ILLINOIS POLLUTION CONTROL BOARD
    November 21,
    1991
    COMMONWEALTH EDISON COMPANY,
    )
    Petitioner,
    V.
    )
    PCB 91-29
    (Variance)
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    )
    Respondent,
    and
    ILLINOIS CHAPTER OF THE
    SIERRA CLUB,
    Intervenor.
    MR. ALAN
    P.
    BIELAWSKI,
    SIDLEY
    & AUSTIN, APPEARED ON BEHALF OF
    COMMONWEALTH EDISON COMPANY;
    MS. LISA NORENO APPEARED ON BEHALF OF THE ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY.
    OPINION AND ORDER OF THE BOARD
    (by R.C.
    Flemal):
    This matter comes before the Board upon a February 21,
    1991
    petition for variance filed by the Commonwealth Edison Company
    (“Edison”).
    Edison requests a five—year variance from the
    requirements
    of
    35
    Ill. Adm.
    Code 302.211(d),
    a subsection of the
    Board’s General Use Water Quality Standards for temperature,
    for
    the discharge from its Joliet, Will County,
    Crawford,
    and Fisk
    generating stations.
    On February 22,
    1991,
    the Illinois Chapter of the Sierra
    Club (“Sierra Club”)
    filed an objection to the variance and a
    petition to intervene.
    On March
    14,
    1991,
    the Board granted
    Sierra Club’s petition to intervene.
    Hearing was held in this
    proceeding on July 22,
    1991 in Joliet,
    Illinois.
    No members of
    the public were present.
    The Illinois Environmental Protection
    Agency. (“Agency”)
    failed to file a recommendation,
    but stated at
    hearing that its position is that a variance is not necessary
    based on its belief that Section 302.211(d)
    does not apply to
    Edison’s discharges.
    The Agency further stated that it does not
    oppose this variance request should the Board determine that
    a
    variance is necessary
    (Tr.
    at 12—13).
    127—17 7

    —2—
    Prior to the filing of the variance petition,
    Sierra Club
    filed suit against Edison in federal district court,
    asking that
    the court enjoin Edison from future alleged violations of Section
    302.211(d)
    at the Crawford,
    Fisk, and Will County plants,
    and to
    impose penalties on Edison for alleged past violations at these
    plants.
    Sierra Club also alleged that the Joliet Station
    discharges violated Section 302.211(d).
    A consent decree was
    entered in that federal court action under which Sierra Club
    agreed to withdraw its opposition to Edison’s request for
    variance in the instant proceeding before the Board.
    The consent
    decree also contained certain conditions which would apply should
    the Board grant this request for variance.
    A copy of the decree
    was originally submitted to the Board on July 30,
    1991,
    subject
    to United States Environmental Protection Agency
    (“USEPA”)
    review.
    USEPA completed its review and a revised copy of the
    consent decree
    (“revised decree”) was submitted to the Board on
    November
    8,
    1991.
    The Board grants Edison’s request for variance for the
    reasons presented below and subject to conditions contained in
    the Order below,
    for a period of five years from today’s date.
    DESCRIPTION OF FACILITIES
    Edison
    is a public utility primarily engaged
    in the
    production, purchase, transmission, distribution, and sale of
    electricity.
    Edison’s service area comprises roughly the
    northern third of Illinois,
    and is populated by approximately
    eight million people
    (Pet.
    at 1-2).
    Edison operates four generating stations
    (Joliet, Will
    County,
    Crawford,
    and Fisk)
    that discharge heat to the Des
    Plaines River or to waterways that are tributary to the Des
    Plaines River.
    Joliet Station
    Joliet Station is a steam-electric generating facility
    capable of producing 1,414 gross megawatts of electricity.
    The
    station
    is located in Will County,
    approximately one mile
    southwest of the City of Joliet, Illinois, adjacent to the Des
    Plaines River.
    Joliet Station consists of three coal-fired
    units, all of which utilize open cycle, once—through condenser
    cooling systems.
    The station has two thermal discharges to the ‘Des Plaines
    River; one from Unit #6 on the east bank of the river and the
    other from Units #7 and #8 on the west bank.
    The maximum design
    temperature rise in the circulating cooling water is
    approximately 9.4°F, with a total circulating water flow rate of
    2,620 cubic feet per second.
    Both thermal discharges flow into
    the Des Plaines River approximately one—half mile downstream of
    127—178

