ILLINOIS POLLUTION CONTROL BOARD
    May 4, 2000
    PEOPLE OF THE STATE OF ILLINOIS,
    Complainant,
    v.
    ENVIRONMENTAL CONTROL AND
    ABATEMENT, INC.,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 95-170
    (Enforcement - Air)
    ORDER OF THE BOARD (by M. McFawn):
    Currently before the Board is “Complainant’s Motion for Reconsideration,” filed on
    March 27, 2000, seeking reconsideration of a finding by the Board in its order of February 17,
    2000. Specifically, complainant asks the Board to reconsider its finding that an issue of material
    fact existed as to respondent Environmental Control and Abatement, Inc.’s (ECA) liability for
    violation of asbestos regulations in connection with an asbestos removal project in Urbana,
    Illinois.
    1
    ECA filed a response opposing complainant’s motion on April 4, 2000. Upon
    reconsideration, the Board concludes that complainant is correct that each individual
    nonscheduled renovation operation requires a separate notification to the Illinois Environmental
    Protection Agency (Agency) if the renovation operation involves asbestos above the regulatory
    threshold amount. Accordingly, the Board modifies its order of February 17, 2000 to grant
    summary judgment in complainant’s favor with respect to the violations of 40 C.F.R. 61.145
    and 415 ILCS 5/9.1(d) alleged in connection with the Urbana project.
    This case involves alleged violations of provisions of the National Emission Standards
    for Hazardous Air Pollutants (NESHAP) for asbestos. The asbestos NESHAP is codified at 40
    C.F.R. 61 Subpart M, which includes 40 C.F.R. 61.145. The alleged violations of this federal
    regulation are within the Board’s jurisdiction because Section 9.1(d) of the Illinois
    Environmental Protection Act (Act), 415 ILCS 5/9.1(d) (1998), prohibits violation of any
    regulation adopted pursuant to Section 112 of the federal Clean Air Act, 42 U.S.C. 7412.
    The Urbana project involved the removal of 1,900 linear feet of asbestos-containing
    piping insulation from a building owned by the University of Illinois. Section 61.145 requires
    each owner or operator of a renovation activity to provide notice of the proposed activity to the
    Agency if the amount of regulated asbestos-containing material (regulated ACM, or RACM)
    involved exceeds a certain threshold. (See Section 61.145(a)(4)(i) for threshold amounts and
    Section 61.145(b) for notice requirements.)
    1
    The Board’s February 17, 2000 order addressed alleged violations at five different project
    sites, but complainant’s motion involves only rulings in connection with the Urbana site.

    2
    The relevant provisions of Section 61.145 provide:
    (a)
    Applicability. To determine which requirements of paragraphs (a), (b),
    and (c) of this section apply to the owner or operator of a demolition or
    renovation activity and prior to the commencement of the demolition or
    renovation, thoroughly inspect the affected facility or part of the facility
    where the demolition or renovation operation will occur for the presence
    of asbestos, including Category I and Category II nonfriable ACM. The
    requirements of paragraphs (b) and (c) of this section apply to each
    owner or operator of a demolition or renovation activity, including the
    removal of RACM as follows:
    * * *
    (4)
    In a facility being renovated, including any individual
    nonscheduled renovation operation, all the requirements of
    paragraphs (b) and (c) of this section apply if the combined
    amount of RACM to be stripped, removed, dislodged, cut,
    drilled, or similarly disturbed is
    (i)
    At least 80 linear meters (260 linear feet) on pipes or at
    least 15 square meters (160 square feet) on other facility
    components[.]
    ***
    (iii)
    To determine whether paragraph (a)(4) of this section
    applies to planned renovation operations involving
    individual nonscheduled operations, predict the combined
    additive amount of RACM to be removed or stripped
    during a calendar year of January 1 through December 31.
    * * *
    (b)
    Notification requirements. Each owner or operator of a demolition or
    renovation activity to which this section applies shall:
    (1)
    Provide the Administrator with written notice of intention to
    demolish or renovate. Delivery of the notice by U.S. Postal
    Service, commercial delivery service, or hand delivery is
    acceptable.
    ***
    (3)
    Postmark or deliver the notice as follows:

    3
    (i)
    At least 10 working days before asbestos stripping or
    removal work or any other activity begins (such as site
    preparation that would break up, dislodge or similarly
    disturb asbestos material), if the operation is described in
    paragraphs (a) (1) and (4) (except (a)(4)(iii) and (a)(4)(iv))
    of this section. ***
    (ii)
    At least 10 working days before the end of the calendar
    year preceding the year for which notice is being given for
    renovations described in paragraph (a)(4)(iii) of this
    section.
    * * *
    (4)
    Include the following in the notice:
    * * *
    (v)
    Procedure, including analytical methods, employed to
    detect the presence of RACM and Category I and
    Category II nonfriable ACM.
    (vi)
    Estimate of the approximate amount of RACM to be
    removed from the facility in terms of length of pipe in
    linear meters (linear feet), surface area in square meters
    (square feet) on other facility components, or volume in
    cubic meters (cubic feet) if off the facility components.
    Also, estimate the approximate amount of Category I and
    Category II nonfriable ACM in the affected part of the
    facility that will not be removed before demolition.
    These provisions require a notice to be submitted to the Agency if a renovation will
    involve asbestos above a certain threshold amount. The regulation provides for different types
    of notices to be used in different circumstances, two of which are of concern to us in this case:
    a standard ten-day notice of an upcoming operation (Section 61.145(b)(3)(i)) and an annual
    notice covering various individual nonscheduled renovation operations to be undertaken in the
    coming calendar year (Section 61.145(b)(3)(ii)). ECA submitted a ten-day notice for the
    Urbana project, but it lacked the information required under Section 61.145(b)(4)(v) and (vi).
    ECA argued, however, that the project had been covered by an annual notice submitted by the
    University. The annual notification was not submitted in connection with the parties’ summary
    judgment motions. ECA argued that it was not required to submit an individual notice of the
    project—the notice it provided was submitted merely as a courtesy to the Agency—so any
    defects in the ten-day notice it did submit would not have been violations of the NESHAP
    regulations.

