 1, 2008.
d)
In 2009 (or the sixth year of the program):
1)
The Agency will allocate to each budget EGU that is listed in Appendix
F of this Part the number of allowances listed in Column 9 of Appendix
F for that budget EGU and any allowances that are not allocated to
budget EGUs under subsection (d)(2) of this Section will be allocated as
provided in subsection (d)(4) of this Section.
2)
The Agency will apportion to each budget EGU that commenced
commercial operation on or after January 1, 1995, and before May 1,
2005, allowances calculated in the following equation:
()
A=
0.50
××
HI ER
2000
Where:
HI = heat input (in mmbtu/control period) as determined
in Section 217.762(b) of this Part.
ER = the NO
x
emission rate in lbs/mmbtu, as determined
in Section 217.762(a)(2) of this Part.
A = allowances of NO
x
/control period.
50
3)
Notwithstanding subsection (d)(2) of this Section, if the total number of
allowances determined by subsection (d)(2) of this Section is more than
15,043, which is the number of allowances remaining in the trading
budget after allocations have been made to budget EGUs in subsection
(d)(1) of this Section, the Agency will prorate the total number of NO
x
allowances available to budget EGUs that received allowances pursuant
to the criteria in subsection (d)(2) of this Section so that the total number
of allowances allocated to these budget EGUs does not exceed 15,043.
4)
If the total number of allowances allocated pursuant to subsection (d)(2)
of this Section is less than 15,043, which is the number of allowances
remaining in the trading budget after allocations have been made to
budget EGUs in subsection (d)(1) of this Section, the Agency will
allocate the remaining allowances to budget EGUs as follows:
A)
For budget EGUs in subsection (d)(1) of this Section, the pro rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(1) of this Part.
B)
For budget EGUs in subsection (d)(2) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(2) of this Part.
5)
The Agency will allocate allowances from the new source set-aside,
pursuant to Section 217.768 of this Part, to budget EGUs that
commenced commercial operation after May 1, 2005 and that have not
operated for the full 2005 control period.
6)
As of April 30, 2009, if the number of allowances in the new source set-
aside exceeds 3% of the total number of tons of NO
x
emissions in the
trading budget apportioned to budget EGUs as determined pursuant to
Section 217.768(i) and (j) of this Part, the number of allowances above
3% will be allocated to budget EGUs receiving allowances pursuant to
this subsection (d).
7)
The Agency will report these allocations to USEPA by April 1, 2006,
except for allocations from the new source set-aside, which the Agency
will report by May 1, 2009.
e)
In 2010 (or the seventh year of the program):
1)
The Agency will allocate to each budget EGU that is listed in Appendix
F of this Part the number of allowances listed in Column 9 of Appendix
51
F for that budget EGU and any allowances that are not allocated to
budget EGUs under subsection (e)(2) of this Section as provided in
subsection (e)(4) of this Section.
2)
The Agency will assign to each budget EGU that commenced
commercial operation on or after January 1, 1995, and before May 1,
2006, allowances as calculated in the following equation:
()
A=
0.50
××
HI ER
2000
Where:
HI = heat input (in mmbtu/control period) as determined
in Section 217.762(b) of this Part.
ER = the NO
x
emission rate in lbs/mmbtu, as determined
in Section 217.762(a)(2) of this Part.
A = allowances of NO
x
/control period.
3)
Notwithstanding subsection (e)(2) of this Section, if the total number of
allowances determined by subsection (e)(2) of this Section is more than
15,043, which is the number of allowances remaining in the trading
budget after allocations have been made to budget EGUs in subsection
(e)(1) of this Section, the Agency will prorate the total number of NO
x
allowances allocated to budget EGUs that received allowances pursuant
to the criteria in subsection (e)(2) of this Section so that the total number
of allowances allocated to these budget EGUs does not exceed 15,043.
4)
If the total number of allowances allocated pursuant to subsection (e)(2)
of this Section is less than 15,043, which is the number of allowances
remaining in the trading budget after allocations have been made to
budget EGUs in subsection (e)(1) of this Section, the Agency will
allocate the remaining allowances to budget EGUs as follows:
A)
For budget EGUs in subsection (e)(1) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(1) of this Part.
B)
For budget EGUs in subsection (e)(2) of this Section, the pro-rata
allocation shall be determined by the heat input calculated
52
pursuant to Section 217.762(b) of this Part, multiplied by the
emission rate in Section 217.762(a)(2) of this Part.
5)
The Agency will allocate allowances from the new source set-aside,
pursuant to Section 217.768 of this Part, to budget EGUs that
commenced commercial operation after May 1, 2006 and that have not
operated for the full 2006 control period.
6)
As of April 30, 2010, if the number of allowances in the new source set-
aside exceeds 3% of the total number of tons of NO
x
emissions in the
trading budget apportioned to budget EGUs as determined pursuant to
Section 217.768(i) and (j) of this Part, the number of allowances above
3% will be allocated to budget EGUs receiving allowances pursuant to
this subsection (e).
7)
The Agency will report these allocations to USEPA by April 1, 2007,
except for allocations from the new source set-aside, which the Agency
will report by May 1, 2010.
f)
In 2011 (or the eighth year) of the program and annually thereafter:
1)
The Agency will apportion the available NO
x
allowances to each budget
EGU based on its heat input determined in Section 217.762(b) of this
Part, multiplied by:
A)
For budget EGUs that commenced commercial operation prior to
January 1, 1995, the NO
x
emission rate determined in Section
217.762(a)(1) of this Part.
B)
For budget EGUs that commenced commercial operation on or
after January 1, 1995, the NO
x
emission rate determined in
Section 217.762(a)(2) of this Part.