    —3—
    the Brandon Road Lock and Dam,
    at river mile 285, which is about
    seven miles upstream of the 1-55 Bridge.
    The annual average capacity factors of the Joliet Station
    over the past five years have ranged from 24.5
    to 39.9,
    with
    the five—year average of about 30.6.
    Edison’s capacity factor
    projections for the Joliet Station for the next five years range
    from 19.4
    to 31.7.
    Maximum operation of the Joliet Station
    generally occurs during Edison’s peak demand periods; that
    is,
    during day-time hours and during the summer months
    (Pet. at 3—
    4)
    Will County,
    Fisk,
    and Crawford Stations
    Will County,
    Crawford, and Fisk Stations
    (collectively, the
    “Canal Stations”)
    are steam electric generating facilities
    capable of producing 1154,
    581, and 342 gross megawatts of
    electricity, respectively.
    Will County Station is located in
    Romeoville,
    Illinois,
    near the intersection of the Chicago
    Sanitary and Ship Canal and Romeo Road.
    Crawford Station is
    located in Chicago, near the intersection of the Stevenson
    Expressway and Pulaski Avenue.
    Fisk Station is located near
    downtown Chicago,
    at the intersection of Loomis Street and the
    Chicago Sanitary and Ship Canal.
    The generating units of each
    Canal Station are coal—fired,
    and each utilizes open cycle,
    once—
    through condenser cooling systems.
    The Canal Stations discharge into the Chicago Sanitary and
    Ship Canal: Will County at river mile 295.5,
    Crawford at river
    mile 318.5, and Fisk at river mile 322.
    The maximum design
    temperature rise in the circulating cooling water is
    approximately 11.1°Ffor Will County, 12.0°Ffor Crawford, and
    12.2°Ffor Fisk.
    The annual average capacity factors over the past five
    years,
    and the projected annual average capacity factors for the
    next five years for the Canal Stations, are as follows:
    1986
    1991
    1992
    1996
    Will County
    28.2
    26.0
    Crawford
    21.9
    15.0
    Fisk
    21.7
    26.0
    As with Joliet Station, the Canal Stations are generally operated
    more during peak demand periods
    (Pet.
    at 4-5).
    APPLICABLE REGULATIONS
    Each of the discharges from these four generating stations
    is subject to secondary contact and indigenous aquatic life water
    quality standards
    (35 Ill.
    Adm. Code 303.441).
    The temperature
    127—179

