ILLINOIS POLLUTION CONTROL BOARD
    June
    3,
    1993
    STATE BANK OF WHITTINGTON,
    )
    Petitioner,
    v.
    )
    PCB 92—152
    )
    (UST Fund)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    EDWARD
    W.
    DWYER AND KATHERINE
    D. HODGE APPEARED ON BEHALF OF THE
    PETITIONER;
    AND
    DANIEL
    P. MERRIMAN APPEARED ON BEHALF OF THE
    RESPONDENT.
    OPINION AND ORDER OF THE BOARD
    (by J. Anderson):
    This matter
    is before the Board on the October 13, 1992
    petition of the State Bank of Whittington
    (Bank).
    The Bank
    requests review of the September 14,
    1992 decision of the
    Illinois Environmental Protection Agency
    (Agency) regarding
    reimbursement of corrective action costs from the Leaking
    Underground Storage Tank Fund
    (Fund).’
    The Bank appeals the
    Agency’s denial of reimbursement for certain costs incurred by
    the Bank in response to a release of petroleum from its four
    underground storage tanks
    (UST).
    Hearing was held on December 16,
    1992 in Benton, Franklin
    County; no members of the public testified.
    The Bank and the
    Agency filed post-hearing briefs on February 16 and April
    20,
    1993 respectively.
    On May 5,
    1993,
    the Bank filed a post-hearing
    reply brief.
    PENDING MOTIONS
    The Board will first address two pending motions.
    Bank’s Second Motion to Supplement
    On March 11,
    1993,
    the Board granted the Bank’s February 16,
    1993 motion to supplement the record.
    On May
    3,
    1993, the Agency
    filed a response to the Board’s March 11 order to supplement the
    On September
    23,
    1992,
    the Agency issued another letter
    correcting a computation that changed the actual amount requested
    for reimbursement from $660,001.35 to $623,220.10.
    That the
    September
    14,
    1992 letter constitutes the Agency’s final decision
    is not in dispute.
    (Ex.
    F; Joint Ex. I.)
    01 L~.3-O023

    2
    record,
    in
    which
    it
    declined
    to
    file
    two
    original
    color
    photographs,
    asserting
    policy
    and
    statutory
    reasons.
    On
    May
    5,
    1993,
    the Board found the Agency’s response unpersuasive and
    ordered the original photographs to be filed.
    On May 10,
    1993,
    the Agency complied by filing a further response and the Bank’s
    original and complete December 19,
    1993 Corrective Action Report
    containing the two color photographs on p.
    18.
    The complete
    original
    report
    is
    hereby
    received
    into
    evidence.
    (Copies
    of
    the
    report are found in Agency Rec. Technical File Part 2 at 171-
    271.)
    On May 5,
    1993, the Bank filed a second motion to supplement
    the Agency record.
    The motion accompanied the Bank’s reply
    brief.
    On May 17,
    1993,
    the Agency filed a response in
    opposition.
    On May 25,
    1993,
    the Bank filed a reply to the
    Agency’s response.
    The requested supplement concerns certain
    records related to the UST appeal pending before the Board of
    DJM
    Oil Company,
    Inc.
    (DJM).
    (DJN Oil Company.
    Inc. v.
    IEPA,
    (October
    29,
    1992)
    PCB 92—163.)
    The
    DJN
    site
    is
    adjacent
    to
    the
    Bank’s
    site in Benton.
    The Bank requests that the record be
    supplemented
    with
    a)
    certain pages of
    DJN’s
    December 10,
    1991
    reimbursement
    application,
    and
    b)
    the
    September
    25,
    1992
    final
    Agency
    determination
    of
    DJM’s application for reimbursement, of
    which the Bank requests the Board to take official notice.
    Both
    documents accompany the motion.
    The Bank asserts that the supplemented information will
    render incorrect the impression, given by the testimony of Agency
    witness Ms. Becky Lockhart and in the Agency’s brief, that roller
    compactor charges are not corrective action and have never been
    reimbursed.
    Counsel for the Bank, who is also counsel for
    DJM
    in
    DJM’s appeal,
    states that the motion to supplement is necessary
    because the Agency has failed to timely file the
    DJM
    record with
    the Board.
    The Bank asserts that the open waiver in the
    DJM
    appeal had not relieved the Agency from its obligation to file
    the record within
    14 days,
    or November 11,
    1992.
    The Agency has
    yet
    to
    file
    the
    DJM
    record.
    The Agency asserts in opposition that:
    a)
    such materials
    were not part of the Agency’s actual administrative record in the
    instant appeal;
    b)
    the Bank did not provide a supporting
    affidavit; and c) the Agency did not consider,
    and should not
    have considered,
    such matters as evidence.
    The Agency further
    argued that such extrinsic evidence should not be offered as
    collateral
    impeachment
    or
    as
    a
    matter
    of
    estoppel.
    Regarding collateral impeachment, the Agency argues that
    “extrinsic evidence (evidence other than that coming from the
    witness
    on
    cross
    examination)
    may
    not
    be
    introduced
    to
    impeach
    a
    witness
    if
    a
    matter
    is
    considered
    collateral
    citation
    ommitted.”
    (Agency Resp.
    in opposition at 3,4).
    Also, the
    Agency
    argues
    that,
    while
    extrinsic
    evidence
    may
    be
    introduced
    to
    0! ~3-O02L~

    3
    contradict a witness,
    it may not relate solely to collateral
    matters citation
    omitted.”
    The Agency further argues that,
    absent a request by the Bank for leave to reopen the proofs and
    submit additional evidence
    -
    which the Bank did not make
    the
    proper time to have offered such material to impeach was at
    hearing when the Agency witness testified and where the issue
    could have been properly aired, not at this stage of the
    proceeding.
    Regarding estoppel, the Agency asserted that the Board
    rejected the the same position argued by the Bank in Southern
    Food Park,
    Inc.
    V.
    IEPA (December 17,
    1992),
    PCB 92-88.
    The
    Agency further argued that the Board has previously held that the
    issue is whether the disputed item passes the two—part corrective
    action test,
    not whether the Agency has ever previously
    reimbursed such an item.
    In support the Agency additionally
    cited Strube v.
    IEPA,
    (May 21,
    1992)
    PCB 91-20; Platolene 500 v.
    IEPA,
    (May
    7,
    1992)
    PCB 92-9; and Enterprise Leasing
    v.
    IEPA,
    (April
    9,
    1992), PCB 91—174.
    In the interests of bringing this dispute to resolution, the
    Board will accept the Bank’s May 25th reply even though the reply
    lacks a request for leave to file a reply pursuant to 35 Ill.
    Adm. Code 101.241
    (c).
    In essence, the Bank requests that the
    Board accept an accompanying affidavit, which the Bank explains
    was omitted from its second motion to supplement by inadvertance
    because of attorney’s haste to timely file the Bank’s reply
    brief.
    The Bank also asks that the Board consider whether the
    Agency’s response to the second motion to supplement is properly
    supported by affidavit as required by 35 Adm. Code 101.242(a)
    and
    (b),
    in that there are certain facts asserted which are not of
    record,
    and requests that the Board strike the Agency’s response.
    Also in the interests of bring this dispute to resolution, the
    Board will accept the Agency’s response.
    Without addressing the other arguments, the Board denies the
    Bank’s second motion to supplement as untimely.
    The Bank does
    not explain why it is first raising this issue at this time,
    particularly in that it was aware of the
    DJN
    documents well
    before the December 16,
    1992 hearing at which the now-challenged
    testimony took place.
    Agency Motion to Strike
    On May 17,
    1993, the Agency moved to strike portions of the
    Bank’s reply brief.
    On May 25,
    1993,
    the Bank filed a response
    to the Agency’s motion to strike.
    The response accompanied the
    Bank’s May 25th reply.
    The portions the Agency requests be
    striken are a)
    references to, and a request that the Board take
    judicial notice of, transcripts containing the hearing testimony
    of Agency employee Mr. Doug Oakley in Southern Food Park,
    specifically citing to the Bank’s reply brief at
    6,
    7, and fn.
    3;
    DL
    L~3-O025