2)
The Agency will allocate allowances from the new source set-aside,
pursuant to Section 217.768 of this Part, to budget EGUs that
commenced commercial operation after the control period four years
prior to the year in which allocations are made and that have not
operated for the full control period four years prior to the year in which
the allocations are being made.
3)
As of April 30, 2011, if the number of allowances in the new source set-
aside exceeds 3% of the total number of tons of NO
x
emissions in the
trading budget apportioned to budget EGUs as determined pursuant to
Section 217.768(e) and (f) of this Part, the number of allowances above
53
3% will be allocated to budget EGUs receiving allowances pursuant to
this subsection (f).
4)
The Agency will report these allocations to USEPA by April 1 of each
year that is three years prior to the year in which the allocations are
being made, except for allocations from the new source set-aside, which
the Agency will report by May 1 of each year in which the allocations
are being made.
BOARD NOTE: Because of litigation involving the NO
x
SIP Call, Michigan v. EPA, No. 98-
1497, 2000 WL 180650 (D.C. Cir. March 3, 2000), the years defining the control periods may
change. Should this occur, the dates set forth under each year will be considered to adjust
correspondingly.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.768
New Source Set-Asides for “New” Budget EGUs
a)
“New” budget EGUs
1)
A “new” budget EGU is one that commenced commercial operation on
or after January 1, 1995, and does not receive allowances pursuant to
Section 217.764 of this Part.
2)
“New” budget EGUs must have an allowance for every ton of NO
x
emitted during the control period as provided in Section 217.756(d) of
this Part.
3)
A “new”budget EGU may request from the Agency a number of
allowances that is not more than the number of allowances for which it is
eligible, as determined in subsection (e) of this Section.
b)
The Agency shall apportion allowances from the new source set-aside as
follows:
1)
For 2004, 2005, and 2006, to budget EGUs that commenced commercial
operation on or after January 1, 1995; and
2)
For 2007 and thereafter, to budget EGUs that have not operated the full
control period four years prior to the control period for which the
allocation is being made.
c)
The Agency will establish a new source set-aside for each control period. Each
new source set-aside will be allocated allowances equal to:
54
1)
5% of the EGU trading budget in 2004, 2005, and 2006, which is 1,535
allowances, subject to adjustment to reflect additions or deletions to the
EGU trading budget;
2)
2% of the EGU of the trading budget in 2007 and thereafter, which is
614 allowances, subject to adjustment to reflect additions or deletions to
the EGU trading budget.
3)
As of April 30 of the applicable year, beginning in 2009 and thereafter,
if the number of allowances in the new source set-aside is greater than or
equal to 3% of the total number of tons of NO
x
emissions in the trading
budget apportioned to budget EGUs, which is 921 allowances, subject to
adjustment to reflect additions or deletions to the EGU trading budget,
pursuant to subsections (i) and (j) of this Section, the number of
allowances above 3% will be allocated to budget EGUs receiving
allowances pursuant to Section 217.764 of this Part. These allowances
shall be allocated on a pro-rata basis.
d)
The account representative of a “new” budget EGU under subsection (a) of this
Section may obtain allowances from the new source set-aside by submitting to
the Agency a request, in writing or in a format specified by the Agency, to be
allocated allowances for the current control period from the new source set-
aside. The allocation request for each applicable control period must be
submitted after the date on which the Agency issues a construction permit to the
budget EGU and before March 1 of the control period for which the allocation
is requested.
e)
In an allocation request under subsection (d) of this Section, the account
representative may request allowances for a control period in a number that does
not exceed the projected heat input in mmbtu during the applicable control
period multiplied by the more stringent of 0.15 lb/mmbtu or the permitted
emission rate, but no more stringent than 0.055 lb/mmbtu. The projected heat
input shall be determined as set forth below, divided by 2000 lbs/ton:
1)
For “new” budget EGUs that have heat input from at least three control
periods prior to the allocation year, the average of the budget EGU’s two
highest seasonal heat inputs from the control periods one to three years
prior to the allocation year;
2)
For “new” budget EGUs that have heat input from only two control
periods prior to the allocation year, the average of the budget EGU’s
seasonal heat inputs from the control periods one and two years prior to
the allocation year;
55
3)
For “new” budget EGUs that have seasonal heat input from only the
control period prior to the allocation year, the heat input from that
control period; or
4)
For “new” budget EGUs that have commenced commercial operation but
have not operated for at least 77 days of the control period prior to the
allocation year, the budget EGU’s maximum design heat input for the
control period as designated in the construction permit.
f)
Beginning in 2007, the Agency will review and allocate allowances pursuant to
each allocation request, contingent upon receiving payment pursuant to
subsection (k) of this Section, by April 15 of the applicable year, as follows:
1)
Upon receipt of the allocation request, the Agency will determine
whether the request is consistent with the requirements of subsections (d)
and (e) of this Section and will make any necessary adjustments to the
request to ensure that the control period and the number of allowances
requested are consistent with those requirements of subsections (d) and
(e) of this Section.
2)
If the new source set-aside for the control period for which allowances
are requested has a number of allowances greater than or equal to the
total number requested by all “new” budget EGUs, the Agency will
allocate the number of allowances requested to the “new” budget EGUs.