    —4—
    standard for secondary contact waters
    (35 Ill. Adm.
    Code 302.408)
    requires that:
    temperature
    .
    .
    .
    not exceed 34°C(93°F)more than
    5
    of the time,
    or 37.8°C (100°F) at any time.
    35
    Ill.
    Adm. Code §302.408.
    However, the lower Des Plaines River between the Interstate 55
    Bridge and the head of the Illinois River
    (confluence of the Des
    Plaines River with the Kankakee River),
    a segment known as the
    “Five—Mile Stretch”,
    is subject to the more stringent general use
    water quality standards.
    Among other requirements, the general
    use standards governing temperature require that:
    the
    maximum temperature rise above natural
    temperatures shall not exceed 2.8°C(5°F); (Section
    35
    Ill.
    Adm. Code 302.211(d))
    and that the temperature of the water not exceed 16°C(60°F),
    during winter months
    (Dec. through Mar.)
    or 32°C(90°F), during
    summer months
    (Apr. through Nov.), more than 1
    of the hours
    in a
    12 month period ending in any month,
    and never exceed these
    temperatures by more than 1.7°C(3°F) (35 Ill. Adm.
    Code
    302.211(e)).
    THERMAL
    DEMONSTRATION
    In 1987, Edison requested that the Board determine, pursuant
    to 35
    Ill. Adm. Code 302.211(f),
    that the thermal discharges from
    the Joliet Station have not caused and cannot reasonably be
    expected to cause significant ecological damage to the general
    use waters.
    The Board found that Edison had made the requisite
    showing under 302.211(f)
    (In the Matter of:
    Proposed
    Determination of No Significant Ecological Damage for the Joliet
    Generating Station, PCB 87-93,
    105 PCB Op.
    149, November 15,
    1989.)
    In the course of PCB 87—93, the Sierra Club,
    also
    participating as an intervenor,
    argued that Edison had failed to
    make a sufficient showing of no significant ecological impact
    because,
    among other reasons, the Joliet plant contributed to
    violations of Section 302.211(d)
    and
    (e)
    in the waters of the
    Five-Mile Stretch.
    In response,
    Edison argued that these
    provisions were inapplicable, principally because Joliet Station
    discharges into secondary contact waters.
    Edison further
    committed to implement an operating plan for the Joliet Station
    which would ensure that the Joliet Station would limit its
    megawatt output as necessary to avOid exceedences of the monthly
    maximum temperature standard of.Section 302.211(e).
    In PCB 87-93, the Board addressed these issues as follows:
    12 9—180

    —5—
    The Board finds that 302.211(d)
    and
    (e) do apply to the
    effect of Edison’s discharges.
    Although Secondary
    Contact Standards may govern at the point of a
    particular discharge,
    it
    is possible for an entity
    located upstream of the beginning of the General Use
    waters to cause or contribute to exceedances
    (sic)
    of
    the General Use Water Quality Standards.
    In fact, the
    reason the Board required Edison to perform a thermal
    demonstration under subsection
    (f)
    is because the Board
    recognized that a source which discharges to Secondary
    Contact waters could affect downstream General Use
    waters.
    The Board finds, however, that in this proceeding
    the issues of whether violations of the 302.211
    standards have occurred in the Five—Mile Stretch and,
    if they have, whether Edison is responsible for them,
    is at best ancillary to the matters at hand.
    The only
    proper forum for the Board to hear allegations of
    violation of the Board’s rules is an enforcement action
    brought pursuant to Title VIII of the Illinois
    Environmental Protection Act.
    The Board cannot and
    will not here reach the issue of whether Edison
    is
    ir
    violation of any Board water quality standard.
    Consideration of whether there is non-compliance of the
    waters of the Five-Mile Stretch with the Board’s water
    temperature standards can enter the immediate case only
    where non—compliance stands as proof of significant
    ecological damage associated with Edison’s discharge.
    The Board finds that there
    is no substantive indication
    that any of the observed temperatures in the’ Five-Mile
    Stretch have caused significant ecological damage.
    PCB
    87—93
    at 19;
    105 PCB Op.
    at 167.
    Regarding whether Edison’s operating plan was acceptable to
    satisfy the requirements of Section 302.211(e),
    the Board found:
    The Board believes that Edison has a viable monitoring
    program
    .
    .
    .
    which, although not field tested at the
    time of hearing,
    is capable of assuring adjustments to
    operations should they prove necessary to ensure
    compliance.
    PCB 87—93 at 21; 105 PCB Op. at 169.
    HARDSHIP
    Edison believes that a requirement to come into immediate
    compliance with the Section 302.211(d)
    standards would result in
    arbitrary or unreasonable hardship.
    The hardship results from
    the difficulty in determining how to measure whether the Joliet
    Station discharge has been contributing to violations of the
    Section 302.211(d)
    standard, due to the distance from the Joliet
    127—181