    4
    and b)
    the Bank’s discussion of the
    DJM
    Oil Company material
    referenced above, specifically citing to the Bank’s reply brief
    at
    13.
    Regarding the
    DJM
    discussion in the Bank’s reply brief,
    for
    the reasons the Board expressed in response to the Bank’s second
    motion to supplement,
    the Board grants the Agency’s motion to
    strike.
    Regarding the transcripts of Mr. Oakley’s testimony in
    Southern Food Park, the controversy in the instant case evolved
    from a discussion
    in the Agency’s post—hearing Brief.
    The Bank
    asserts in its reply brief
    (at
    5,
    6.) that the discussion should
    be stricken in that
    it has implied, without factual basis or
    citation to the record, that the Bank’s consultant is taking
    unfair advantage of an unsophisticated Bank as well as the Fund.
    The Bank specifically quoted the following language on pp.
    21 and
    22 of the Agency’s post-hearing Brief as the basis for its
    protest:
    Beyond a reasonable amount representing fairly the
    administrative and procurement and oversight costs of an
    owner or operator, handling charges represent profit to the
    contractor.
    The profit motive acts as an incentive to the
    contractor to take as great
    an advantage of the opportunity
    as possible.
    Usually owners and operators never see the
    amount actually paid to the subcontractor for the work
    performed.
    They do, however, see an amount attributed to
    the subcontractors by the contractor which, for all but
    experienced and commercially sophisticated owners and
    operators is unknown to them to contain a contractor mark
    up,
    or handling charge.
    Since the amount of the
    subcontractor bills are attributed to subcontractors who
    never dealt with the owner or operator, an owner’s or
    operator’s expressed concerns over high prices may be
    directed away from the contractor, who can merely shrug and
    reply that it’s
    a costly business.
    The strong influence of the profit motive may result in a
    contractor unreasonably maximizing its profits at the
    expense of the UST Fund
    (and hence, the taxpayers).
    The Bank asserts that the above quote is factually at odds
    with how the handling charges were itemized in the instant
    appeal.
    The Bank further states that it
    is the Agency that
    offered Mr. Douglas Oakley’s testimony in Southern Food Park, and
    that his testimony would show that the Agency will reimburse
    handling charges if they are hidden in another reimbursable
    category.
    OI~3-OO26

    5
    In its response the Bank also requests that the Board
    consider whether the Agency’s motion to strike is properly
    supported by affidavit,
    because the motion contains facts
    asserted which are not of record and are unsupported by affidavit
    as required by
    35 Ill. Adm. Code 101.242(a)
    and
    (b), and also
    requests that the Board strike the Agency’s motion.
    Again,
    in
    order to bring this dispute to resolution, the Board will accept
    the Agency’s motion to strike.
    In resolving this issue, the Board need not recount the
    Bank’s and the Agency’s supporting arguments for taking or not
    taking judicial notice of the transcripts in Southern Food Park.
    In reviewing the record now before us, the Board agrees with the
    Bank insofar as it cannot find any evidence whatsoever that would
    justify the Agency’s inclusion of the discourse quoted above.
    The Board finds unacceptable what must be viewed as an attempt by
    the Agency to insinuate that its description of an owner’s
    inexperience and a contractor’s bad faith conduct applies to the
    Bank and to the Bank’s contractor.
    Therefore, the Board strikes
    all discussion of this subject matter from the Agency’s brief as
    well as from the Bank’s reply brief.
    DENIED COSTS APPEALED
    The reimbursement denied is listed in 11 paragraphs
    contained in Attachment A of the Agency’s September 14,
    1993
    letter.
    (Pet.
    Exh.
    E.)
    The Bank appeals reimbursement denials
    as specified paragraphs
    2,
    6,
    7,
    8, and
    10 of Attachment A,
    summarized as follows:2
    Paragraph
    2
    -
    $1,917.34, handling charges.
    Paragraph
    6
    -
    $7,050.00,
    costs associated with
    roller/compactor charges.
    Paragraph
    7
    -
    $5,459.81,
    surveying costs.
    Paragraph
    8
    -
    $3,047.50,
    nuclear density testing charges.
    Paragraph 10
    -
    $1,771.25,
    ARDL
    (the Bank’s engineering
    consulting firm) personnel costs associated with seeking
    reimbursement from the fund.
    BACKGROUND
    2
    At hearing, the Agency stipulated that costs contained
    in paragraph
    1
    (tank removal costs), paragraph
    3
    (laboratory rush
    charges), and paragraph
    4
    (personnel charges incurred after
    notification to the Illinois Emergency Management Agency) were
    reimbursable.
    The remaining paragraphs were not appealed.
    (Jt.
    Exh.
    2;
    Pr.
    at
    5,
    7,
    262;
    Pet. at 7—9.)
    01
    L~3-OO27