3)
If the new source set-aside for the control period for which allowances
are requested has a number of allowances less than the total number of
allowances requested by all “new” budget EGUs, the Agency will
allocate the available allowances to the “new” budget EGUs on a pro-
rata basis, based on the number of allowances requested.
g)
For “new” budget EGUs that commenced commercial operation on or after
January 1, 1995, but prior to January 1, 2004, the Agency will notify the
account representative of the number of allowances that have been allocated to
the “new” budget EGU by March 30 of the applicable year. There will be no
charge for allowances received under this subsection.
h)
For “new” budget EGUs that commenced commercial operation on or after
January 1, 2004, the Agency will notify by March 30 of the applicable year the
account representative of the number of allowances that are eligible for purchase
for the “new” budget EGU pursuant to the requirements of subsection (k) of this
Section. If the Agency does not receive payment by April 15 of the applicable
year, the account representative will forfeit his/her eligibility to purchase the
allowances offered. The Agency will make available for purchase those
forfeited allowances on a pro-rata basis to “new” budget EGUs that received
56
allocations pursuant to subsection (f)(2) of this Section, up to the number of
allowances requested by each account representative. Such additional
allocations are subject to the purchase requirements of subsection (k) of this
Section, to the extent applicable.
i)
For “new” budget EGUs that have commenced commercial operation but have
operated for 76 or fewer days of the control period in 2003, USEPA will deduct
allowances to account for the actual utilization of the EGU during the 2004
control period consistent with the provisions of 40 CFR 96.42(e). Any
allowances allocated by the Agency for such “new” budget EGUs that are not
used for compliance during the 2004 control period shall be returned to the
Agency’s new source set-aside account.
j)
For the years 2004, 2005, and 2006, any allowances that are not allocated
pursuant to subsections (g), (h) and (i) of this Section will be allocated on a pro-
rata basis to the budget EGUs listed in Appendix F of this Part. There will be
no charge for allowances received under this subsection.
k)
Fees for new source set-aside allowances:
1)
“New” budget EGUs that commence commercial operation on or after
January 1, 2004, that obtain allowances allocated from the new source
set-aside shall pay for such allocations pursuant to Section 9.9 of the
Act.
2)
The price of allowances from the new source set-aside shall be:
A)
The average price at which NO
x
allowances are traded in the
interstate NO
x
Trading Program for the preceding control period;
and
B)
For 2004 only, the price shall be the average price at which NO
x
allowances were traded in 2003 in the Ozone Transport Region.
3)
The fees collected by the Agency from the sale of allowances will be
distributed pro-rata to budget EGUs receiving allowances pursuant to
Section 217.764 of this Part on the basis of allocated allowances subject
to Agency administrative costs assessed pursuant to Section 9.9 of the
Act.
l)
A “new” budget EGU will become an existing budget EGU and will receive
allowances pursuant to the requirements of Section 217.764 of this Part, as
follows:
57
1)
For a budget EGU that commences commercial operation between and
including January 1, 1995, and April 30, 2003, the budget EGU will be
allocated allowances in 2004 for the 2007 control period and will become
an existing budget EGU on May 1, 2007.
2)
For a budget EGU that commences commercial operation after April 30,
2003, the budget EGU will become an existing budget EGU in the
control period for which it receives an allocation pursuant to Section
217.764 of this Part. It will be considered a “new” budget EGU and
will receive its allowances from the new source set-aside in the
intervening years from start-up until it receives allocations pursuant to
Section 217.764 of this Part.
BOARD NOTE: Because of litigation involving the NO
x
SIP Call, Michigan v. EPA, No. 98-
1497 2000 WL 180650 (D.C. Cir. March 3, 2000), the years defining the control periods may
change. Should this occur, other dates in this Section will be considered to adjust as necessary.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.770
Early Reduction Credits for Budget EGUs
If a budget EGU reduces its NO
x
emission rate as required by the applicable provisions of
subsection (c) of this Section in the 2001, 2002, or 2003 control period, for use in the 2004
control period, or later control periods authorized by USEPA, the account representative may
request early reduction credits (ERCs) for such reductions, and the Agency will allocate ERCs
to the budget EGU in accordance with the following:
a)
Each budget EGU for which the account representative requests any ERCs
under subsection (d) of this Section shall monitor NO
x
emissions in accordance
with 40 CFR 96, subpart H, as incorporated by reference in Section 217.104 of
this Part, starting with the control period prior to the control period for which
ERCs will first be requested and for each control period for which ERCs will be
requested. For example, if ERCs are requested for reductions made in the 2001
control period, the budget EGU must have implemented the applicable
monitoring for the 2000 control period. The unit’s monitoring system
availability shall be not less than 90 % during the control period prior to the
control period in which the NO
x
emissions reduction is made and the unit must
be in compliance with any applicable State or federal emissions or emissions-
related requirements.
b)
The NO
x
emission rate and heat input under subsections (c) through (e) of this
Section shall be determined in accordance with 40 CFR 96, subpart H.
58
c)
Each budget EGU for which ERCs are requested under subsection (d) of this
Section must have reduced its NO
x
emission rate for each control period for
which ERCs are requested, as follows:
1)
For budget EGUs subject to the requirements of Title IV of the CAA and
not included in a NO
x
averaging plan pursuant to 40 CFR 72 and 76, as
incorporated by reference in Section 217.104 of this Part, at least 30%
less than the NO
x
emission rate specified in the applicable Title IV
permit or other applicable federally enforceable permit.
2)
For budget EGUs subject to the requirements of Title IV of the CAA and
included in a NO
x
averaging plan pursuant to 40 CFR 72 and 76, at least
30% less than the annual emission rate required in the NO
x
averaging
plan in the applicable Title IV permit or other applicable federally
enforceable permit.
3)
For budget EGUs not subject to the requirements of Title IV of the
CAA, at least 30% less than the actual NO
x
emissions rate (lbs/mmbtu)
for the 2000 control period.
d)
The account representative of a budget EGU that meets the requirements of
subsections (a) through (c) of this Section may submit to the Agency a request
for ERCs for a EGU based on NO
x
emission rate reductions made by the EGU
in control periods 2001, 2002, and 2003, in accordance with subsection (c) of
this Section.
1)
The number of ERCs for any applicable control period shall be an
amount equal to the unit’s heat input for such control period multiplied
by the difference between the EGU’s NO
x
emission rate (meeting the
requirements of subsection (c) of this Section for the applicable control
period) and the EGU’s actual NO
x
emission rate for the applicable
control period, divided by 2000 lbs/ton, and rounded to the nearest ton.
