ILLINOIS POLLUTION CONTROL BOARD
    November 19,
    1992
    CARL MADOUX, ALICE MADOUX,
    )
    GLENN MOODY,
    AND
    MARGARET
    )
    MOODY,
    Complainants,
    )
    PCB 90—148
    (Enforcement)
    v.
    B
    & N STEEL SERVICE CENTER,
    INC.,
    Respondent.
    JAMES
    S.
    SINCLAIR, STOBBS
    & SINCLAIR APPEARED ON BEHALF OF THE
    COMPLAINANTS;
    PAUL H.
    LAUBER, FARRELL & LONG,
    P.C. APPEARED ON BEHALF OF THE
    RESPONDENT.
    OPINION
    AND
    ORDER OF THE BOARD
    (by G.T. Girard):
    This matter initially came before the Board on the August
    6,
    1990,
    formal complaint filed by Carl Madoux, Alice Madoux, Glenn
    Moody, and Margaret Moody (collectively, complainants) against B
    & M Steel Service Center,
    Inc.
    (B
    & M Steel).
    The Board accepted
    this matter for hearing on August 30,
    1990.
    The Board held a
    public hearing on June 30,
    1991, at Alton.
    Members of the public
    attended and participated at hearing.
    The complainants filed
    their post—hearing brief on August 12,
    1991.
    B
    & M Steel filed
    its response brief on September 5,
    1991.
    The complainants
    filed
    a reply brief on September 18,
    1991.
    On May 21,
    1992, the Board issued an interim opinion and
    order finding the respondent in violation of Section 24 of the
    Illinois Environmental Protection Act (the Act)
    (Ill. Rev.
    Stat.
    1992,
    ch.
    111 1/2, par.
    1024).
    The Board’s interim order
    directed the respondent to file a report detailing all measures
    that it believes would be effective to reduce the noise emissions
    at its facility and more specifically from the Pettibone
    forklifts and the pipe-striking-pipe.
    (Madoux et. al.
    v.
    B
    & M
    Steel Service Center,
    Inc., May
    21,
    1992,
    PCB
    hereinafter
    cited as “May 21 at”.)
    On September
    1,
    1992, the respondent filed its report with
    the Board and on September 30,
    1992, the complainants filed their
    reply.1
    Respondent states that it “is willing to or already has
    1
    The respondent’s report will be cited as “Res.
    rep.
    at”;
    the respondent’s document prepared by Engineering Dynamics
    International will be cited as
    “EDI
    rep.
    at”; the complainants’
    O137-OIL~J

    2
    taken some measures to reduce identifiable sound emissions” from
    its property.
    (Res.
    rep. at 1.)
    B
    & M indicated that in order to address the two major
    complaints of noise from the Pettibone forklift equipment and
    noise of pipe-on—pipe sound its consultant had developed two
    suggestions.
    The first remedy which B
    & M has already
    accomplished was to install “new, more efficiently designed
    mufflers” on the Pettibone forklifts.
    (Res. rep. at 2.)
    In
    addition,
    B
    & N installed engine side covers to muffle some of
    the sound other than exhaust.
    (Res.
    rep.
    at 2.)
    The total cost
    of these improvements “was approximately $1816.00”.
    (Res. rep.
    at 2.)
    The second control option offered by B
    & N is to redesign
    the sorting rack facilities to control the distance the pipe must
    travel before hitting the sorting table or other pipe.
    (Res.
    rep. at 2.)
    B
    & N indicated that it should be able to design and
    implement these changes within 120 days of a determination by the
    Board.
    (Res. rep.
    at 2.)
    The cost estimate set forth by B
    & N
    is “approximately $7980.00”.
    (Res. rep. at
    2.)
    The complainants’ reply maintains that the report filed by B
    & M’S consultants is inadequate.
    Complainants cite to numerous
    alleged flaws in the study in support of their positions.
    Therefore,
    complainants have several reservations concerning the
    proposed remedies offered by B
    & N.
    Specifically, complainants
    ask for verification of the installation of the mufflers and side
    panels including specific information regarding the type and
    model of muffler installed.
    (Corn. rep. at 7.)
    In addition, the
    complainants expressed concern as to whether or not the second
    remedy suggested by B
    & M will reduce noise.
    (Com.
    rep.
    at 7.)
    Noise report
    The noise evaluation report filed by B
    & N includes sound
    level data measured at various locations in and around the B
    & N
    facility, including measurements taken near the property line of
    one of the complainants.
    The report also includes a discussion
    of the control options for reducing noise emissions from B
    & M’s
    operation.
    The report includes long term noise measurement data made
    with Larson Davis 700—20 dosimeters and tape recordings made
    using a Nagra SJ recorder.
    Based on the analysis of noise
    measurement data, the report concludes that:
    (i) the pre—existing
    mufflers used on the Pettibones were adequate and that little,
    if
    any, benefit was gained by replacing the mufflers.
    (EDI rep. at
    9); and
    (ii)
    the levels of pipe noise do not warrant labeling
    reply will be cited as “Com. rep.
    at
    “.
    Ot370~2