    6
    Procedural History
    The procedural history has a particular bearing on certain
    issues raised
    in this case.
    In March,
    1989,
    the Bank purchased
    the property (site),
    located at 200 North Main Street,
    Benton,
    Franklin County.3
    From 1938 until
    1973,
    the site had been used
    for a gas station operation.
    A building that had been on the
    site was demolished prior to the removal of the USTs.
    On April
    20,
    1989,
    following an inspection, the Office of the State Fire
    Marshal
    (OSFM)
    ordered four USTs on the site to be registered.
    On May 5,
    1989,
    the OSFM ordered the Bank to remove the tJSTs.
    Between September 22 and September 25,
    1989, the four USTs were
    removed.
    On September 22,
    1989,
    after a release of petroleum was
    discovered during the removal of the first three UST5, the Bank
    notified the Illinois Emergency Management Agency
    (IEMA)
    (then
    called the Emergency Services and Disaster Agency)
    *
    (Pet.
    at 1-
    3;
    Pet. Br. at 4,5; Agency Br. at 1-3.)
    On September 22,
    1989, the Bank hired ARDL,
    Inc.,
    an
    environmental testing laboratory and consulting firm.4
    Mr. Todd
    Gentiles,
    an engineer and field services manager of ARDL,
    oversaw
    all aspects of the site remediation, submitted the required plans
    and reports to the Agency, and prepared the initial reimbursement
    application and additional reimbursement information when
    requested by the Agency.
    The application and additional
    supplements requested by the Agency were submitted between June
    of 1991 and January of 1992.
    (Pet.
    at 5; Pet.
    Br. at 5; Pr. at
    172—174,
    240; Agency Rec. TF at 47, 132.)~
    By letter of May 22,
    1990,
    the Agency had initially deemed
    the Bank ineligible to access the Fund due to a determination by
    the OSFM that the UST5 were exempt from registration.
    However,
    based on an affidavit of Benton’s mayor, the OSFN reversed itself
    and the Bank reapplied for reimbursement.
    On September 6,
    1991,
    the Agency notified the Bank by letter that it was eligible for
    ~
    The Bank purchased the site from a financial
    institution, which had taken ownership from the Federal Savings
    and Loan Insurance Corporation, which,
    in turn, had taken
    ownership from another financial institution.
    (Pet.
    at 2.)
    ~
    We note that ARDL also was overseeing remediation of the
    DJM
    property, which also belongs to the Bank;
    the
    DJM
    property is
    located to the north of, and adjacent to, the site at issue here.
    ~
    The Agency record consists of Part
    1,
    Fiscal File, Books
    A and B
    (denoted as FFA and FFB); Part 2, Technical File
    (denoted
    as TF); Supplemental Agency Record
    (denoted as SF) that was
    stipulated into evidence at the December 16,
    1992 hearing; and
    the Bank’s Corrective Action Report
    (denoted as CAR) containing
    the original photographs filed pursuant to Board order.
    Qtl~3-UO28

    7
    reimbursement but that the deductible would be $100,000.
    The
    Bank appealed the deductible to the Board,
    but withdrew its
    appeal after the Agency reduced the deductible to $10,000.
    (See
    PCB 91—190; Agency Br. at
    6,
    7; Pet. at 3,
    4,
    Exh.
    B,
    C; FFA at
    24,
    44,45.)
    On May 14,
    1992,
    the Agency approved an “interim”
    reimbursement of $320,000.
    On
    August
    10,
    1992, the Bank filed a
    complaint in the Circuit Court in Franklin County against the
    Director and the LUST Fund Manager of the Agency.
    The complaint
    included counts requesting mandamus relief and alleging violation
    of the Administrative Procedures Act for failure to make a final
    determination.
    On September 14,
    1992,
    two days prior to hearing
    on the complaint,
    the Agency issued its final determination. It
    is that determination,
    as further modified by stipulation at the
    Board’s hearing, that is now before the Board.
    (Pet.
    at
    5,
    6,
    Exh. D,
    E.)
    Site Remediation
    The site is bounded on the south and west by two roadways,
    East Washington Street, which is a city street, and North Main
    Street, which is Highway 37.
    To the east is
    a city alley and to
    the north is the earlier discussed
    DJM
    property, which we note
    was later excavated under a separate incident number.
    The
    remediation at the site involved boundary—to—boundary excavation,
    with vertical walls,
    to a depth of 14 feet.
    A sandstone
    formation was encountered at the bottom of the excavation. From
    September
    9,
    1991 through October 10,
    1991, approximately 11,600
    tons of contaminated soil were excavated and taken to a landfill.
    Starting on October
    11,
    1991 and for ten days thereafter,
    backfilling took place.
    The site was filled using 12 to 18 inch
    lifts,
    each compacted with a vibratory roller.
    Nuclear density
    tests,
    to assure 95
    compaction,
    were performed on each lift by
    Holcomb Foundation Engineering, a civil engineering
    subcontractor.
    (Tr.
    at 133—138,
    187, 213—219; TF at 62,
    76,
    135,
    152; see
    CAR
    photos at 18—20.)
    Contamination and Groundwater Concerns
    Following the excavation, laboratory analyses of soil
    samples collected within the excavated area confirmed that soil
    at the south property boundary and the sandstone formation
    exceeded the Agency cleanup objectives.
    The south wall samples
    also indicated that the contamination had migrated off-site.
    An
    unanticipated concern of considerable significance was the
    presence of groundwater found at 12 feet.
    Corrective action
    included the removal of 36,800 gallons of perched water,
    precipitation and groundwater.
    (TF at 135,
    139,
    136,
    144.)
    Because the soil sampling indicated a potential for
    groundwater contamination,
    a groundwater monitoring plan was
    01 q3-0029

    8
    established and
    is still ongoing.
    The corrective action plan to
    date does not provide for off-site remediation.
    Whether such
    remediation will be necessary will be determined by future
    groundwater monitoring results.
    (Bank’s Br.
    at 7; TR at 136.)
    HANDLING CHARGES
    There are three distinct categories of the disputed
    $1,917.34 in handling charges.6
    As categorized by the Agency,
    they are “(a) handling charges associated with denied costs,
    (b)
    “duplicated” handling charges,
    and
    (c) handling charges in excess
    of fifteen percent.”
    (Agency Br. at 11.)
    (a).
    Roller/compactor and Nuclear Density Testing Handling
    Charc~~
    The parties agree that the disallowed $1,123.18 in handling
    charges
    is dependent on the outcome of the Board’s determination
    regarding the disallowed roller/compactor and nuclear density
    testing costs themselves.
    As addressed later,
    the Board
    is
    reversing the Agency’s denial of the roller/compactor and nuclear
    density testing costs,
    so the Agency’s denial of the associated
    handling charges here is reversed.
    b).
    15
    Billing by Both Consultant and Subcontractor
    The handling charges
    (also called handling fees)
    that the
    Agency disallowed
    in this category total
    $735.44.
    ARDL, the Bank’s consultant,7 utilized a subcontractor,
    Midwest Petroleum,
    for small item field purchases,
    e.
    g., the
    securing of rock and stone.
    When the subcontractor submitted its
    6
    Douglas Oakley,
    of the Agency’s Remedial Accounting
    Procurement Unit in the Bureau of Land testified as to some of
    what comprised the $1917.34 in handling charges denied,
    referencing documents in the FFA.
    In that both parties agreed in
    their briefs that the following amounts were correct, the Board
    will not disturb the totals.
    However, the totals don’t “add up”,
    and the Board has noted below at least two amounts that appear to
    be in error.
    The Board leaves any corrections to the discretion
    of the parties:
    $1123.18 for 15
    handling charges associated
    with roller/compactor charges
    ($247.50, $810.00 and $65.68);
    $735.44 for contractor and subcontractor separate billings of 15
    ($242.54, $30.60,
    $407.27 and $55.03);
    $55.98
    (sic)
    for
    adjustment in 46
    handling charges
    ($49.61 and $6.37
    (sic,
    see
    FFA
    at
    186))
    and $7.12 for adjustment in 16
    handling charge.
    (Tr. at 21-28; Bank’s Br.
    at
    8; Agency’s Br. at 18.)
    ~
    ARDL is sometimes referred to in this record as the
    Bank’s consultant and sometimes as the contractor.
    0 IL~.3-U03O

