ILLINOIS POLLUTION CONTROL BOARD
    May 23,
    1991
    IN THE MATTER OF:
    )
    CERTAIN HAZARDOUS WASTES FROM
    )
    R91-11
    PRIMARY ZINC SMELTING
    AND
    )
    (Emergency Rulemaking)
    REFINING,
    35 Iii.
    Adm. Code
    )
    721.104(b) (7) (U)
    )
    ORDER OF THE BOARD
    (by J. Anderson):
    This matter is before the Board on the May 20,
    1991 Motion
    for Extension of Time,
    filed by the Agency, and the May 21,
    1991
    request of Big River Zinc Corp.
    for Board delay in further
    action.
    The Agency states that the unavailability of certain key
    personnel, the shortened time required by the Board for response,
    and other unavoidable elements of delay make it impossible for
    the Agency to respond before May 22,
    1991,
    by FAX,
    or May 23,
    1991,
    by mail.
    Big River Zinc states that it anticipates comment
    from USEPA headquarters
    in Washington,
    D.C., that would clarify
    the comments submitted by USEPA Region
    5 and the status of the
    K066 hazardous waste listing in light of the remand in American
    Mining Congress v.
    EPA,
    907 F.2d 1179
    (D.D.C.
    1990).
    The Board acknowledges the receipt of the agency response,
    and hereby grants the Agency-requested extension to file its
    response to the Board Order of May 14,
    1991.
    In the interest of
    obtaining USEPA comment, the Board will delay action on the
    emergency rule until Big River Zinc or the Agency comes before
    the Board with a motion for further action.
    Nevertheless,
    in the
    absence of such a motion, the Board will proceed to take action
    in this matter no later than Thursday, June 20,
    1991.
    IT IS SO ORDERED.
    I, Dorothy M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board
    do hereby certify that the above Order was adopte~ç1on the
    day of
    ~
    ~
    ,
    1991,
    by a vote of
    ~
    Dorothy M.//Gunn, Clerk
    Illinois i~6llutionControl Board
    122—355