2)
Upon request of the account representative, the ERC allowance
allocation for a particular EGU may be deposited in the source’s general
account rather than in the unit’s compliance account.
3)
The early reduction request must be submitted in a format specified by
the Agency by:
A)
November 1, 2001, for reductions made in the 2001 control
period;
B)
November 1, 2002, for reductions made in the 2002 control
period; and
59
C)
November 1, 2003, for reductions made in the 2003 control
period.
e)
In the event that the date for implementing the NO
x
SIP Call, May 31, 2004, is
delayed, the early reduction request must be submitted in accordance with any
rulemaking or guidance by USEPA on the distribution of the Compliance
Supplement Pool under the NO
x
SIP Call (63 Fed. Reg. 57356).
f)
The Agency will allocate ERCs to the budget EGUs meeting the requirements of
subsections (a) through (c) of this Section and covered by ERC requests meeting
the requirements of subsection (d) of this Section in accordance with the
following procedures:
1)
Upon receipt of each ERC request, the Agency will accept the request
only if the requirements of subsections (a) through (d) of this Section are
met and will make any necessary adjustment to the request to ensure that
the amount of the ERCs requested meets the requirements of subsections
(b) through (d) of this Section;
2)
The Agency shall allocate at least 15,261 ERCs over three years, as
follows:
A)
If USEPA has approved this Subpart as a SIP revision, not more
than one-half of the total ERC allowances for reductions made in
the control period in 2001;
B)
Not more than one-half of the total ERC allowances for
reductions made in the control period in 2002; and
C)
Any ERC allowances not allocated pursuant to subsection
(f)(2)(A) or (B) of this Section, for reductions made in the control
period in 2003.
3)
If the number of ERC allowances requested for a reduction achieved in
the control period in 2003 is less than or equal to the number of ERC
allowances designated for that control period in subsection (f)(2)(A) of
this Section, the Agency will allocate to each budget EGU one allowance
for each accepted ERC request;
4)
If the number of ERC allowances requested for a reduction achieved in
the control period in 2003 is greater than the number of ERC allowances
designated for that control period in subsection (f)(2)(A) of this Section,
the Agency will allocate to each budget EGU allowances for accepted
requests on a pro-rata basis.
60
g)
The Agency will notify the account representative submitting an ERC request
for the subsequent control period of the number of ERC allowances that will be
allocated to each budget EGU for that control period as follows:
1)
By March 1, 2002, for ERCs requested for and earned in the 2001
control period;
2)
By March 1, 2003, for ERCs requested for and earned in the 2002
control period; and
3)
By March 1, 2004, for ERCs requested for and earned in the 2003
control period.
h)
By May 1, 2004, the Agency will submit to USEPA the ERC allocations made
by the Agency under this Section. USEPA will record such allocations to the
extent that they are consistent with the requirements of this Section.
i)
ERC allowances recorded under subsection (h) of this Section may be deducted
for compliance under 40 CFR 96.54, as incorporated by reference in Section
217.104 of this Part, for the control period in 2004 or such additional control
periods as may be specified by USEPA. Notwithstanding 40 CFR 96.55(a),
USEPA will deduct as retired any ERC allowances that are not deducted for
compliance in accordance with 40 CFR 96.54 for the control period in 2004.
j)
ERC allowances are treated as banked allowances in 2004 for the purposes of 40
CFR 96.55(a) and (b).
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.774
Opt-In Units
a)
Any operating fossil fuel-fired stationary boiler, combustion turbine, combined
cycle system, cement kiln or stationary internal combustion engine in the State
may qualify under this Subpart to become a budget opt-in unit if it:
1)
Is not a budget EGU under Section 217.754 of this Part;
2)
Vents all of its emissions to a stack;
3)
Has documented heat input for more than 876 hours in the six months
immediately preceding the submission of an application for an initial
budget permit under subsection (d) of this Section;
4)
Is not covered by a retired unit exemption under 40 CFR 96.5;
61
5)
Is not covered by the low-emitter exemption under Section 217.754(c) of
this Part; and
6)
Is not located at a source listed in Appendix D of this Part.
b)
Except as otherwise provided in this Part, a budget opt-in unit shall be treated as
a budget EGU for purposes of applying this Subpart and 40 CFR 96.
c)
Authorized account representative:
1)
If an opt-in unit is located at the same source as one or more budget
EGUs, it shall have the same account representative as those budget
EGUs.
2)
If the opt-in unit is not located at the same source as one or more budget
EGUs, the owner or operator of the opt-in unit shall submit a complete
account certificate of representation under 40 CFR 96.13.
d)
To apply for a budget permit, the account representative of a unit meeting the
qualifications of subsection (a) of this Section must, except as provided under
Section 217.778(f) of this Part, submit to the Agency:
1)
A budget permit application for the unit that:
A)
Meets the requirements under Section 217.758 of this Part; and
B)
Contains provisions for a change in the regulatory status of the
unit to a budget opt-in unit under Section 217.754 of this Part
pursuant to the provisions of Section 217.780(b) of this Part.
