ILLINOIS POLLUTION CONTROL BOARD
June 17,
1993
RONALD E. TEX and
SUSAN
D.
TEX,
)
)
Complainant,
v.
)
PCB 90—182
(Enforcement)
S.
SCOTT COGGESHALL and
)
COGGESHALL CONSTRUCTION COMPANY,)
CHESTER BROSS, MIKE BROSS,
)
CONSTRUCTION COMPANY,
)
)
Respondent.
OPINION AND ORDER OF THE BOARD
(by G. T. Girard):
On October 29,
1992,
the Board entered an interim opinion
and order finding respondents in violation of Section 901.102(a)
of the Board’s noise rules.
(35 Ill. Adm. Code 901.102(a).)1
The BOard directed respondents to prepare a study of the
“economic reasonableness and technical practicability of the
control options outlined by Gregory Zak as well as any additional
options which it may deem appropriate to reduce the noise
emissions from the asphalt plant”.
(10/29/92 at 16.)2
The
Board directed the respondents to file such study no later than
March 15,
1993,
and allowed the complainants until April 15,
1993
to respond.
The Board notes that on December 3,
1992,
the Board granted
a motion by the respondent suggesting the death of
S.
Scott
Coggeshall and dismissed S.
Scott Coggeshall from the proceeding.
The respondents filed the study on March 15,
1993.
Complainant,
after being granted an extension of time by the Board on April
22,
1993,
filed its response on May 5,
1993.
On May 14,
1993,
respondents filed a request for leave to file a reply.
The Board
hereby grants the motion to file a reply pursuant to 35
Ill.
Adm.
Code 101.241(c).
1
The Board directs readers to the October 29,
1992, Interim
opinion and Order
for
case details which will
not
be
repeated
herein.
2
The Board will cite the October 29,
1992,
Interim Opinion
and Order as “10/29/92 at
_“;
the Board will cite the respondents
report as “R.rep. at
_“
and the respondents reply as “R.rply at
_“;
the Board will cite the complainants response as “C.res.
at
—
‘I
0
L~3-O
I 57
2
DISCUSSION
In detemining the proper remedy in an enforcement case, the
Board must consider the factors set forth in Section 33(c)
of the
Environmental Protection Act
(Act).
(415 ILCS 5/33.)
Section
33(c)
of the Act provides:
In making its orders and determinations, the Board
shall take into consideration all the facts and
circumstances bearing upon the reasonableness of the
emissions,
discharges,
or deposits involved including,
but not limited to:
1.
the character and degree of injury to,
or
interference with the protection of the
health, general welfare and physical property
of the people;
2.
the social and economic value of the
pollution source;
3.
the suitability or unsuitability of the
pollution source to the area in which it is
locate, including the question of priority of
location in the area involved;
4.
the technical practicability and economic
reasonableness of reducing or eliminating the
emissions, discharges or deposits resulting
from such pollution source; and
5.
any subsequent compliance.
The Board has previously considered the Section 33(c)
factors in this case.
(See 10/29/93 at 13—15.)
The Board finds
that the additional filings submitted pursuant to the October 29,
1993 Board order provide no new evidence regarding the Section
33(c)
factors in this record,
except for Section 33(c) (iv).
Therefore, the Board will not reiterate its previous holdings on
Sections 33(c)(i)(ii)(iii)
and
(v).
The discussion following
summarizes the parties’ positions regarding the economic
reasonableness and technical practicability (Section 33(c) (iv))
of the control options.
Respondents’ study.
Respondents retained the services of Dr. Paul Schomer of
Schomer
& Associates to study the noise problem at the plant.
According to respondents the study concentrates on determining
the predominant noise sources and developing noise mitigation
01
L~.3-Q
158
3
evaluation of the remedies recommended by Mr. Greg Zak of the
Agency.
Dr. Schomer’s study utilizes noise emission measurements
from the various components of the plant to determine the
contribution of each component to the overall noise emissions.
The noise measurements were obtained by monitoring the emissions
during full plant operation and when gradually decreasing the
plant operation sequentially by turning off the various plant
components3.
(R.rep.
Exh.
B at 4.)
Based on the results of the
noise monitoring,
the study concludes that the predominant
sources of noise from the plant are the bag house blower
(high
frequencies)
and burner operation
(low frequencies).
(R.rep.
Exh.
B at 7—S.)
In addition,
the study notes that the mechanical
equipment noise is important in the 1000
—
2000 Hz range, and the
fire blower may contribute significantly at certain frequencies.
(R.rep Exh. B at 7-8.)
The study also includes a comparison of the noise emission
levels at full plant operation with the applicable standards
under the Board regulations.
The comparison indicates that noise
levels must be reduced by
6,
3,
7, and
4 dB at 125,
1000,
2000,
and 4000 Hz bands,
respectively, to comply with the Board
Standards.
(R.rep Exh.
B,
Fig.
11.)
The respondents’ study includes an evaluation of the
following options for reducing the noise emission levels from the
plant:
1.
The construction of barrier walls around the
burner and generator as well as adding a stack
silencer;
2.
Re—engineering of the plant
(as suggested by
Gregory Zak);
3.