    9
    field purchase bills to ARDL,
    it included its 15
    handling
    charge.
    These Midwest Petroleum’s billings,
    including the 15
    handling charge, were paid by ARDL.
    Then ARDL added its 15
    handling charge to the Midwest Petroleum bill.
    (For example,
    see
    FFA at
    159.)
    The Agency subtracted from Midwest Petroleum’s bill
    its 15
    handling fee and adjusted ARDL’s computation of its 15
    handling fee accordingly.
    The essence of the dispute between the Bank and the Agency
    is whether both
    ARDL
    and Midwest Petroleum can add handling fees.
    The Agency asserts that combined they exceed the Agency’s 15
    limit and that these charges are duplicate charges.
    We will first summarize the basis for the Agency’s policy
    regarding the 15
    rate.
    There
    is no dispute that the Agency had no statutory
    guidance regarding the handling charge rate.8
    At hearing, Mr.
    Oakley testified that at some unstated point in time the Agency’s
    policy was to pay a five percent handling charge, based on the
    markup of its regular state contracts.
    Then the Agency met with
    various representatives of industry, owners and operators,
    petroleum marketers and consultants to determine what was a fair
    handling charge in relation to the market place price.
    As a
    result of these “market place” discussions, the Agency changed
    its policy and established the 15
    level.
    Mr. Oakley stated that
    it was possible that the Agency paid more than 15
    on the basis
    of competitive bidding, but he wouldn’t know what those handling
    charges were because “it wouldn’t be apparent”.
    (Tr. at 35; also
    Tr.
    at 28—34.)
    Next, we will summarize the “duplicate charges” dispute.
    The Agency asserts that it was Agency policy that a 15
    handling charge was reasonable for the prime contractor on both
    subcontracts and field purchases.
    The Agency argues that it
    never intended that there be two 15
    handling charges on the same
    item,
    in effect more than doubling the handling charge for
    Midwest Petroleum’s field purchases.
    The Agency stated that,
    even though neither handling charge exceeded 15,
    the total was
    unreasonable.
    (Tr. at 37; Agency’s Br. at 17.)
    The Bank argues that:
    8
    Section 22.18b(i) (1) and
    (2)
    of the Act (P.A.
    87—1171,
    HB 4039,
    eff. September 18,
    1992)
    newly defines handling charges,
    and establishes
    a sliding scale of the percent allowable handling
    charge, with the percent allowable decreasing as the costs
    increase.
    Both briefs alluded to the new language to support
    certain of their positions,
    but neither argued that it was
    applicable to this proceeding.
    01
    L~3-003I

    10
    The problem with labeling this
    15
    handling charge as a
    “double markup”
    is that
    it ignores the very standard
    contracting and subcontracting business practice which the
    Agency has identified as the basis for its limiting handling
    charges to 15..
    .The application of a flat 15
    handling
    charge inherently assumes there is one “tier” of billing,
    e.g.,
    the consultant orders supplies from a vendor and seeks
    a
    15
    handling charge for carrying these costs.
    However,
    in the case of contractors, subcontractors and even sub—
    subcontractors,
    there can be two, three or more tiers of
    parties carrying costs.
    At each level,
    costs are incurred
    in administering subcontracted work,
    such as arranging for
    purchases and for carrying subcontract and field purchase
    debt.
    (Bank’s Br.
    at 9.)
    The Agency responds that:
    At first blush this does not sound unreasonable,
    but in
    theory the practice of contract “stacking” could go on
    ~
    infinitum.
    .
    .
    .None of the contracting parties in
    an example
    given by the Agency
    charge more than fifteen percent(15),
    but the total handling charge imposed upon the
    owner/operator
    which does not represent actual corrective
    action work done at the site
    exceeds 100.
    (Agency’s Br. at 16,
    17.)
    The Bank replies that, insofar as the Agency is implying
    that there
    is
    “double dipping” in the Bank’s example, this is not
    true:
    ARDL assumed that a handling charge of 15
    applied by the
    subcontractor
    (e.g.
    “Midwest Petroleum”)
    was reasonable and
    acceptable to the Agency.
    ARDL,
    as the contractor,
    incurred
    certain costs to review the subcontractor billings, evaluate
    charges, prepare billings and, most importantly pay the
    subcontractor while bearing the cost of carrying the money
    until reimbursement is received from the UST Fund.
    Similarly,
    the subcontractors incurred certain costs beyond
    actual bills for materials,
    as did ARDL.
    Proper materials
    must be selected, picked—up and/or delivered,
    items require
    storage until use, and the items must be paid for at the
    time of delivery or pick-up....Midwest Petroleum and
    ARDL
    each attempted to cover their respective administrative
    costs.
    (Bank’s reply Br.
    at 10.)
    The Bank asserts that the result of the Agency’s argument is
    that:
    .
    .the contractor can pay the subcontractor’s handling
    charge and operate his own business at a loss, or the
    contractor can keep the 15
    and not pay the subcontractor’s
    general and administrative overhead at the risk of being
    0
    LL~3-U032