    3
    them a nuisance, particularly when compared with other common
    sounds and when considering the larger picture of the acoustical
    environment.
    (EDI rep.
    at 9.)
    The noise control options discussed in B
    & M’s report
    address both yard vehicles
    (Pettibones) and pipe handling
    operations.
    The report states that replacing mufflers and re-
    installing the side panels did not have significant effect on
    noise emissions.
    However,
    the report recommends that the
    mufflers on the Pettibones be maintained in good working order
    and replaced at the end of their normal life
    (EDI rep. at 10).
    The EDI report includes a brief evaluation of three
    alternative options to reduce noise emissions from the pipe
    handling operation:
    (i)
    interior building acoustical treatment;
    (ii)
    acoustical barrier wall at north property line; and
    (iii)
    redesigning the pipe sorting rack facilities.
    The report states
    that insulating the interior walls of the building would result
    in reducing reverberant Sound by
    4 dB in mid and high
    frequencies.
    (EDI rep.
    at 10.)
    The report does not include the
    cost of applying such insulation;
    however,
    an estimate provided
    at hearing indicated the cost to be $6960.
    (Tr. 161-64.)
    The EDI report indicates that constructing a barrier wall at
    the north property line would reduce noise levels by
    9
    -
    12 dBA
    at 50 feet from the property line depending on the height of the
    wall
    (10’
    or 20’).
    (EDI rep.
    at
    10.)
    The report states that
    if
    a barrier wall
    is mandated,
    a smaller (lengthwise) wall
    constructed closer to the north door would be more effective.
    (EDI rep.
    at
    11.)
    The cost of
    a concrete barrier wall has been
    estimated to be $lOO/lin—ft for
    a
    10’ wall to $300/un—ft for
    a
    20’ barrier.
    The third option discussed in the noise report involves the
    redesigning of the sorting rack facilities.
    The report states
    that using web slings to catch pipes restricts the energy from
    pipe contact and reduces the contact/impact sound generated by
    pipe handling.
    (EDI rep.
    at 11.)
    However,
    the report does not
    provide any estimates of the magnitude of sound reduction.
    The
    cost of redesigning the sorting rack has been estimated to be
    $7980.
    (Res.
    rep.
    at 2.)
    This approach is one of the options
    which has been chosen by B
    & N to reduce the noise emissions froTr
    pipe handling operations.
    Complainant’s response
    The response filed by the complainants take issue with
    several points
    in the report submitted by the respondent.
    Mainly,
    the complainants are concerned that the respondent has
    undertaken to retry the case before the Board instead of
    addressing the problems found by the Board
    in its interim order.
    The complainants specifically take issue with the numerical noise
    OI37-OI~3