Encapsulating the plant
(as suggested by Gregory
Zak); and
4.
Moving the plant.
(R.rep.
at 2.)
With regard to the suggestions offered by Mr.
Zak
(points
2
and 3), Dr. Schomer’s study notes that both options would be very
expensive.
According to the study,
the cost of re—engineering
(and rebuilding)
the plant or enclosing the plant in a reinforced
concrete structure could easily cost $100,000 or more.
(R.rep.
~ The plant components include generator, mechanical equipment
and material feeds,
bag house blower, and fire blower.
0iL~.3~0159
4
Exh. B at 10-il.)
In addition, the study notes that enclosing
the plant in a reinforced concrete structure without noise
control would result in very high noise levels within the
structure.
Such high noise levels would violate Occupational
Safety and Health Administration
(OSHA) noise limits.
(R.rep.
Exh. B at 10-11.)
Further, with regards to the suggestion that
the plant be moved,
respondents state the costs to move the plant
as well as obtaining an alternative site are “not economically
reasonable”.
(R.rep.
at 2.)
Dr. Schomer’s study recommends that the following steps be
taken to alleviate the noise levels:
1.
Retain the wooden barrier wall installed around
the generator or replace the same with a more
permanent structure to minimize the generator
noise.
The cost of a new permanent wall is
estimated to be less than $10,000;
2.
Install a stack silencer to reduce the bag house
blower sound emitting from the stack.
The cost of
the silencer is estimated to be in the order of
$5,000;
3.
Install a barrier wall close to the inlet of the
fire—burner fan to reduce the burner noise.
The
cost of the barrier wall will be in the order of
$10, 000.
(R.rep. Exh. B at
12..)
The study concludes that the recommended solutions are
technically feasible,
and the implementation of the same would
result in significant reduction of the noise levels at the
complainants’ structure.
Further, the study notes that
implementing all the recommendations may not result in overall
compliance with the Board standards in the 1000 and 2000 Hz bands
due to mechanical equipment sound.
(R.rep.
Exh. B at 13.)
Finally, Dr. Schomer’s study notes that any further significant
reductions in the noise levels over the reduction that will be
realized by the recommended methods would require the re—
engineering of the plant.
(R.rep. Exh.
B at 13.)
Complainants’ response.
Complainants ask that the Board “direct that the plant be
moved as a technically practical and economically reasonable
means of bringing compliance” with the Board’s regulations.
(C.res. at 4.)
In support of the position that moving the plant
is economically reasonable and technically feasible, the
complainants provided an affidavit from Michael J. McGillicuddy,
vice president and Macomb Branch Manager of Illinois Valley
Li
I
4 ~
—
S
Paving Company.
Mr. McGillicuddy states that the cost of moving
a “Batch type plant”
is approximately $75,000.
(C.res.
Exh. B.)
Complainants specifically responded to the remaining control
options as well.
With regard to encapsulating the plant,
complainants state:
“the Schoiner report agrees with Mr.
Zak that
encapsulating the plant in concrete is the most expensive and
least—feasible alternative.”
(C.res.
at 2.)
Regarding re—
engineering the plant, the complainants state:
“Mr.
Schomer
dismisses,
in a cursory way, the possibility of re—engineering
because it would cost over $100,000.00.”
(C.res.
at 2.)
The complainants maintain the Dr.
Schonier recommends the
least expensive procedure (that of constructed barrier walls and
adding a stack silencer), however;
least expensive is not
“synonymous with economic reasonableness” according to
complainants.
(C.res. at 2.)
Further, the complainants state:
“Despite Mr. Schomer’s very considerable training, experience and
writings qualifying him as an acoustical expert, this very
considerable technical background does not establish him as an
economic expert qualified to evaluate the ‘economic
reasonableness’ of any option from the prospective
(sic
of the
cost of that option compared to the economic benefit to the plant
to the respondents and the present operator.”
(C.res. at 3.)
Complainants also argue that respondents study does not
address,
“in other than a conclusory manner”, the economic
reasonableness of any control measures except in Exhibits C and
D.
(C.res. at 3.)
The complainants then assert that Exhibit D,
an affidavit by Mike Hillyer,
“is substantially different from
the testimony of witness Michael Hillyer”.
(C.res. at 3.)
Respondents’ reply.
Respondents reply that the testimony of Mr. Hillyer did not
address “site availability for the asphalt plant nor did he
address costs of site amenities similar to the Deere Road plant
site”.
(R.rply at 2.)
The respondents assert that those costs
are addressed for the first time in Exhibit D of its report.
The
respondents also point out that the Illinois Valley Paving
Company operates a drum-mix plant while the Coggeshall plant is a
batch plant.
(R.rply at 2.)
The respondent argues that it would
require
6 weeks to move the Coggeshall plant and cost $100,000.
(R.rply at 2.)
Section 33(c) (iv).
The Board notes that all the alternatives considered
in the
respondent’s noise study appear to be technically feasible.
However, the Board notes that there
is a significant difference
between the implementation cost of the options recommended by the
respondent and the complainants,
The option recommended by the
I
~,
‘)
(~
UI”rU
U
6
respondents’ study, which includes the construction of barrier
walls and installation of a silencer would cost approximately
$25,000.