    —6—
    Station discharge
    and’ the beginning of general use waters,
    and
    how to adjust plant operations based upon the measurements
    (Pet.
    at 8).
    Edison explains that for its plants that discharge directly
    to general use waters, compliance is demonstrated by showing that
    the area and dimensions of the discharge plume which is more than
    5°F above the temperature of the water at the intake1 is within
    the mixing zone constraints permitted by the Board’s regulations
    (35 Ill. Adm. Code 302.102).
    The two temperature measurements
    that are compared
    (i.e., the temperature of the water at the
    intake and the temperature at the edge of the mixing zone)
    are
    taken contemporaneously, because the 5°Fstandard applies at the
    point of discharge.
    Edison further states that from an
    operational perspective,
    it is relatively easy to determine the
    level at which a plant can operate without causing the standard
    to be violated.
    As the size of the plume begins to approach the
    size of an allowable mixing zone,
    the plant’s output
    is
    controlled to assure that the plume does not exceed the
    applicable restrictions
    (Pet.
    at 9).
    Edison submits that the Section 302.211(d)
    regulations
    cannot be applied to Joliet in the same manner, nor is
    a similar
    operational strategy viable.
    The 5°Ftemperature rise standard
    applies beginning at the 1-55 bridge.
    The bridge
    is’ about
    7
    miles downstream from the Joliet Station discharge.
    The water
    discharged from the station takes anywhere from 10 to 45 hours to
    travel to the 1-55 bridge.
    During that time interval, the
    temperature of the water
    in the river is influenced by a number
    of factors in addition to the Joliet discharge,
    such as diurnal
    radiation heating, evaporative and conductive heat exchange
    affected by air temperature,
    cloud cover, wind speed,
    and
    humidity; and other’ discharges of heated water into the river
    between the Joliet Station discharge and the 1-55 bridge.
    Edison
    believes that the time lag for effluent travel and other
    variables make operational changes designed to achieve compliance
    unworkable
    (Pet.
    at 10).
    The difficulties in temperature
    measurement comparison,
    operational changes,
    and possible future
    modelling are supported by affidavits of Jeffrey Smith and Dr.
    Forrest Holly submitted by Edison with its petition
    (Exhs. A and
    B, respectively).
    As explained below
    in the section concerning the compliance
    plan,
    Edison proposes to submit am adjusted standard petition or
    site-specific rulemaking petition to the Board,
    and requests the
    time in the instant proceeding to complete needed studies prior
    to submission of the proposal.
    Edison submits that while the
    studies are being conducted,
    it “will continue to be subject to
    1 The “natural temperature” of the water, as those terms are
    used in Section 302.211(d)
    is considered to be the temperature of
    the water at the intake to the plant.
    12 7—182

    —7—
    claims that its operations at Joliet and the Canal Stations
    violate §302.211(d),
    and thus subject to claims for substantial
    civil penalties and possibly drastic, though environmentally
    unjustified, judicially imposed deratings of its plants”
    (Pet. at
    15-16).
    Edison believes absent the grant of
    a variance,
    it
    appears that its only protection from such claims would be to
    build cooling towers at a very substantial cost or derate its
    units
    (Pet.
    at 16).
    The affidavit of~Jeffrey Smith explains that
    the cost to Edison of attempting to comply with §302.211(d)
    is
    likely to be upwards of $100 million (1988 estimate),
    if the
    company were required to install cooling towers.
    In addition,
    cooling,towers are likely to cause significant fogging in the
    area,
    particularly along State Route
    6.
    (Pet.
    Exh. A at 10).
    COMPLIANCE PLAN
    Edison has committed to initiate an adjusted standard or
    site-specific proceeding before the Board following completion of
    studies to be conducted (revised decree at ¶13).
    Edison states
    that it does not have the information necessary to meet its
    burden of proof in an adjusted standard or site—specific
    proceeding and discusses its plan as
    follows:
    The affidavit of Dr. Robert Otto (Exhibit
    C) explains
    that while there is a good deal of information,
    of
    a
    qualitative nature, supporting the conclusion that
    temperature
    is not the factor limiting the ecology of
    the Five-Mile Stretch, additional data and information
    is needed to support the preparation of analyses
    required to obtain site specific relief.
    To collect the needed data and information,
    Edison
    proposes to design and conduct various studies of the
    Five-Mile Stretch.
    The design and implementation plans
    for the studies would be developed in consultation with
    the appropriate environmental and conservation
    authorities.
    The overall objectives of the studies
    would be as follows:
    (1) measure and assess the
    physical contours and characteristics of the Five-Mile
    Stretch to better understand how the physical makeup of
    the river affects its ability to support and sustain
    aquatic life;
    (2) measure and compute the thermal
    environment in the waters of the Five-Mile Stretch to
    better understand the extent to which the waters are
    affected by the various heat inputs, particularly at
    locations where the physical habitat appears conducive
    to aquatic life propagation;
    (3)
    sample and analyze
    waters, sediments and organisms for toxic materials to
    determine the extent to which these materials may limit
    aquatic life
    in the Five—Mile Stretch; and
    (4)
    determine and access current populations of
    12 7—183