2)
A monitoring plan for the unit in accordance with 40 CFR 96, subpart
H.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.776
Opt-In Process
The owner or operator of a unit meeting the qualifications of Section 217.774(a) of this Part
may submit an application for a budget permit for a budget opt-in unit under Section
217.774(d) of this Part. The Agency will issue or deny a budget permit for such opt-in unit in
accordance with Section 217.758 of this Part and the following:
a)
The Agency will determine, on an interim basis, the sufficiency of the
monitoring plan accompanying the initial application for a budget permit for an
62
opt-in unit. A monitoring plan is sufficient, for purposes of interim review, if
the plan contains information demonstrating that the NO
x
emission rate and heat
input of the unit are monitored and reported in accordance with 40 CFR 96,
subpart H. A determination of sufficiency shall not be construed as acceptance
or approval of that unit's monitoring plan.
b)
If the Agency determines that the unit's monitoring plan is sufficient under
subsection (a) of this Section and after completion of the monitoring system
certification under 40 CFR 96, subpart H, the NO
x
emission rate and the heat
input of the unit shall be monitored and reported in accordance with 40 CFR 96,
subpart H, for one full control period during which the monitoring system
availability is not less than 90 % and during which the unit is in full compliance
with any applicable State or federal emissions or emissions-related
requirements.
c)
Based on the information monitored and reported under subsection (b) of this
Section, the unit's baseline heat rate shall be calculated as the unit's total heat
input (in mmbtu) for the control period and the unit's baseline NO
x
emission
rate shall be calculated as the unit's total NO
x
emissions (in lbs) for the control
period divided by the unit's baseline heat rate.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.778
Budget Opt-In Units: Withdrawal from NO
x
Trading Program
a)
Requesting withdrawal. To withdraw from the NO
x
Trading Program, the
account representative of a budget opt-in unit shall submit to the Agency a
request to withdraw from the NO
x
Trading Program and to withdraw the budget
permit effective as of a specified date between (and not including) September 30
and May 1. The submission shall be made no later than 90 days prior to the
requested effective date of withdrawal.
b)
Conditions for withdrawal.
1)
Before a budget opt-in unit may withdraw from the NO
x
Trading
Program and the budget permit may be withdrawn under this Section, the
following conditions must be met:
A)
For the control period immediately before the withdrawal is to be
effective, the account representative must submit to the Agency
an annual compliance certification report in accordance with 40
CFR 96.30.
B)
If the budget opt-in unit has excess emissions for the control
period immediately before the withdrawal is to be effective,
63
USEPA has deducted from the budget opt-in unit's compliance
account, or the overdraft account of the NO
x
budget source where
the budget opt-in unit is located, the number of allowances
required in accordance with 40 CFR 96.54(d) for the control
period.
2)
After the requirements for withdrawal under subsection (b)(1) of this
Section are met, USEPA will deduct from the opt-in unit's compliance
account, or the overdraft account of the budget source where the budget
opt-in unit is located, allowances equal in number to any allowances
allocated to that unit under Section 217.782 of this Part for the same or
earlier control period for which the withdrawal is to be effective.
USEPA will close the budget opt-in unit's compliance account and will
establish, and transfer any remaining allowances to, a new general
account for the owners and operators of the opt-in unit. The account
representative for the budget opt-in unit shall become the account
representative for the general account.
c)
A budget opt-in unit that withdraws from the NO
x
Trading Program shall
comply with all requirements under the NO
x
Trading Program concerning all
years for which such budget opt-in unit was a budget opt-in unit, even if such
requirements arise or must be complied with after the withdrawal takes effect.
d)
Notification.
1)
After the requirements for withdrawal under subsections (a) and (b) of
this Section are met (including deduction of the full amount of
allowances required), the Agency will revise the budget permit indicating
a specified effective date for the withdrawal that is after the requirements
in subsections (a) and (b) of this Section have been met and that is prior
to May 1 or after September 30.
2)
If the requirements for withdrawal under subsections (a) and (b) of this
Section are not met, the Agency will issue a notification to the owner or
operator and the account representative of the budget opt-in unit that the
opt-in unit's request to withdraw its budget permit is denied. If the
budget opt-in unit's request to withdraw is denied, the budget opt-in unit
shall remain subject to the requirements for a budget opt-in unit.
e)
Reapplication upon failure to meet conditions of withdrawal. If the Agency
denies the budget opt-in unit's request to withdraw, the account representative
of the budget opt-in unit may submit another request to withdraw in accordance
with subsections (a) and (b) of this Section.
64
f)
Ability to return to the NO
x
Trading Program. Once an opt-in unit withdraws
from the NO
x
Trading Program and its budget permit is withdrawn under this
Section, the account representative may not submit another application for a
budget permit under Section 217.774(d) of this Part for the unit prior to the date
that is four years after the date on which the budget permit with opt-in
conditions is withdrawn.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.780
Opt-In Units: Change in Regulatory Status
a)
Notification. When an opt-in unit becomes a budget opt-in unit under Section
217.754(d) of this Part, the owner or operator shall notify the Agency and
USEPA in writing of such change in the opt-in unit's regulatory status within 30
days after such change.
b)
Any permit application that provides for a change in the regulatory status of a
unit to a budget opt-in unit pursuant to Section 217.774(d)(1)(B) of this Part and
is included in a budget permit is effective on the date on which such opt-in unit
becomes a budget opt-in unit under Section 217.754 of this Part.
c)
USEPA action.
1)
USEPA will deduct from the compliance account for the budget opt-in
unit under this Section, or the overdraft account of the budget source
where the budget opt-in unit is located, allowances equal in number to
and allocated for the same or a prior control period as:
A)
Any allowances allocated to the budget unit (as an opt-in unit)
under Section 217.782 of this Part for any control period after the
last control period during which the unit's budget permit was
effective; and
B)
If the effective date of any budget permit under subsection (b) of
this Section is during a control period, the allowances allocated to
the budget opt-in unit (as an opt-in unit) under Section 217.782 of
this Part for the control period multiplied by the ratio of the
number of days in the control period, starting with the effective
date of the budget permit under subsection (b) of this Section,
divided by the total number of days in the control period.
2)
The account representative shall ensure that the compliance account of
the budget opt-in unit under subsection (b) of this Section, or the
overdraft account of the budget source where the budget opt-in unit is
located, contains the allowances necessary for completion of the
65
deduction under subsection (c)(1) of this Section. If the compliance
account or overdraft account does not contain sufficient allowances,
USEPA will deduct the required number of allowances, regardless of the
control period for which they were allocated, whenever allowances are
recorded in either account.
