ILLINOIS POLLUTION CONTROL BOARD
    February 27,
    1992
    FIRST BUSEY TRUST
    & INVESTMENT
    )
    CO..,
    as Trustee of the
    ANNE
    )
    LAYCOCK TRUST,
    Petitioner,
    v.
    )
    PCB 91—213
    )
    (Underground Storage
    ILLINOIS’ ENVIRONMENTAL
    )
    Tank Reimbursement)
    PROTECTION AGENCY,
    )
    )
    Respondent.
    E. PHILLIPS KNOX
    AND
    DARIUS PHEBUS, PHEBUS, TUMMELSON, BRYAN
    &
    KNOX APPEARED ON BEHALF OF PETITIONER
    RONALD SCHALLAWITZ APPEARED ON BEHALF OF RESPONDENT
    OPINION.
    AND
    ORDER OF THE BOARD
    (by B.
    Forcade):
    This matter is before the Board on a petition for review
    filed November 7,
    1991, by petitioner First Busey Trust
    &
    Investment Co.
    (First Busey),
    as Trustee of the Anne Laycock
    Trust, pursuant to IllRev. Stat.
    1991,
    ch.
    111 1/2,
    par.
    1022.18b(g)
    and 1040.
    First Busey challenges the Environmental
    Protection Agency’s
    (Agency) determination that a $100,000
    deductible applies to First Busey’s application for reimbursement
    from the Underground Storage Tank (UST)
    Fund for corrective
    actions.
    A hearing was held on January 15,
    1992 in Urbana,
    Illinois.
    The Petitioner filed its closing argument and brief on
    January 28,
    1992.
    The Agency filed its post hearing brief on
    February 3,
    1992.
    FACTS
    First Busey as Trustee for the Anne Laycock Trust was the
    owner of a commercial site at 1209 E. University Ave.
    in Urbana,
    Illinois.
    (Pet.
    p.
    1).
    The property contains two underground
    storage tanks.
    The 600 gallon tank (T-1)
    was originally used to
    store tractor fuel and then to store waste oil from farm
    equipment for pump out disposal.
    The 1,700 gallon tank (T-2) was
    originally used for heating oil and then converted to the storage
    of waste oil from farm equipment for pump-out disposal.
    The
    tanks have not been used since prior to April,
    1987.
    (Tr.
    12).
    The property was leased to Massey—Ferguson,
    Inc.
    for
    operation of a farm implement dealership from May of 1966 to
    April
    1,
    1987 from First Busey’s predecessor.
    On April
    1,
    1987
    Heartland Power Co.
    (Heartland) became the lessee and operator of
    130—287