    4
    measurements included in the report to show that there is no
    noise pollution.
    (Com.
    rep. at 1).
    In addit!on, the
    complainants take issue with contents of the report dealing with
    the
    “Summary
    of Findings”, the “Procedures for Investigation and
    Measurement”, and “Noise Reduction Measures”.
    Specifically in the
    “Summary
    of
    Findings”,
    the
    complainants
    state that the citation to the noise regulations
    is not correct
    since
    it deals with numerical standards.
    The complainants also
    note that the use of term “maximum”
    in describing the sound
    values is not explained clearly.
    (Corn. rep. at 2.)
    With regard to the “Procedures for Investigation and
    Measurement”, the complainants maintain that the equipment used
    was dated and the data collected was not handled within industry
    standards for the measurement of noise.
    (Comp. rep. at 3.)
    In
    addition, the complainants point out that all sound measurements
    took place with the north door of the building open contrary to a
    suggestion made at hearing by Mr. Gregory Zak.
    (Comp. rep.
    at
    3.)
    Lastly,
    in reference to the “Noise reduction measures”,
    the
    complainants note that the report does not include the
    specifications of the mufflers used on the Pettibones or discuss
    other measures that may be needed to reduce noise emissions from
    the Pettibones.
    Regarding the pipe handling operation, the
    complainants note that the report does not provide any estimates
    of the noise reduction that would be achieved by redesigning the
    pipe sorting rack facilities.
    (Corn. rep.
    at 5.)
    In addition,
    the complainants point out that the report does not consider Mr.
    Zak’s proposal of enclosing the pipe handling operation as an
    alternative method of noise reduction.
    (Corn.
    rep.
    at 6.)
    In conclusion, the complainants argue that the respondent’s
    report does not adequately address the Board’s order to evaluate
    alternative measures to reduce noise emissions.
    The complainants
    urge the Board not to accept the report and proposals set out in
    the response.
    The complainants maintain that the Board should
    require the respondent to undertake further studies to evaluate
    the noise reduction potential of redesigning the sorting rack
    facilities.
    The complainants also ask that the Board require
    additional information regarding the measures used to control
    noise emissions from the Pettibones.
    DISCUSSION
    As previously stated, the Board’s interim order required B
    &
    N to prepare a report of alternative options that would be
    effective
    in
    reducing
    the
    noise
    emissions
    from
    its
    “Pettibone”
    front
    end
    loaders
    and
    from
    its pipe handling operations.
    However,
    although
    control
    measures
    for
    noise
    emissions
    were
    discussed, the noise report filed by B
    & M concentrates on trying
    0! 37-0
    LL~

    5
    to show that B
    & M’s operation is not a source of noise
    pollution.
    As previously explained in the interim order, numerical
    quantification of noise emissions is not controlling in
    determining violations pursuant to Section 24 of the Act and 35
    Ill.
    Athn.
    Code 900.102.
    (May 21 order at
    6.)
    Moreover, the
    Board has already found B
    & N in violation of Section 24 of the
    Act.
    Therefore,
    the Board will focus on the control measures
    discussed in the report.
    Regarding the complainants’ concerns
    about the adequacy of the report to address the requirements of
    the Board’s interim order,
    the Board finds that the report
    contains sufficient information to craft remedies to reduce noise
    pollution.
    The noise reduction measures are discussed below.
    Noise reduction measures for yard vehicles
    The Board notes that the respondent has already replaced
    mufflers and re-installed the side panels on the Pettibories.
    (Res. rep.
    at 1.)
    However, the noise report indicates that such
    measures did not result
    in significant numerical noise reduction.
    (EDI rep. at 4.)
    The complainants have stated that they believe
    that properly installed mufflers of type recommended by Mr.
    Zak
    (Nelson Model
    400) would reduce the Pettibone noise.
    (Corn. rep.
    at
    5
    & 7.)
    In this regard,
    the Board notes that the noise report
    does not include specifications of the new mufflers replaced on
    the Pettibones.
    However,
    B
    & M has stated that it obtained
    information as to the manufacturer, make and model of the muffler
    from Mr.
    Zak.
    (Res. rep.
    at 2.)
    In order to ensure that proper
    measures are undertaken by B
    & N to reduce noise emissions from
    Pettibones,
    the Board will direct B
    & N to install Nelson Model
    400 mufflers on its Pettibones if they have not already done so.
    Noise reduction measures for pipe handling operation
    In order to reduce noise emissions from pipe handling
    operations,
    control measures must be implemented to reduce noise
    generated from activities within the building and the open yard.
    B
    & N performs cutting and bundling operations within the
    building, and inspection and sorting of pipes is performed
    outside the building in the yard.
    (Tr. at 176—81.)
    The options discussed in the respondent’s noise report for
    attenuating noise emissions from within the building include
    insulating the interior walls,
    and constructing a barrier wall
    close to the north door of the building.
    In addition to these
    measures, Mr Zak suggested that the noise emissions may be
    reduced by keeping the building doors closed during operation
    (Tr.
    168.)
    B
    & N has not proposed to undertake any measures to
    reduce noise emissions generated from its activities within the
    building.
    However,
    since the record indicates that the
    activities within the building generate noise emissions,
    the
    0137-01ti5