Whereas, the option supported by the complainants,
which essentially requires the plant to be moved to another
location would cost over $100,000.
The options suggested by Mr.
Greg Zak, which
includes encapsulation and re—engineering would
also cost more than $100,000.
Therefore, the Board must evaluate
the economic reasonableness of implementing the various options
in crafting a remedy.
The Board notes that both parties seem to agree that
encapsulating the plant, which has been estimated to cost
$100,000 is expensive.
Regarding re-engineering the plant,
Mr.
Zak stated that this option
is not practicable because of the
cost which would exceed $100,000.
(Tr. 1/8/92 at 106-110;
10/29/92 at 14.)
Dr. Schomer agrees that re-engineering would
cost over $100,000.
The complainants offer no evidence to refute
either Mr.
Zak or Dr.
Schomer.
The respondents’ study includes two different estimates of
the moving costs.
The first estimate, which includes the cost of
moving a “batch” plant to a new site ranges from $60,000 to
$100,000.
(R.rep.
Exh.
C)
The Second estimate, which includes
only the cost of acquiring land, establishing gas service, rock
base,
fencing, maintenance buildings and building hook—ups ranges
from $256,416 to $411,416.
(R.rep. Exh.
D.)
The evidence
submitted by the complainants indicate that moving the plant
would cost $75,000.
(C.res.
Exh. B.)
The moving cost reflects
dismantling, moving, and erecting a batch type plant at a new
location.
The complainants estimate that the total cost of
making the plant operable at the new site would be
in the range
of $90,000 to $125,000.
(C.res. Exh.
B.) The total cost
includes,
in addition to moving cost, the cost of site
preparation,
land acquisition, and initial operation.
The Board
notes that there is
a significant difference between the
estimates of the moving costs provided by the complainants and
the respondents.
However, the Board notes that even if it
considers the lower cost estimate, the cost of moving the plant
would be in excess of $100,000, which amounts to the same as that
of encapsulation or re—engineering.
Therefore, the Board finds moving the plant to be also in
the same category of the expensive options.
In view of this, the
Board finds that encapsulation, re—engineering the plant,
or
moving the plant are not economically reasonable remedies.
The
Board believes that requiring the implementation of these options
would place a significant financial burden on the respondents.
Finally, the option recommended by the respondents, which
includes the construction of barrier walls and installation of a
stack silencer would cost in the order of $25,000.
iJ
~~3-Cj
I 62
7
The Board finds that the noise control methods recommended
by the respondents to be an economically reasonable and
technically feasible approach to reduce the noise problems at the
plant.
The Board notes that the this option costs relatively
less than the other expensive alternatives discussed above, but
achieves a significant reduction in the noise levels.
The Board
recognizes that implementing the recommended option may still
result in a violation of Section 901.102 standards by
1 to
2 dB
in the 1000 and 2000 Hz bands.
However, considering the cost
implications, the Board believes that the respondents’
recommended option is the most appropriate solution.
CONCLUSION
Although complainants request that the Board direct that the
plant be moved, the Board is reluctant to direct such a step in
this case.
As stated in the October
29,
1992, Opinion, the plant
is in a suitable location in an area zoned for industry.
The
Board finds that moving the source at a cost of over $100,000 to
be economically unreasonable.
Therefore,
after studying all the options the Board finds
that construction of barrier walls and the addition of a stack
silencer are economically reasonable and technically practicable
solutions which will bring respondent into compliance.
However,
the Board notes that if the respondent is still
in violation of
Section 901.102 standards after implementation of the measures,
the respondent could be liable for civil penalties under the Act,
absent site—specific relief.
ORDER
Respondents shall take,
at a minimum, the following steps to
alleviate the noise emissions from the asphalt plant located in
Macomb, Illinois:
1.
Replace the existing wooden barrier wall around the
generator with a more permanent structure;
2.
Install a 24” by 72” stack silencer such as the
Industrial Acoustic Company’s IAC Model SL3 silencer;
and
3.
Construct a barrier wall as close to the inlet of the
fire-burner fan as feasible.
The barrier wall shall be
at least 2.5 feet taller than the top of the opening
for the burner
in the end of the drum.
The length of
the wall shall be three times its height and it shall
be centered at the burner.
The barrier wall shall be
01
L3-0
163
8
made of sound absorbing material such as SoundBlox~or
IAC Moduline~
IT IS SO ORDERED
Board Member R.
C.
Fleinal dissents.
Section 41 of the Environmental Protection Act (415 ILCS
5/41
(1992)) provides for the appeal of final orders of the Board
within 35 days.
The Rules of the Supreme Court of Illinois
establish filing requirements.
(See also 35 Ill. Adm. Code
101.246, Notion for Reconsideration.)
I, Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
Board, hereby certify that the above opinion a
order was
adopted on the
/7~Z
day of
____________________
1993, by a vote of
~,-/
~
A~’
~borothy
M.
Gi~in, Clei~k
Illinois Polijition Control Board
1)
~.3-OI 6~.