    4
    In its February 17, 2000 order, the Board found that an issue of material fact existed as
    to the existence and scope of an annual notification for the Urbana facility. The Board
    concluded that if such a notification was submitted, it could have covered ECA’s work. In its
    analysis, the Board stated:
    We note the People’s argument that the Urbana project was subject to the
    notification requirement because it involved 1900 linear feet of RACM. People’s
    Response at 3-4. The issue here is not whether the project was subject to the
    notification requirement—clearly it was. The question is rather whether an
    annual notification submitted by the University covered this project, and if so, if
    ECA’s work would be considered a specific nonscheduled operation within the
    noticed project. If a project (of whatever size) is covered by an annual
    notification, a separate notification is not required even though a specific
    operation may involve more than the threshold amount of RACM. See 40
    C.F.R. 61.145(b)(3)(i), (ii), (iv). People v. Environmental Control and
    Abatement, Inc. (February 17, 2000), PCB 95-170, slip op. at 11.
    Among the purposes of a motion for reconsideration is to bring to the tribunal’s attention
    errors in the application of existing law. Korogluyan v. Chicago Title & Trust Co., 213 Ill.
    App. 3d 622, 627, 572 N.E.2d 1154, 1158 (1st Dist. 1991); see also 35 Ill. Adm. Code
    101.246(d). In seeking reconsideration, complainant asserts that the Board erred in its
    application of Section 61.145. Based on the language of Section 61.145(a)(4), complainant
    argues that, notwithstanding any annual notice that may have been submitted, where the amount
    of RACM involved in a particular nonscheduled renovation operation exceeds the regulatory
    threshold, a separate notice must be provided for that nonscheduled renovation operation.
    Complainant cites no authority in support of its arguments. Nevertheless, given
    complainant’s arguments, the Board has identified an ambiguity in the terms of Section 61.145.
    Paragraphs (a)(4), (a)(4)(iii), (b)(3)(i) and (b)(3)(ii) can credibly be read either to require a
    separate notice for individual nonscheduled operations that involve more than the threshold
    amount of RACM (as urged by complainant) or to permit an annual notice to cover such
    nonscheduled operations (as the Board ruled in its February 17, 2000 order). To resolve this
    ambiguity, we have reviewed the comments of the United States Environmental Protection
    Agency in connection with the amendments to Section 61.145 that added these provisions. We
    note the following statement from the “Notice of Proposed Rule Revision” published at 54 Fed.
    Reg. 912 (January 10, 1989):
    To clarify whether planned renovations involving individual, nonscheduled
    operations must comply with the notification provisions of § 61.145(b),
    paragraph (a)(4)(i), is modified to require that the additive amount of asbestos to
    be removed or stripped over a calendar year of January 1 through December 31
    be used instead of over the “maximum period of time a prediction can be made
    not to exceed 1 year.” This clarifies the intent of the current regulation to cover
    individual, nonscheduled asbestos removal operations involving small amounts of
    asbestos if the total amount of asbestos that will be removed in 1 year is

    5
    projected to exceed the quantities of asbestos specified in § 61.145(a). When
    individual renovations exceed the cutoff, a separate notification is required. 54
    Fed. Reg. at 917 (emphasis added).
    Based on this federal comment, we conclude that complainant is correct that a separate
    notice was required for the Urbana project, notwithstanding that the University may have
    submitted an annual notice, because the project involved more than the regulatory threshold
    amount of RACM,
    i.e.
    , 1,640 linear feet over the threshold level of 260 linear feet. Neither
    party disputes that the notice submitted by ECA in connection with the Urbana project did not
    indicate the procedure and analytical methods that would be used to detect the presence of
    ACM, nor did it indicate the approximate amount of RACM to be removed from the site, as
    required by Section 61.145(b)(4)(v) and (vi). Accordingly, summary judgment should have
    been entered in complainant’s favor with respect to the alleged violations of Section
    61.145(b)(4) and Section 9.1(d) of the Act.
    Therefore, that portion of the Board’s February 17, 2000 order denying complainant’s
    motion for summary judgment with respect to alleged violations of Section 61.145(b)(4)(v) and
    (vi) and Section 9.1(d) of the Act in connection with the Urbana project is vacated, and the
    Board grants complainant’s motion for summary judgment on those alleged violations. The
    Board reserves ruling on the issue of an appropriate remedy pending a hearing on the alleged
    violations not resolved in this order or the Board’s order of February 17, 2000.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the 4th day of May 2000 by a vote of 7-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board

    Back to top