ILLINOIS POLLUTION CONTROL BOARD
June 20,
1991
CHEMICAL WASTE MANAGEMENT,
)
Petitioner,
)
PCB 91—98
)
(Provisional Variance)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
ORDER OF THE BOARD
(J. C. Marlin):
This matter comes before the Board upon receipt
of an Agency
Recommendation dated June
18,
1991.
The recommendation refers to
a request from Petitioner,
Chemical Waste Management for a 30 day
provisional variance from the 90—day on—site limitations
for
hazardous wastes set forth
in
35 Iii.
Adrn. Code 722.134(b).
Upon receipt of the request the Agency issued its
recommendation,
concluding that the hazardous wastes must remain
on—site for longer than 90 days due to unforeseen,
temporary and
uncontrollable circumstances and failure
to grant the requested
30-day provisional variance would impose an arbitrary or
unreasonable hardship on Petitioner.
The responsibilities of the Agency and the Board
in these
short—term provisional variances are different from the
responsibilities
in standard variances.
See Ill.
Rev. Stat.
1989,
ch. 11l~,pars.
1035(b)
&
(C).
In provisional variances
it
is the responsibility of the Agency to make the technical
determinations and finding of arbitrary or unreasonable
hardship.
The Board’s responsibility is to adopt
a formal Order,
to assure the formal maintenance of the record,
to assure the
enforceability of the variance, and to provide notification of
the action by a press release.
Having received the Agency recommendation finding that
a
denial of the request relief would impose an arbitrary and
unreasonable hardship the Board hereoy grants Petitioner a
provisional variance from 35 Ill. Mm. Code 722.134(b)
from May
6,
1991 to June
5,
1991
IT
IS SO ORDERED.
J. Dumelle and B.
Forcade concurred.
—2--
I,
Dorothy M.
Gunn, Clerk of the Illinois Pollution Control
Board,
hereby certify that
t
bove Order was adopted on
the
~
day of ___________________________
,
1991,
by a
vote of
__________
~1l
Dorothy M.
c~4fin, Clerk
Illinois P~4utionControl Board