    11
    unable to locate a subcontractor willing to bid.
    Petitioner
    submits that it is “reasonable” to reimburse the general and
    administrative overhead costs of both the contractor and the
    subcontractor.
    (Bank’s reply Br. at 10,
    11.)
    The Agency also appeared to argue that:
    a) the use of the
    Agency’s “Subcontractor Summary” forms incorrectly identified the
    field purchases as a subcontract9
    and b)
    in that the materials
    were used by Midwest Petroleum on the job, such labor costs were
    properly billed to
    ARDL
    as part of Midwest’s subcontract, and
    ARDL appropriately assessed a handling charge; however it was not
    appropriate for both to receive the maximum allowable handling
    charge on the materials purchased.
    (Agency Br. at 17,18.)
    The issue before us
    is one of reasonableness,
    as regards:
    the Agency’s limiting the handling charge to 15;
    its
    disallowance of a handling charge claim by the subcontractor; and
    whether ARDL’s and Midwest Petroleum’s handling charge claims
    were duplicates or were based on each one’s overhead.
    As regards the Agency’s 15
    limit per
    se,
    at least in this
    handling charge dispute category, there seemed to be no argument
    that 15
    reflected practices in the market place.
    We also note
    that it was the Agency witness, Mr. Doug Oakley, who testified
    that the 15
    figure was established as a standard handling charge
    only after Agency meetings with many persons familiar with the
    market place.
    In the absence of specifity in the Act or
    regulation applicable to this proceeding, the Board agrees that
    establishing the 15
    handling charge by basing it on market place
    practices is a reasonable approach.
    The issue here is whether
    the Agency, solely as a matter of policy and intent, can deny
    access to the 15
    handling charge to persons other than the prime
    contractor.
    The Board concludes that it
    is inconsistent for the
    Agency,
    as a matter of policy, to allow a 15
    handling charge on
    the basis that this fairly reflects overhead costs in the market
    place,
    and then turn around and deny the 15
    handling charge to
    some persons simply because they are not the prime contractor.
    The Board also is persuaded,
    and so finds,
    that the record
    supports the subcontractor’s handling charges as based on
    overhead costs separate from that of ARDL’s.
    Therefore,
    the Board reverses the Agency’s denial of
    reimbursement of Midwest Petroleum’s handling charges.
    c).
    Handling charges in excess of 15
    There were three billing submittals in this category.
    The
    ~‘
    We note that the Agency’s reimbursement form for
    subcontractors includes the statement:
    “The IEPA will pay no more
    than a 15
    handling charge.”
    (FFA at 79.)
    01 L~.3-0O33

    12
    Agency in all cases reduced the handling charges to 15.
    They
    were reduced from 46.4,
    46
    and 16.4
    respectively, resulting in
    a disallowance of $49.61,
    $6.37 and $7.12 respectively.
    The
    Agency suggested that the 16.4
    appeared to be a mathematical
    error and the Bank did not discuss the issue.
    Mr. Todd Gentles
    of ARDL testified that the 46
    handling charges resulted from
    internally audited general and administrative costs plus a small
    fee on small purchases, which was company policy at the time.1°
    Gentles was unable to answer what constituted a small purchase,
    and what the cutoff point was.
    He noted that he thought it could
    be as high as $5000, but that that determination is made by the
    firm’s business manager.
    (Tr. at 178,
    179,
    253.)
    Mr. Gentles also testified that the company’s small purchase
    policy was established years earlier, when it handled small
    projects,
    and then carried over to the LUST program on small
    purchases.
    The policy was developed at a time prior to the onset
    of the high-cost LUST remediation projects and before the company
    used outside subcontractors.
    (Pr. at 252,253.)
    The Agency argued that this testimony was insufficient to
    establish that the 46
    handling charge was reasonable.
    The Board
    agrees and so finds.
    Mr. Gentles explained generally what ARDL’s
    policy
    ~
    but he was unable to provide with any specificity how
    that policy was applied by his firm, certainly in a LUST setting.
    ‘°
    Between the time of the filing of the Bank’s and the
    Agency’s post-hearing briefs, the Board decided the case of
    Beverly Malkey.
    as Executor of the Estate of Roger Malkey, d/b/a/
    Malkey’s Mufflers v.
    IEPA,
    (March 11,
    1993),
    PCB 92—104.
    The
    Agency quoted the Board’s holding on p.
    3 of its opinion:
    the
    consultant...provided
    no documentation to support his
    claim.
    Petitioner never submitted actual handling charges
    by any other in the industry.
    (See, Enterprise Leasing v.
    IEPA (April
    9,
    1992), PCB 91-72,
    132 PCB 79.)
    ...
    The Board
    finds that petitioner did not carry its burden of
    demonstrating that the handling charges of 58
    were
    reasonable.
    (Agency Br. at 20.)
    The Bank conceded Malkey established a new element of proof
    in demonstrating charges to be reasonable.
    However, the Bank had
    viewed that
    it
    had the burden to prove that the handling charges
    as requested by petitioner were reasonable, and had no way of
    knowing that the Board would require evidence of various industry
    handling charges.
    The Bank asserts that Nalkey is not applicable
    to the instant appeal,
    in that the Bank had no way to present
    such evidence at this stage without opening the record of the
    proceedings to address the Malkev holding.
    The Board need not
    find that Malkey
    is controlling,
    in that the Bank has not met its
    burden of proof based on the record here.~~
    0
    L~3-U03k

    13
    Therefore, the Board affirms the Agency’s denial of
    reimbursement of handling charges in excess of 15.
    CORRECTIVE ACTION ISSUES
    The remaining issues involve whether the activities for
    which reimbursement is sought constitute corrective action,
    rather than whether the charges were reasonable.
    “Corrective action”
    is defined in Section 22.18(e) (1) (C)
    of
    the Act as follows:
    “Corrective action” means
    an action to stop, minimize,
    eliminate,
    or clean up a release of petroleum or its effects
    as may be necessary or appropriate to protect human health
    and the environment.
    This includes, but is not limited to,
    release response investigation, mitigation of fire and
    safety hazards, tank removal,
    soil remediation,
    hydrogeological investigations,
    free product removal,
    groundwater remediation and monitoring, exposure
    assessments,
    and the provision of alternate water supplies.
    Corrective action does not include removal of an underground
    storage tank if the tank was removed or permitted for
    removal by the Office of the State Fire Marshal prior to the
    owner or operator providing notice of a release of petroleum
    in accordance with applicable notice requirements.
    Corrective action does not include legal defense costs.
    Legal defense costs include legal costs for seeking payment
    under Section 22.18b.
    (415 ILCS 5/22.l8(e(l)(c)
    (1992).)
    The Board has held that,
    in order for an action to
    constitute corrective action, and thus the costs incurred to be
    reimbursable,
    the action must fulfill both aspects of the
    “corrective action” definition,
    i.
    e.:
    (1)
    it is “an action to
    stop, minimize,
    eliminate,
    or clean up a release of petroleum or
    its effects as may be necessary or appropriate to protect human
    health and the environment”; and,
    (2)
    such action “includes, but
    is not limited to, release investigation, mitigation of fire and
    safety hazards,
    etc.
    (See Enterprise Leasing Com~anvv. IEPA
    (April
    9,
    1992),
    PCB 91-174.)
    We note that this holding has been
    referred to variously as the Enterprise Leasing test, the “two—
    pronged” test,
    or “two—step” test.
    We will refer to this as the
    two-step test.
    Roller/compactor and Nuclear Density Testing Charges
    Ms. Lockhart testified for the Agency regarding the Agency’s
    denial of reimbursement of $7050.00 in costs of roller-compacting
    the backfill and $3047.40 in costs of nuclear density testing.
    0! L~,3-0U35

