ILLINOIS POLLUTION CONTROL BOARD
    March 15, 2001
    BUILDER’S PLUMBING SUPPLY,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 01-125
    (UST – Appeal)
    (90-Day Extension)
    ORDER OF THE BOARD (by C.A. Manning):
    On March 12, 2001, the parties filed a joint notice of extension of the 35-day period to
    appeal a decision of the Illinois Environmental Protection Agency (Agency). As the notice
    does not specify a shorter period, the Board will grant the extension for a total of 125 days
    from the Agency’s January 31, 2001 decision. The Board hereby grants petitioner an
    extension of the time period for filing an appeal in the matter until June 5, 2001, pursuant to
    Section 40(a)(1) of the Environmental Protection Act (415 ILCS 5/40(a)(1) (1998)). Because
    the Board has timely received a joint notice of extension, the Board extends the appeal period
    to the aforementioned date. The Board will dismiss this matter and close the docket if
    petitioner fails to file an appeal on or before that date.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the 15th day of March 2001 by a vote of 7-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board