3)
For every control period during which any budget permit under
subsection (b) of this Section is effective, the budget opt-in unit under
subsection (b) of this Section will be treated, solely for purposes of
allowance allocations under Section 217.764 or 217.768 of this Part, as a
unit that commenced operation on the effective date of the budget permit
under subsection (b) of this Section and will be allocated allowances in
accordance with Section 217.764 or 217.768 of this Part.
4)
Notwithstanding subsection (c)(2) of this Section, if the effective date of
any budget permit under subsection (b) of this Section is during a control
period, the following number of allowances will be allocated to the
budget opt-in unit under subsection (b) of this Section or under Section
217.764 or 217.768 of this Part for the control period: the number of
allowances otherwise allocated to the budget opt-in unit under Section
217.764 or 217.768 of this Part for the control period multiplied by the
ratio of the number of days in the control period, starting with the
effective date of the budget permit under subsection (b) of this Section,
divided by the total number of days in the control period.
d)
When the owner or operator of an opt-in unit does not renew the budget permit
for the budget opt-in unit issued pursuant to Section 217.774(d), USEPA will
deduct from the budget opt-in unit's compliance account, or the overdraft
account of the budget source where the budget opt-in unit is located, allowances
equal in number to and allocated for the same or a prior control period as any
allowances allocated to the budget opt-in unit under Section 217.782 of this Part
for any control period after the last control period for which the budget permit is
effective. The account representative shall ensure that the budget opt-in unit's
compliance account or the overdraft account of the budget source where the
budget opt-in unit is located contains the allowances necessary for completion of
such deduction. If the compliance account or overdraft account does not contain
sufficient allowances, USEPA will deduct the required number of allowances,
regardless of the control period for which they were allocated, whenever
allowances are recorded in either account.
e)
After the deduction under subsection (d) of this Section is completed, USEPA
will close the opt-in unit's compliance account. If any allowances remain in the
compliance account after completion of such deduction and any deduction under
40 CFR 96.54, USEPA will close the opt-in unit's compliance account and will
establish, and transfer any remaining allowances to, a new general account for
66
the owner or operator of the opt-in unit. The account representative for the opt-
in unit shall become the account representative for the general account.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.782
Allowance Allocations to Budget Opt-In Units
a)
Allowance allocations:
1)
By the December 31 immediately before the first control period for
which the budget permit is effective, the Agency will allocate allowances
to the budget opt-in unit and submit to USEPA the allocation for the
control period in accordance with subsection (b) of this Section.
2)
By no later than the December 31 after the first control period for which
the budget permit is in effect and the December 31 of each year
thereafter, the Agency will allocate allowances to the budget opt-in unit
and submit to USEPA allocations for the next control period, in
accordance with subsection (b) of this Section.
b)
For each control period for which the budget opt-in unit has a budget permit,
the budget opt-in unit will be allocated allowances in accordance with the
following procedures:
1)
The heat input (in mmbtu) used for calculating allowance allocations will
be the lesser of:
A)
The opt-in unit's baseline heat input determined pursuant to
Section 217.776(c) of this Part; or
B)
The opt-in unit's heat input, for the control period in the year
prior to the year of the control period for which the allocations
are being calculated, as determined in accordance with 40 CFR
96, subpart H.
2)
The Agency will allocate allowances to the budget opt-in unit in an
amount equaling the heat input (in mmbtu) determined under subsection
(b)(1) of this Section multiplied by the lesser of:
A)
The unit's baseline NO
x
emission rate (in lbs/mmbtu) determined
pursuant to Section 217.776(c) of this Part; or
B)
The lowest NO
x
emissions limitation (calculated in lbs/mmbtu)
under State or federal law that is applicable to the budget opt-in
unit for the year of the control period for which the allocations
67
are being calculated during the control period, regardless of the
averaging period to which the emissions limitation applies.
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.Appendix D
Non-Electrical Generating Units
COMPANY ID # / NAME
UNIT DESIGNATION
UNIT DESCRIPTION
12
3
A E STALEY MANUFACTURING CO
115015ABX
85070061299
COAL-FIRED BOILER 1
115015ABX
85070061299
COAL-FIRED BOILER 2
115015ABX
73020084129
BOILER #25
ARCHER DANIELS MIDLAND CO EAST PLANT
115015AAE
85060030081
COAL-FIRED BOILER 1
115015AAE
85060030081
COAL-FIRED BOILER 2
115015AAE
85060030081
COAL-FIRED BOILER 3
115015AAE
85060030082
COAL-FIRED BOILER 4
115015AAE
85060030082
COAL-FIRED BOILER 5
115015AAE
85060030082
COAL-FIRED BOILER 6
115015AAE
85060030083
GAS-FIRED BOILER 7
115015AAE
85060030083
GAS-FIRED BOILER 8
CPC INTERNATIONAL INC.