    14
    At the time of hearing, she has been a project manager for
    the past two years in the Agency’s LUST program, and made the
    decision to disallow the Bank’s roller/compactor and nuclear
    density testing charges.
    Ms. Lockhart testified that she
    performed two reviews of the technical file,
    in December 1991 and
    on May
    12,
    1992.
    Ms. Lockhart did not believe that the
    activities fulfilled the first step of the two—step corrective
    action test.
    Regarding safety concerns, she testified that
    compacting clay along the boundary abutting the state highway
    would depend on how close
    it was, and whether the excavation was
    shored pursuant to OSHA requirements.11
    She did not think the
    excavation had been shored.
    She was not sure it needed to be in
    order to support the highway, explaining that she wasn’t on site
    and thus did not know exactly how close it was to the highway.
    She also testified that the phrase in the corrective action
    definition
    “.
    .
    .or clean up
    a release of petroleum or its effects
    .
    .“
    meant environmental, not structural, effects.
    (Pr. at 40,
    41,
    46,
    49—51,
    61,
    71—73; FFB at 210, 211.)
    Ms. Lockhart testified that each decision is site
    specific, but that she had never seen a case where she has
    allowed roller/compaction and nuclear density testing as
    corrective action costs.
    She had reviewed 120 sites,
    and while
    all of them used excavation and soil removal,
    she did not
    remember whether any of them involved compaction costs or whether
    reimbursement was requested.
    A primary factor she considered in
    making her decision in this case was that the compaction appeared
    ~
    In relation to the safety issue, both parties support
    their positions by reference to the Bank’s alleged obligations
    pursuant to certain requirements of the federal Occupational
    Safety and Health Administration
    (OSHA)
    and of the State’s
    Adjacent Landowner Excavation Protection Act.
    The Agency argued
    that safety factors were not corrective action because the Bank
    was already obliged to do what it did.
    (See.
    e.
    g. Agency’s Br.
    at 32-34; Bank’s Reply Br.
    at 14-16.)
    Whatever the compliance
    requirements may be in these documents
    they are not part of the
    record
    -
    they would not in any event be relevant to our
    consideration here.
    Questions of compliance with these statutes
    or regulations are within the purview of those who administer
    them,
    not
    the
    Agency.
    See
    Rockford
    Drop
    Forge
    Company
    v.
    Illinois
    Environmental Protection Agency,
    (December 20,
    1990), PCB 90-46,
    fn.
    at
    7;
    The
    Grigoleit
    Company
    v.
    Illinois
    Environmental
    Protection Agency,
    (June
    4,
    1992),
    PCB 90—135, fn.
    #9 at 10.)
    In
    like manner, we find nothing in the corrective action definition
    that allows a charge to be reimbursed simply because it is
    required by another statute or regulation.
    If an action meets
    the
    definition
    of corrective action it may be reimbursed whether
    or
    not
    it
    is
    required
    by
    another
    law.
    If
    it
    does
    not
    meet
    the
    definition,
    it
    may
    not
    be
    reimbursed
    even
    if
    required
    by
    another
    law.
    01 L~.3-0036

    15
    to have occurred because the Bank intended to put a building on
    the site.
    She stated that, having never seen compaction costs
    before, she discussed it with others, and was told that “the
    frequence
    (sic)
    was done to put new buildings on the site.”
    (Tr.
    at 56.)
    Ms. Lockhart also stated that her review included a June
    12,
    1992 letter from the Bank president,
    Mr.
    Steve Swinney,
    stating that the Bank intended to construct a new building on the
    “sites”, and she believed the letter was referring to the Bank’s
    site and the
    DJM
    facility to the north.
    (TF2 at 80; Tr.
    56,
    57,
    92—93,
    103.)
    Ms.
    Lockhart stated that she did not look at other factors,
    such as groundwater conditions or other site specific issues in
    reaching her decision.
    (Tr. at 59-61.)
    Mr. George Glass testified for the Agency regarding his site
    visits.
    He had been a project manager for about two—and—one—half
    years and worked out of the Agency’s Marion office.
    He approves
    the corrective action plans after reviewing them for any
    deficiencies regarding sufficiency of information and relevance
    to remediating the site.
    The first of his visits to the Bank’s
    site occurred after the tanks had been removed.
    He reviewed the
    excavation with regard to the extent of the contamination and the
    cleanup objectives.
    If,
    as here,
    contamination is identified at
    the boundary of a site,
    and further excavation is not feasible,
    because of a street or other structures,
    then, based on further
    testing, he confers with the owner/consultant doing the remedial
    work as to the safety of proceeding further, and discusses Agency
    concerns regarding devising a suitable alternative course of
    remediation proposed.
    He does not review reimbursement
    applications,
    and any recommendations he would have made to Ms.
    Lockhart would have concerned only the physical aspects of the
    cleanup, not questions related to reimbursement.
    He has overseen
    remediation for about 200—250 sites.
    He was aware of one other
    site in Carbondale where compaction activities occurred, but was
    not aware of whether reimbursement was requested.
    (Pr.
    105—119,
    133,
    155—157,
    159—161.)
    Mr.
    Glass testified as to his ongoing interaction with the
    consultant regarding the boundary contamination, the odor and
    visual stain problems on the sandstone floor and the presence of
    groundwater.
    He stated that monitoring wells were automatically
    required in situations such as this when contamination goes off
    site.
    (Tr. at 142—158.)
    Regarding safety concerns at the west and south wall
    boundary excavations, Mr.Glass testified that there was a
    potential that the soil would sluff off,
    and agreed that it could
    “affect the lateral subjacent support of that adjoining highway.”
    (Tr.
    at 158.)
    Mr. Gentles testified that he is a petroleum engineering
    01
    I~3-OQ37

