ILLINOIS POLLUTION CONTROL BOARD
    July 27, 2000
    IN THE MATTER OF:
    PETITION OF ILLINOIS AMERICAN
    WATER COMPANY’S ALTON PUBLIC
    WATER SUPPLY REPLACEMENT
    FACILITY DISCHARGE TO THE
    MISSISSIPPI RIVER FOR ADJUSTED
    STANDARD FROM 35 ILL. ADM. CODE
    302.203, 304.106, AND 304.124
    )
    )
    )
    )
    )
    )
    )
    )
    )
    AS 99-6
    (Adjusted Standard - Water)
    ORDER OF THE BOARD (by C.A. Manning):
    On July 14, 2000, petitioner Illinois American Water Company (IAWC) and the Illinois
    Environmental Protection Agency filed a joint motion for expedited decision. The parties
    explain that, pursuant to statements that IAWC made to the Illinois Commerce Commission,
    IAWC’s new water treatment facility in Alton, Illinois must begin operation as scheduled by
    December 31, 2000. In order to begin operation by that date, IAWC must begin start-up
    procedures by early October 2000. The start-up procedures will test and refine the ability of the
    new facility to serve the Alton area. The start-up procedures will also allow IAWC to address
    any problems prior to December 31, 2000.
    The Board grants the parties’ joint motion for expedited decision consistent with the
    Board’s resources and decision times.
    IT IS SO ORDERED.
    Board Member G.T. Girard abstained.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the
    above order was adopted on the 27th day of July 2000 by a vote of 5-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board