031012ABI
91020069160
COAL-FIRED BOILER 6
031012ABI
73020146041
BOILER SERIAL 15813
031012ABI
73020146042
BOILER SERIAL 15812
031012ABI
73020146043
GAS FIRED BOILER NO 4
031012ABI
73020147045
BOILER SERIAL 18345
031012ABI
73020147046
GAS FIRED BOILER NO 5
GREAT LAKES NAVAL STATION
097811AAC
78080071011
BOILER # 5
097811AAC
78080071011
BOILER # 6
INDIAN REFINING LIMITED PARTNERSHIP
101805AAC
72110297015
BOILER 18601
101805AAC
72110297016
BOILER 18602
101805AAC
72110297017
BOILER 18603
JEFFERSON SMURFIT CORPORATION
119010AAL
72120426001
BLR 7-COAL FIRED
68
MARATHON OIL CO ILLINOIS REFINING DIVISION
033808AAB
72111291055
BOILER #3 OIL,REF GAS
FIRED
033808AAB
72111291056
BOILER #4 REF GAS,OIL
FIRED
MOBIL JOLIET REFINING CORP
197800AAA
72110567002
AUX BOILER-REFINERY
GAS FULL FIRE IF COGEN
DOWN
197800AAA
86010009043
STATIONARY GAS
TURBINE
PEKIN ENERGY COMPANY
179060ACR
73020087019
QUANTUM - USI DIVISION
063800AAC
72100016013
BOILER # 1
063800AAC
72100016013
BOILER # 2
063800AAC
72100016014
#3 GAS FIRED BOILER
063800AAC
72100016016
#5 GAS FIRED BOILER
063800AAC
72100016017
#6 BOILER
QUANTUM - USI DIVISION
041804AAB
72121207108
BOILER NO 1
041804AAB
72121207109
BOILER NO 2
041804AAB
72121207110
BOILER NO 3
041804AAB
72121207111
BOILER NO 4
041804AAB
72121207112
BOILER NO 5
SHELL OIL CO WOOD RIVER MFG COMPLEX
119090AAA
72110633080
BOILER NO 15
119090AAA
72110633081
BOILER NO 16
119090AAA
72110633082
BOILER NO 17
U S STEEL - SOUTH WORKS
031600ALZ
82010044013
NO. 6 BOILER,#5 POWER
STATION (FUEL-NAT.GAS)
031600ALZ
82010044014
NO 1 BLR NG
UNIV OF ILL - ABBOTT POWER PLANT
019010ADA
82090027006
BOILER #7 (265 MBTU)
69
UNO-VEN COMPANY
197090AAI
72110253037
BOILER 43-B-1
(Source: Added at ____ Ill. Reg. ________, effective ____________________)
Section 217.Appendix F
Allowances for Electrical Generating Units
Company
Name/ ID
#
Generating
Unit
Designatio
n
EGU
Designatio
n
NO
x
Budget
Allowa
nces
80% of
NO
x
Budget
Allowa
nces
50% of
NO
x
Budget
Allowa
nces
2004,
2005,
2006
Allowa
nces
2007,
2008
Allowa
nces
2009,
2010
Allowa
nces
1
2
3
456789
Company Totals
No
NSSA
No
NSSA
No
NSSA
5%
NSSA
2%
NSSA
2%
NSSA
Ameren Energy Generating Company
135803AA
A
Coffeen 1 Coffeen 1
550
440
275
523
431
270
135803AA
A
Coffeen 2 Coffeen 2
945
756
473
898
741
463
077806AA
A
G. Tower 3 Boiler 7
55
44
28
52
43
27
077806AA
A
G. Tower 3 Boiler 8
44
35
22
42
35
22
077806AA
A
G. Tower 4 Boiler 9
199
159
100
189
156
98
033801AA
A
Hutsonville
3
Boiler 5
161
129
81
153
126
79
033801AA
A
Hutsonville
4
Boiler 6
129
103
65
123
101
63
135805AA
A
Meredosia
1
Boiler 1
33
26
17
31
26
16
135805AA
A
Meredosia
1
Boiler 2
23
18
12
22
18
11
135805AA
A
Meredosia
2
Boiler 3
23
18
12
21
18
11
135805AA
A
Meredosia
2
Boiler 4
28
22
14
27
22
14
135805AA
A
Meredosia
3
Boiler 5
432
346
216
410
339
212
70
135805AA
A
Meredosia
4
Boiler 6
28
22
14
27
22
13
079808AA
A
Newton 1 Newton 1
1,101
881
551
1,046
863
539
079808AA
A
Newton 2 Newton 2
1,074
859
537
1,020
842
526
Ameren Eng. Gen. Co. Totals
4,825
3,860
2,413
4,584
3,783
2,364
AES
057801AA
A
D. Creek
D. Creek
914
731
457
868
717
448
143805AA
G
Edwards 1 Edwards 1
251
201
126
239
197
123
143805AA
G
Edwards 2 Edwards 2
368
294
184
350
288
180
143805AA
G
Edwards 3 Edwards 3
655
524
328
622
513
321
AES Totals
2,188
1,750
1,094
2,079
1,715
1,072
CWLP
167120AA
O
Dallman 1 Boiler 31
141
113
71
134
111
69
167120AA
O
Dallman 2 Boiler 32
202
162
101
192
158
99
167120AA
O
Dallman 3 Boiler 33
474
379
237
450
372
232
167120AG
Q
G. Turbine
#2
G. Turbine
#2
91
73
46
86
71
45
167120AA
O
Lakeside 7 Lakeside 7
47
38
24
45
37
23
167120AA
O
Lakeside 8 Lakeside 8
42
34
21
40
33
21
CWLP Totals
997
798
499
947
782
489
Midwest Generation
063806AA
F
Collins 1
Collins 1
302
242
151
287
237
148
063806AA
F
Collins 2
Collins 2
305
244
153
290
239
150
063806AA
F
Collins 3
Collins 3
469
375
235
446
368
230
063806AA
F
Collins 4
Collins 4
290
232
145
275
227
142
71
063806AA
F
Collins 5
Collins 5
458
366
229
435
359
224
031600AIN Crawford 7 Crawford 7
365
292
183
347
286
179
031600AIN Crawford 8 Crawford 8
463
370
232
440
363