    16
    graduate from the University of Missouri, Rolla,
    has been
    employed by ARDL for eleven years, and presently administers all
    ARDL’s
    consulting projects related to environmental work.
    He has
    been involved with about 50 UST sites.
    Mr. Gentles’ oversight
    remediation responsibilities at the Bank site included the
    investigation and remediation regarding the backfilling
    activities.
    He oversaw the taking of samples for lab analysis to
    determine whether cleanup objectives had been achieved.
    (Tr. at
    168—173.)
    Mr. Gentles testified that he would have advised the degree
    of compaction of the soils regardless of the Bank’s future
    building plans.
    He stated that a lesser degree of compaction at
    the site can create a tendency for the contaminants to bleed into
    the backfill area, and that the contamination was confirmed as
    going off the site.
    He also stated that the structural integrity
    of the side walls, particularly those on the west and south
    walls, was a major concern.
    He testified that Highway 37 was
    within eight to ten feet from the property line, with city
    utilities underneath the street.
    He also stated that a main
    water line feeds down the east alley and through Washington
    Street.
    His concern was that highway traffic could cause
    sluffing and subsidence over time,
    causing lateral movement that
    would tear up the highway and fracture the underground utilities.
    He was also concerned about personal injury,
    in that the site
    could have gradually subsided from six inches to two feet without
    the compaction.
    The nuclear density testing was undertaken to
    achieve as much as possible the permeability values,
    if not the
    full cleanup objectives,
    of the natural soils that had been
    removed.
    He stated that, as an engineer, he was concerned that
    the backflow migration of subsurface waters would cause the
    recontamination of the soils,
    and asserted that the compaction
    would very much minimize this problem.
    He stated that the Agency
    requested the monitoring wells because of its concern about the
    impact of the site on the groundwater system.
    (Tr. at 185-196,
    220,
    221.)
    Mr Gentles also stated that he did not recommend use of a
    geomembrane liner.
    He asserted that,
    although there was lesser
    cost using
    a liner without compaction, with compaction testing
    there was lesser migration of contaminants.
    He testified that
    with the soil types in Illinois there is more benefit from actual
    compaction than from a liner, which also could be damaged in the
    process of backfilling and such damage would not be evident.
    (Tr. at 227,228.)
    We have reviewed the record and the arguments presented.
    In
    their arguments, both parties cite to Platolene 500 v. IEPA
    (May
    7,
    1992), PCB 92—9,
    a case which involved concrete replacement.
    Platolene distinguished between corrective action and
    restoration, and stated that which one applies is determined by
    the particular facts surrounding the action.
    (Also see Strube
    V.
    0! t43-0038

    17
    IEPA (May
    21,
    1992),
    PCB 91-205.)
    Both parties also refer to a
    “safety hazard” exception,
    citing to Platolene.
    The Bank states,
    “Platolene 500,
    Inc., provides a ‘safety hazard exception”.
    (Bank’s Reply Br.
    at 14.)
    The Board notes that Platolene
    provides no such exception.
    The word “safety” appears only one
    time in Platolene,
    and that is within a quotation on page
    6 to
    Section 22.18(e) (1) (C)
    of the Act, which is the section defining
    corrective action.
    We also take note of a more recent Board
    holding,
    in Princeton/Beck Oil Company v.
    IEPA
    (May 5,
    1993), PCB
    93-8.
    Beck involved compaction of a backfill.
    The Agency argued
    that the sole purpose of Beck’s compaction of backfill was to
    shore up the foundation of
    a building on the premises, pointing
    out that the compaction did not affect the contamination.
    The
    Board agreed with the Agency that, under the facts presented,
    Beck did not meet the first part of the two-step test,
    and found
    that the backfill in that case was analogous to the replacement
    of concrete.
    (Ibid. at
    3,
    4.)
    The facts here are quite distinguishable from the other
    cases.
    Here,
    the post—excavation environmental concerns are
    evident, and the Agency shared those concerns.
    Indeed, only
    future results from the monitoring wells will show whether the
    boundary-to—boundary roller/compaction and the nuclear density
    testing were sufficient to prevent further contamination.
    The
    Agency record and the testimony show the growing, and often
    unexpected,
    environmental and safety problems as the remediation
    progressed.
    The Agency did not present any testimony addressing
    its actual reimbursement decision that took into consideration
    the actual conditions specific to the site; the testimony shows
    that the decision that these activities did not constitute
    corrective action was based solely on the Agency’s observations
    that such compaction
    is unusual and usually
    is for the purpose of
    providing building support.
    In so stating, we note that the
    record indicates that Ms. Lockhart was mistaken
    (as the Bank
    argues without Agency rebuttal, see Bank’s Br. at 17; Bank’s
    reply Br. at 19)
    when she testified that Mr. Swinney’s June
    2,
    1992 letter indicating planned construction was part of her
    technical review,
    in that this letter was not in the record at
    the times she testified her reviews occurred,
    namely in December,
    1991 and on May 12,
    1992.
    We conclude, and so find, that the roller/compaction and
    nuclear density costs meet the two-part test in the definition of
    corrective action.
    More specifically, the Bank took these
    actions to
    “.
    .
    .stop, minimize,
    eliminate,
    or clean up a release
    of petroleum or its effects as may be necessary or appropriate to
    protect human health and the environment”, and the actions are of
    the type contemplated by the statute.
    Therefore,
    the Board reverses the Agency’s denial of the
    reimbursement of the Bank’s costs for the roller/compaction and
    nuclear density tests.
    As earlier discussed, the Agency’s denial
    0
    I
    t43-0f339

    18
    of the accompanying handling charges are reversed as well.
    Surveying Costs
    The $5459.81 in survey costs for which the Agency denied
    reimbursement were commissioned and paid for by the Bank, not
    ARDL’s
    engineer,
    Mr. Gentles.
    (FFA 214-228.)
    A. Real Estate Plat
    of Survey and Property Line Agreement was performed by Lawrence
    A. Lipe and Associates,
    Consulting Engineers
    (surveyor).
    The
    survey encompassed the Bank site, the
    DJM
    property north of the
    Bank,
    and property across the alley to the east of the Bank site.
    Included is a
    property line agreement between the owners to the
    east and the Bank.
    (TF at 172; Agency Br.
    at 41.)
    Ms. Lockhart testified that the Agency did not require
    surveys,’2 and to her knowledge the Agency had never reimbursed
    for survey costs.
    She acknowledged that ARDL appeared to rely on
    the survey to conduct its corrective action, but that the
    “physical act of performing
    a survey is not corrective action”
    (Pr.
    at 70).
    She stated that surveying costs do not meet the
    first part of the two—part test of corrective action and are thus
    not reimbursable.
    (Tr.
    at 61-70; FFB at 211.)
    Mr. Gentiles testified that he was aware of a survey being
    conducted.
    The Bank’s purpose, to his knowledge, was to find out
    the true boundaries of the site.
    Mr. Gentles testified that he
    had never ordered a survey for any other remediation project, but
    that he had never before conducted a boundary—to—boundary
    excavation,
    adjacent to roads and water and sewer utilities.
    He
    asserted that even if the Bank had not commissioned the survey,
    he still would have done so for this site.
    He wished to keep the
    DJM cleanup distinct; the survey assisted in remediation
    decisionmaking,
    including the question of off-site remediation;
    and it was an important tool for addressing safety
    considerations.
    (Tr. at 198,
    199,
    202,
    203,
    240,
    250,
    251, 261;
    TF 55.)
    The Agency argued that requesting reimbursement for surveyor
    costs
    is analagous to Mr. Gentles’ use of the Joint Utility
    Location Information for Excavators
    (JULIE) map and the United
    States Geological Survey
    (USGS) topographical map; the fact that
    such documents are used does not make the government’s costs
    reimbursable as corrective action.
    (The Agency also refers to
    Mr. Swinney’s June 2,
    1992 letter, which requested an Agency
    12
    There was considerable discussion as to whether
    questions on the Agency’s reimbursement forms required a survey
    to properly respond to them.
    As the Board has earlier held, the
    Board does not weigh the contents of such Agency documents in
    reaching its UST determinations.
    (Russell
    L. Bacon v. IEPA
    (December 17,
    1992),
    PCB 92—111.)
    Ut
    L43-QQL~Ø

