ILLINOIS POLLUTION CONTROL BOARD
December
3,
1992
HARLEM TOWNSHIP,
)
Petitioner,
PCB 92—83
v.
)
(Underground Storage Tank Fund
Reimbursement Determination)
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
ORDER OF THE
BOARD
(by B.
Forcade):
This matter comes before the Board on a Motion for
Reconsideration and Motion for Extension of Time filed by Harlem
Township on November 23,
1992.
The motion states that the
counsel for Harlem Township was not timely informed of the
Board’s October 16,
1992 decision in this matter.
The counsel
for petitioner claims that she first learned of the Board’s
decision on November 18,
1992 through a third party.
The
statutory time period for filing a motion for reconsideration is
35 days.
Therefore the deadline for filing such a motion in this
case was November 20,
1992.
The petitioner notes that because
the decision was not transmitted to the petitioner it cannot
supply the specific reasoning for reconsideration at this time.
The motion requests the Board to reconsider its decision and
allow an extension of time, until December 23,
1992,
for
petitioner to supplement the motion for reconsideration.
The Board’s records do not indicate that a copy of the
decision was sent to counsel for the petitioner.
The Board
grants the motion for the extension of time.
Harlem Township is
granted an extension of time, until December 23,
1992, in which
to supplement its motion for reconsideration.
IT IS SO ORDERED.
I, Dorothy M.
Gunn,
Clerk of the Illinois Pollution Control
Board, hereby certify
th~t
the above order was adopted on the
2 ~
~-
day of
~
,
1992, by a vote of
J”l.
/J~../’
Dorothy M. ~nn,
Clerk
Illinois Pd)Llution Control Board
0 137-05t47