227
031600AM
I
Fisk 19
Fisk 19
523
418
262
497
410
256
031600AM
I
Fisk
Peaker
GT 31-1
975974
031600AM
I
Fisk
Peaker
GT 31-2
975974
031600AM
I
Fisk
Peaker
GT 32-1
975974
031600AM
I
Fisk
Peaker
GT 32-2
975974
031600AM
I
Fisk
Peaker
GT 33-1
975875
031600AM
I
Fisk
Peaker
GT 33-2
975875
031600AM
I
Fisk
Peaker
GT 34-1
975875
031600AM
I
Fisk
Peaker
GT 34-2
975875
197809AA
O
Joliet 6
Boiler 5
119
95
60
113
93
58
197809AA
O
Joliet 7
Boiler 71
455
364
228
432
357
223
197809AA
O
Joliet 7
Boiler 72
709
567
355
673
556
347
197809AA
O
Joliet 8
Boiler 81
748
598
374
711
587
367
197809AA
O
Joliet 8
Boiler 82
497
398
249
472
390
244
179801AA
A
Powerton 5 Boiler 52
739
591
370
702
579
362
179801AA
A
Powerton 5 Boiler 51
739
591
370
702
579
362
179801AA
A
Powerton 6 Boiler 61
739
591
370
702
579
362
179801AA
A
Powerton 6 Boiler 62
739
591
370
702
579
362
097190AA
C
Waukegan
6
Boiler 17
199
159
100
189
156
98
72
097190AA
C
Waukegan
7
Waukegan
7
376
301
188
357
295
184
097190AA
C
Waukegan
8
Waukegan
8
667
534
334
634
523
327
097190AA
C
Peaker
GT 31-1
543442
097190AA
C
Peaker
GT 31-2
543542
097190AA
C
Peaker
GT 32-1
543543
097190AA
C
Peaker
GT 32-2
543543
197810AA
K
Will
County 1
Will
County 1
364
291
182
346
285
178
197810AA
K
Will
County 2
Will
County 2
354
283
177
336
278
173
197810AA
K
Will
County 3
Will
County 3
449
359
225
427
352
220
197810AA
K
Will
County 4
Will
County 4
766
613
383
728
601
375
Midwest Generation Totals
11,926 9,541
5,963 11,330 9,350
5,844
Dom. Energy
021814AA
B
Kincaid 1 Kincaid 1
792
634
396
752
621
388
021814AA
B
Kincaid 2 Kincaid 2
873
698
437
829
684
428
Dom. Energy Totals
1,665
1,332
833
1,581
1,305
816
El. Energy Inc.
127855AA
C
Joppa 1
Joppa 1
481
385
241
457
377
236
127855AA
C
Joppa 2
Joppa 2
515
412
258
489
404
252
127855AA
C
Joppa 3
Joppa 3
513
410
257
487
402
251
127855AA
C
Joppa 4
Joppa 4
384
307
192
365
301
188
127855AA
C
Joppa 5
Joppa 5
463
370
232
440
363
227
127855AA
C
Joppa 6
Joppa 6
524
419
262
498
411
257
El. Energy Inc. Totals
2,880
2,304
1,440
2,736
2,258
1,411
73
DMG
157851AA
A
Baldwin 1 Baldwin 1 1,114
891
557
1,058
873
546
157851AA
A
Baldwin 2 Baldwin 2
931
745
466
884
730
456
157851AA
A
Baldwin 3 Baldwin 3 1,318
1,054
659
1,252
1,034
646
125804AA
B
Havana 1-5 Boiler 1
000000
125804AA
B
Havana 1-5 Boiler 2
000000
125804AA
B
Havana 1-5 Boiler 3
000000
125804AA
B
Havana 1-5 Boiler 4
000000
125804AA
B
Havana 1-5 Boiler 5
000000
125804AA
B
Havana 1-5 Boiler 6
000000
125804AA
B
Havana 1-5 Boiler 7
000000
125804AA
B
Havana 1-5 Boiler 8
000000
125804AA
B
Havana 6
Boiler 9
547
438
274
520
429
268
155010AA
A
Hennepin 1 Hennepin 1
149
119
75
142
117
73
155010AA
A
Hennepin 2 Hennepin 2
540
432
270
513
423
265
183814AA
A
Vermilion
1
Vermilion
1
17
14
9
16
13
8
183814AA
A
Vermilion
2
Vermilion
2
31
25
16
30
24
15
119020AA
E
Wood
River 1
Wood
River 1
000000
119020AA
E
Wood
River 2
Wood
River 2
000000
119020AA
E
Wood
River 3
Wood
River 3
000000
119020AA
E
Wood
River 4
Wood
River 4
219
175
110
208
172
107
74
119020AA
E
Wood
River 5
Wood
River 5
714
571
357
678
560
350
DMG Totals
5,580
4,464
2,790
5,301
4,375
2,734
SIPCO
199856AA
C
Marion 1
Marion 1
14
11
7
13
11
7
199856AA
C
Marion 2
Marion 2
10
8
5
10
8
5
199856AA
C
Marion 3
Marion 3
30
24
15
29
23
15
199856AA
C
Marion 4
Marion 4
511
409
256
485
401
250
SIPCO Totals
565
452
283
537
443
277
Union Electric
119105AA
A
Turbine
Turbine
432432
119105AA
A
Venice 1
Venice 1
10
85985
119105AA
A
Venice 2
Venice 2
13
10
7
12
10
6
119105AA
A
Venice 3
Venice 3
653653
119105AA
A
Venice 4
Venice 4
764754
119105AA
A
Venice 5
Venice 5
15
12
8
14
12
7
119105AA
A
Venice 6
Venice 6
16
13
8
15
13
8
119105AA
A
Venice 7
Venice 7
221211
119105AA
A
Venice 8
Venice 8
221221
Union Electric Totals
75
60
38
71
59
37
TOTAL
30,701 24,561 15,351 29,166 24,070 15,044
(Source: Added at ____ Ill. Reg. __________, effective _____________)
IT IS SO ORDERED.
75
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
the above opinion and order was adopted on the 21st day of December 2000 by a vote of 7-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board