    19
    sign—off regarding corrective action at the Bank site in order to
    complete a real estate closing for the
    DJM
    site, which was
    necessary to construct its new building.
    Ms. Lockhart did not
    testify about this.
    The Board will not give weight to this
    argument for this reason as well as for our reasons expressed
    earlier
    -
    that this letter was not before Ms. Lockhart during her
    review.)
    (Agency Br.
    at 40-43; TF at 79,
    80.)
    The Bank argues that the survey of the neighboring areas was
    valuable in remediation decisionmaking.
    The Bank argued that
    conducting and relying on the survey were activities that
    directly related to soil remediation,
    and as such constituted
    reimbursable corrective action.
    (Bank’s Br.
    at 20—22.)
    While the Agency’s attempt to compare a government map with
    a privately conducted survey map is off—point,
    it does
    articulate,
    even if indirectly, what concerns the Board.
    The record is clear that the Bank, not
    ARDL,
    commissioned
    and paid for the survey.
    As this opinion earlier states, ARDL
    was the Bank’s engineering firm throughout the clean—up, starting
    from September 22,
    1989.
    Mr. Gentles testimony leaves no
    suggestion that the Bank ever even discussed the survey with him,
    much less what he thought it should consist of.
    The scope of the
    survey, which included the boundaries of three properties, surely
    went beyond the uses articulated by Mr. Gentles.
    Even if the
    survey might have been valuable for separate billing purposes
    related to the cleanup of the two sites, this would not support
    the argument that the survey constituted corrective action.
    We do not dispute that Mr. Gentles made good use of the
    survey, or that he felt the need to rely on a survey.
    However,
    the record persuades the Board that the Bank conducted the survey
    for other purposes, and was made available to Mr. Gentles in the
    same manner as would any other useful Bank document.
    The
    corrective action needs appear to have played little,
    if any,
    role in the rationale for commissioning the survey,
    including its
    scope.
    In so saying, we do not wish to imply that survey costs
    could not constitute corrective action in another factual
    situation.
    Here, however, the nexus between the particular
    survey undertaking and the corrective action undertaking is
    unacceptably remote.
    Under these circumstances the Board
    concludes, and so finds, that the costs of the survey do not meet
    the first step of the two—step test.
    The survey was not “an
    action to stop,
    minimize, eliminate,
    or clean up a release of
    petroleum or its effects as may be necessary or appropriate to
    protect human health and the environment”.
    Therefore, the Board affirms the Agency’s denial of
    of reimbursement of the Bank’s survey costs.
    Costs associated with Seeking Reimbursement from the Fund
    01 L~3-Q0L~
    I

    20
    The issue related to the denial of reimbursement for the
    Bank’s personnel costs
    of $1771.25 for preparing the application
    is not a difficult one to define.
    Essentially, the question is,
    do
    ARDL’S
    costs for preparing reimbursement packages constitute
    corrective action.
    The Bank presents essentially two arguments:
    1) that it
    is a costly undertaking because much of the cost is
    incurred in response to the Agency’s format/information
    requirements and subsequent requests for large amounts of
    information; and b) that the Agency had been reimbursing these
    costs since the inception of the reimbursement program, and then
    abruptly reversed its policy.
    (Bank’s Br. at 23,
    24.)
    The Agency argues that the notion that reimbursement of
    costs is somehow associated with what remediation services are to
    be performed is incorrect.
    The Agency also contends that, what
    may be reimbursable from the Fund for documentation costs is not
    determined on the basis of whether the Agency required it.
    (Agency Br.
    at 43-45.)
    The Board finds that the definition of corrective action
    does not encompass the recovery of moneys from the Fund.
    Costs
    of corrective action involve abating a release of contamination.
    Costs of applying for reimbursement from the Fund involve who
    pays.
    Whether or not the Fund existed,
    corrective action would
    be required.
    Seeking monies from the Fund is not required.
    We
    find nothing in the definition of corrective action that links
    those actions with actions taken to seek access to the Fund.
    We
    particularly reject the notion that corrective action strategies
    can be dictated by whether the costs are reimbursable from the
    Fund.
    We also note that the Board has previously found that the
    Agency’s prior actions,
    if in error,
    are properly remedied by
    correcting the error,
    not perpetuating it.
    (Chemrex,
    Incorporated
    v.
    IEPA (February
    4,
    1993), PCB 92-123.)
    Therefore,
    the Board affirms the Agency’s denial of
    reimbursement for the Bank’s costs associated with seeking UST
    Fund reimbursement.
    CONCLUSION
    For the reasons expressed above,
    the Board affirms the
    Agency’s denial of reimbursement to the Bank for: handling
    charges in excess of 15;
    surveying costs,
    and costs associated
    with seeking reimbursement from the Fund.
    For the reasons
    expressed above, the Board reverses the Agency’s denial of
    reimbursement to the Bank for:
    15
    handling charges related to
    roller/compactor and nuclear density testing costs;
    15
    handling
    charges of the contractor/subcontractor; and costs associated
    with roller! compaction and nuclear density testing.
    This opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    0! L~.3-0QL~.2

    21
    ORDER
    The Board hereby affirms the Agency’s September 14,
    1992
    determination to deny reimbursement to the State Bank of
    Whittington for:
    1)
    $55.98 in handling charges in excess of
    15.
    (But see footnote #6.)
    2)
    $5,459.81 in surveying costs.
    3)
    $1,771.25 in personnel costs associated with seeking
    reimbursement from the Fund.
    The Board hereby reverses the Agency’s September 14,
    1992
    determination to deny reimbursement to the State Bank of
    Whittington for:
    1)
    $1,123.18 in handling charges associated with
    roller/compactor and nuclear density testing charges.
    2)
    $735.44 for contractor/subcontractor 15
    handling
    charges.
    3)
    $7,050.00 and $3,047.50 in costs associated with
    roller/compactor and nuclear density testing charges,
    respectively.
    IT IS SO ORDERED
    Section 41 of the Environmental Protection Act, (415 ILCS
    5/41
    (1992)), provides for appeal of final orders of the Board
    within 35 days.
    The Rules of the Supreme Court of Illinois
    establish filing requirements.
    (But see also 35 Ill. Adm. Code
    101.246,
    “Motions for Reconsideration”.)
    J. Theodore Meyer concurs
    I, Dorothy M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the abov
    opinion and order was
    adopted on the
    ~
    day of
    ____________,
    1993, by a vote
    of
    ~
    .
    Dorothy N.,4unn, Clerk
    Illinois E(9!llution Control Board
    01~3-00t~3

    Back to top