    —8—
    macrophytes, macroinvertibrates and fishes
    (Pet at 14—
    15)
    Dr.
    Otto estimates that the studies discussed above
    will take about four years to design and implement.
    Thereafter,
    it will take at least
    a year to prepare a
    report of the findings and conclusions, submit a
    petition for site specific relief to the Board and for
    the Board to deliberate and issue its decision.
    (Pet.
    at’ 14—15)
    In addition, the Board notes that the revised decree
    includes provisions on how the study is to be conducted,
    including working with all affected governmental agencies2 to
    develop the scope and duration of the study
    (to be completed in
    five years from any grant of variance),
    and working with Sierra
    Club and its experts in conducting the study.
    The revised decree
    further states:
    Edison
    and Sierra Club agree that there is
    a need to
    gather additional information concerning the ecology of
    the Chicago Sanitary and Ship Canal and the lower Des
    Plaines River and further assess the impacts industrial
    and municipal discharges are having on these waters.
    Following completion of such studies,
    Edison)
    and
    Sierra Club agree the Edison)
    shall propose that the
    Board
    promulgate thermal standards or alternative
    NPDES permit effluent limitations consistent with
    §316(a)
    of the Clean
    Water
    Act that would apply to
    Edison’s
    Plants in lieu of the existing standards.
    Revised decree at ¶7.
    ENVIRONMENTAL
    IMPACT
    In PCB 87—93,
    the Board found that Edison successfully
    demonstrated that the heat discharges from the Joliet Station
    have not caused and cannot be reasonably expected to cause
    significant ecological damage to the waters of the Five—Mile
    Stretch.
    In so doing, the Board also found that the temperature
    of the waters of the Five-Mile Stretch was not a factor limiting
    its quality,
    and that other factors continue to override the
    effect of temperature on the waterway.
    These overriding factors
    include loss of habitat due to channelization, disruption of
    habitat due to barge traffic,
    and the presence of heavy metals
    and other pollutants in the system (PCB 87—93 at 20).
    2 Agency, USEPA,
    and the Illinois Department of
    Conservation.
    12 7—184

