ILLINOIS POLLUTION CONTROL BOARD
    June 8, 2000
    PEOPLE OF THE STATE OF ILLINOIS,
    Complainant,
    v.
    BODINE ELECTRIC COMPANY,
    an Illinois corporation,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 98-145
    (Enforcement - Air)
    ORDER OF THE BOARD (by E.Z. Kezelis):
    On June 1, 2000, the complainant filed a stipulation and proposal for settlement
    accompanied by a motion requesting relief from the hearing requirement of Section 31(c)(1) of
    the Environmental Protection Act (Act) (415 ILCS 5/31(c)(1) (1998)).
    Pursuant to Section 31(c)(2) of the Act, the complainant may file with the Board a
    stipulation and proposal for settlement accompanied by a request for relief from the hearing
    requirement. 415 ILCS 5/31(c)(2) (1998). Unless the Board determines that a hearing is
    needed, the Board is required to publish notice of the stipulation and proposal for settlement and
    request for relief from the hearing requirement.
    Accordingly, the Board directs the Clerk of the Board to cause publication of the
    required newspaper notice for the stipulation and proposal for settlement and request for relief
    from the hearing requirement. Any person may file a written demand for hearing within 21
    days of the published notice. If a hearing is requested, the Board will deny the request for
    relief and schedule a hearing.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the 8th day of June 2000 by a vote of 7-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board