    6
    Board will direct the respondent to apply insulation to the
    building’s interior walls and roof, and close all building doors
    during operation.
    B
    & N has proposed to redesign its sorting rack facilities
    to reduce noise emissions from its pipe handling activities
    performed in its open yard.
    The other options discussed in the
    noise report include constructing a barrier wall along B
    & M’s
    north property line.
    Another option suggested by Mr.
    Zak
    involves enclosing the inspection and sorting rack facilities
    within a insulated steel building.
    (Tr. at 161-64.)
    The Board
    notes that B
    & N will incur considerable cost if
    it is required
    to construct a building ($23,766)
    or a 200-foot barrier wall
    ($20,000.)
    On the other hand,
    the option proposed by B
    & M to
    redesign the sorting rack facilities would be less expensive
    ($7980)
    The proposed modification of sorting rack involves the
    reduction of the distance a pipe must travel before hitting the
    sorting table or another pipe and using web slings to catch the
    pipes.
    B
    & M has noted that this modification results in
    reduction of sound intensity by lessening the impact.
    (Res.
    rep.
    at 2.)
    B
    & M has not provided any estimate of noise reductions
    that would be achieved by redesigning the sorting rack.
    Since
    the impact of pipe on pipe contact is the primary cause of noise
    emissions from B
    & M’s facility, the Board believes that measures
    to lessen the impact energy would result in significant noise
    reduction.
    In this regard, Mr.
    Zak has also noted in his
    testimony that modification of operating procedures is an
    effective method of noise reduction.
    (Tr. at 155-56
    & 158.)
    Therefore,
    the Board will direct B
    & N to implement the
    modifications to its sorting rack facilities.
    CONCLUSION
    The Board finds that the report submitted by respondent’s
    is
    sufficient to allow the Board to determine what remedy should be
    applied.
    The Board notes however,
    that there are several areas
    of deficiencies in the report as well as the report’s attempt to
    declare the noise emissions a non-nuisance.
    That latter
    determination was already made in the Board’s May 21,
    1992,
    interim opinion and order.
    The Board directs the respondent to undertake the following
    remedies:
    (1)
    install Nelson Model 400 mufflers on its Pettibones
    if
    it has not already done so;
    (ii) apply fiberglass insulation
    to the interior walls and roof of its existing building;
    (iii)
    close all doors leading in or out of its building during
    operation except for when entering or exiting; and
    (iv) redesign
    all sorting facilities as set forth
    in its response to the Board.
    Further, the Board directs the respondent to cease and desist
    from vioiation of Section 24 of the Act,
    01310R6

    7
    ORDER
    The respondent,
    B
    & M Steel,
    shall undertake all measures
    necessary to cease and desist from further violations of Section
    24 of the Act.
    In addition respondent shall undertake the
    following measures to reduce noise emissions:
    1.
    the respondent shall install Nelson Model 400
    mufflers on its Pettibones if it has not
    already done so;
    2.
    the respondent shall apply fiberglass
    insulation to the interior walls and roof of
    its existing building;
    3.
    the respondent shall close all doors leading
    in or out of its building during operation
    except for when entering or exiting;
    4.
    the respondent shall redesign all sorting
    facilities as set forth in its response to
    the Board;
    5.
    the respondent shall cease and desist from
    further violation of Section 24 of the Act.
    Section 41 of the Environmental Protection Act
    (Ill. Rev.
    Stat.
    1991,
    ch.
    111 1/2, par.
    1041) provides for the appeal of
    final orders of the Board within 35 days.
    The Rules of the
    Supreme Court of Illinois establish filing requirements.
    (But
    see also 35 Ill.
    Adm. Code 101.246, Motions for Reconsideration,
    and Castenada v.
    Illinois Human Rights Commission
    (1989),
    132
    Ill.2d 304,
    547 N.E.2d 437.)
    Board Member R.
    C.
    Flemal dissents.
    IT IS SO ORDERED.
    I, Dorothy N. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opinion and order was
    adopted on the
    /9~
    day of
    7~’-~/~&y
    ,
    1992, by~avote
    of
    (~,—J.
    (1
    I
    Control Board

    Back to top