    —9—
    Edison states that its projections for Joliet Station’s
    operations during the next five years are in line with the
    projections Edison presented to the Board in PCB 87—93.
    Edison
    further states that it will operate Joliet Station in accordance
    with an operating plan that ensures compliance with §302.211(e),
    as
    it committed to do
    in PCB 87-93
    (Pet.
    at 15—16).
    ‘DISCUSSION AND CONCLUSIONS
    In consideration of any variance, the Board determines
    whether,a petitioner has presented adequate proof that immediate
    compliance with the Board regulations at issue would’ impose an
    arbitrary or unreasonable hardship
    (Ill. Rev.
    Stat.
    1989,
    ch.
    111½, par.
    1035(a)).
    Furthermore, the burden is upon the
    petitioner to show that its claimed hardship outweighs the public
    interest in attaining compliance with regulations designed to
    protect the public
    (Willowbrook Motel
    v. Pollution Control.Board
    (1977),
    135 Ill.App.3d,
    481 N.E.2d,
    1032).
    Only with such
    showing can the claimed hardship rise to the level of arbitrary
    or unreasonable hardship.
    The Board finds that based upon the facts and circumstances
    of this case, denial of variance would impose an arbitrary or
    unreasonable hardship upon Edison.
    The hardship outweighs any
    risk of environmental harm posed by the heat discharges from
    Edison’s plants,
    for the time period of the variance, especially
    since interim standards are today imposed on the Joliet and Canal
    Stations
    in the following Board order.
    The interim standards are
    also allowed for in the revised decree upon grant of variance.
    A variance by its nature is
    a temporary reprieve from
    compliance with the Board’s regulations
    (Monsanto Co.
    v.
    IPCB
    (1977),
    67
    Ill.
    2d 276,
    367 N.E.
    2d 684),
    and compliance
    is to be
    sought regardless of the hardship that the task of eventual
    compliance presents an individual polluter
    (~.)
    Accordingly,
    except in certain special circumstances, a variance petitioner is
    required,
    as a condition to grant of variance, to commit to a
    plan that
    is reasonably calculated to achieve compliance withn
    the term of the variance.
    The Board finds that in this instance,
    extraordinary circumstances exist which allow for grant of
    variance even though compliance will not be achieved during the
    term of the variance.
    Included in these circumstances are the
    distal location of the Joliet Station and Canal Stations relative
    ‘to the point of application of the General Use Water Quality
    Standards, the unique nature of thermal discharges and unknown
    127—185

    —10—
    effect of those discharges on the receiving waterways3,
    and the
    study,
    which all parties agree is necessary.
    Furthermore,
    this situation is also extraodinary since
    whether Edison is actually violating the standards is not known
    and
    is also part of the subject of the study to be completed.
    Therefore, the Board believes that the circumstances
    in this
    instance call for departure from the norm, and grants variance
    even though the state of compliance of the petitioner is not now
    known,
    and may not be known during the term of the variance.
    The Board accordingly grants variance subject to conditions
    as indicated in the order below.
    In adding some of the terms of
    the consent decree to its order as conditions upon this grant of
    variance, the Board notes that it only includes those items that
    pertain to the interim standards and the study to be conducted.
    The Board specifically excludes those items pertaining to the
    conduct between Edison, the government agencies, and Sierra Club
    as being outside the purview of this variance proceeding and
    solely within the province of the revised decree.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law
    in this matter.
    ORDER
    Petitioner,
    Commonwealth Edison Company
    (“Edison”),
    is
    hereby granted variance from the temperature standards of 35
    Ill.
    Adm. Code 302.211(d),
    for the discharges from its Joliet, Will
    County,
    Crawford, and Fisk generating stations (hereinafter,
    “the
    Company’s Plants”), subject to the following conditions:
    (1)
    Variance terminates on November 21,
    1996,
    or when
    compliance
    is demonstrated, whichever is earlier.
    (2)
    Except as provided below,
    for the period the
    variance
    is in effect, the Company’s Plants
    shall comply with the following interim
    temperature standards (“Interim Standards”)
    to be measured at the 1-55 Bridge:
    January-March
    60°F
    In PCB 87—93,
    the Board also found that other limiting
    factors continue to exist that override the effect of temperature
    on this waterway, including loss of habitat due to
    channelization,
    disruption of habitat due to barge traffic,
    and
    the presence of heavy metals and other pollutants in the system.
    The Board expressed hope that this situation can be reversed in
    the not-distant future
    (PCB 87-93 at
    20,
    105 PCB Op.
    168).
    127—186

    —11—
    April 1—15
    70°F
    April 16—30
    75°F
    May 1—15
    80°F
    May 16—31
    85°F
    June
    88°F
    July-August
    90°F
    September
    86°F
    October
    75°F
    November
    65°F
    December
    60°F
    (3~ The Company’s Plants may cause the water
    temperature at the 1—55 Bridge to exceed the
    Interim Standards by no more than 3°Ffor 1
    of the hours in the twelve month period
    ending with any month.
    In addition,
    for each
    period from April through June that the
    Interim Standards are in effect, the
    Company’s Plants may cause the water
    temperature at the 1-55 Bridge to exceed the
    Interim Standards by no more than 3°Ffor an
    additional 30 hours.
    (4)
    The Interim Standards shall not constitute
    any evidence with regard to the appropriate
    level at which to set final thermal standards
    or alternative NPDES permit effluent
    limitations.
    (5)
    Edison shall initiate a study
    (the “Study”),
    which will include the following measures:
    a.
    Edison will retain a panel of experts
    qualified to formulate,
    direct and
    oversee the conduct’ of the Study;
    b.
    Edison shall use its best efforts to work
    with all affected governmental agencies,
    including the Illinois Environmental
    Protection Agency, the United States
    Environmental Protection Agency, and the
    Illinois Department of Conservation to
    develop the scope and duration of the Study;
    c.
    Edison shall use its best efforts to
    complete the Study and any proceedings
    before the Board to establish thermal
    standards or alternative effluent
    limitations
    for the Company’s Plants
    within five years.
    (6)
    Following completion of the Study,
    Edison
    shall initiate proceedings before the Board
    127—18’?

    —12—
    to establish thermal standards or alternative
    NPDES permit effluent limitations consistent
    with §316(a)
    of the Clean Water Act
    applicable to the Company’s Plants.
    (7)
    Edison shall install and use its best efforts
    to maintain 24—hour temperature monitors
    during the period of the Study at the
    following locations:
    a.
    On the Chicago Sanitary and Ship Canal
    above Edison’s Will County Station
    discharge;
    b.
    At the Brandon Road Lock and Dam, or,
    in
    the event Edison is not given permission
    to install
    a monitor at that location,
    at an alternate location agreeable to
    both Sierra Club and Edison;
    c.
    At the 1-55 Bridge on the Des Plaines
    River;
    d.
    On the Kankakee River,
    near Edison’s
    Braidwood Station.
    Within 45 days of the date of this Order, Petitioner shall
    execute and forward to Lisa Moreno, Division of Legal Counsel,
    Illinois Environmental Protection Agency,
    2200 Churchill Road,
    Post Office Box 19276,
    Springfield, Illinois 62794—9276,
    a
    Certification of Acceptance and Agreement to be bound to all
    terms and conditions of this variance.
    The 45-day period shall
    be held in abeyance’ during any period that this matter
    is being
    appealed.
    Failure to execute and forward the Certificate within
    45 days renders this variance void and of no force and effect as
    a shield against enforcement of rules from which variance was
    granted.
    The form of said Certification shall be as follows:
    CERTIFICATION
    I
    (We),
    hereby accept and agree to be bound by all terms and conditions
    of the Order of the Pollution Control Board
    in PCB 91-29 November
    21,
    1991.
    Petitioner
    Authorized Agent
    127—188

    —13—
    Title
    Date
    Section 41 of the Environmental Protection Act,
    Ill.
    Rev.
    Stat.
    1989 ch.
    111
    ½
    par.
    1041, provides for appeal of final
    Orders of the Board within 35 days.
    The Rules of the Supreme
    Court of Illinois establish filing requirements.
    ITIS
    SO
    ORDERED.
    I,
    Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board,
    hereby certify that the above, Opinion and Order was
    adopted on the
    ~
    day of
    ____________________,
    1991,
    by
    a vote of
    ______________
    .
    C
    ~
    ~
    Dorothy M. 4unn,
    Clerk
    Illinois P~’llutionControl Board
    12 7—189

    Back to top