    2
    the property.
    Heartland employed aboveground storage tanks for
    waste oil disposal and did not use the underground storage tanks.
    (Tr.
    12).
    In fall of 1989, Heartland and First Busey began
    negotiations for the sale of the property to Heartland.
    (Tr.
    24)
    As part of the sale of the property, First Busey and
    Heartland agreed that First Busey would remove T—1 and T—2 since
    the tanks had not been used since April
    1,
    1987.
    The tanks were
    pulled on March 14 and 15,
    1990 at which time a release of
    petroleum was discovered.
    ESDA was notified of the release on
    March
    15’,
    1990.
    (Ag. Rec. p.23).
    The tanks were registered with
    the Office of the State Fire Marshal
    (OSFM)
    on March
    5 and April
    5,
    1990.
    (Ag. Rec. pp.
    24
    & 25).
    On May 3, 1991 First Busey submitted an Application for
    Reimbursement from the Illinois Underground Storage Tank Fund.
    (Pet.
    Ex.
    1, Ag. Rec. pp.
    21—27).
    The Agency received this
    application on May 9,
    1991.
    (Pet.Ex.
    3).
    The Agency did an
    initial review of the application on June 20,
    1991.
    •As a result
    of this review the Agency sought confirmation of the tank
    registration from the OSFM.
    The necessary information was
    received from the OSFM on July 26,
    1991.
    (Tr.
    73).
    After further
    review of the application, the Agency, on August 14, sent First
    Busey a letter requesting documentation that there was no prior
    knowledge of the petroleum release that was discovered on March
    14,
    1990.
    (Ag. Rec. p.44).
    On September 12,
    1990,
    the Agency
    received letters from Mike Murphy, trust officer at First Busey,
    and James Strong of Strong Associates Ltd. stating there was no.
    knowledge of the release of petroleum prior to July 28,
    1989.
    (Ag. Rec.
    pp.
    35-37).
    Mr. Strong was hired by First Busey to
    assist in the sale of the property and the removal of the tanks.
    The Agency on October 4, 1991 informed First Busey that a
    $100,000 deductible would apply to First Busey’s application for
    reimbursement.
    (Ag. Rec.
    pp.
    48,
    49).
    First Busey
    is appealing
    the Agency’s determination that a $100,000 deductible applies.
    Whether the $100,000 deductible applies depends on which law
    is applied to the application.
    The relevant dates in determining
    which law is to be applied in reviewing First Busey’s application
    for reimbursement are:
    May 9,
    1991
    —application received by the Agency,
    July 26,
    1991
    -information received from the OSFN,
    September 6,
    1991
    -effective date of new legislation
    September 12,
    1991
    -Agency received letter from petitioner
    concerning knowledge of release.
    The status of Petitioner’s application on these dates will
    determine which law is to be applied.
    The issues in this case involve the applicable law to be
    applied when reviewing an application for reimbursement, the
    130—288

    3
    interpretation of the phrase “in use on that date at that site”
    in Section 22.l8b(d) (3) (B)
    (i)
    of the Environmental Protection Act
    (Act) and when an application is considered filed.
    ARGUMENT
    The Agency concluded that the $100,000 deductible applied to
    •First Busey’s reimbursement application under Section
    22.18b(d) (3) (B) (i)
    of the Environmental Protection Act
    (Act)
    as
    amended on September
    6,
    1991.
    The amended statute reads in part:
    If prior to July 28,
    1989 the owner or
    operator had registered none of the
    underground storage tanks at the site on that
    date,
    the deductible amount under
    subparagraph
    (A)
    of paragraph
    (3)
    of this
    subsection(d) shall be $100,000 rather than
    $10,000.
    (PA 87—323, HB 1741, effective
    September 6,
    1991)
    The Agency states that it applied this section to the
    Petitioner’s application because it was the applicable provision
    of the Act in effect at the time that a complete application was
    received from the Petitioner.
    The Agency considered First
    Busey’s application to be complete on September 12,
    1991 when the
    Agency received the letter from First Busey documenting there was
    no knowledge of the release prior to July 28,
    1989..
    The Agency
    determined that the $100,000 deductible applied because the tanks
    were not registered prior to July 28,
    1989.
    The petitioner argues that the provision to be applied to
    their application should be the statute in effect at the time
    their original application was filed on May 9,
    1991.
    The
    applicable provision of the Act (Section 22.18b(d)(3)(B)(i))
    effective on this date reads
    in part:
    If prior to July 28,
    1989 the owner or
    operator had registered none of the
    underground storage tanks in use on that date
    at the site,
    the deductible amount under
    subparagraph
    (A)
    of paragraph
    (3)
    of this
    subsection(d) shall be $100,000 rather than
    $10,000.
    (PA 86—958, effective December 5,
    1989) (Emphasis added)
    Petitioner further argues that the application was complete
    upon receipt of the information from the OSFM.
    The petitioner
    argues that the application satisfied the reimbursement checklist
    prepared by the Agency and therefore should be considered
    complete.
    The Petitioner concludes that if the application was
    complete on July 26,
    1991, the application should be reviewed
    130—289

    4
    under the statute as it read prior to it being amended on
    September 6,
    1991.
    The amendment to the statute changed the phrase “in use on
    that date at the site” to “on that date at the site.”
    In A.K.A.
    Land Inc. v. EPA, PCB 90—188
    (March 14,
    1991) the Board construed
    “in use” as meaning that the UST5 are utilized in the active
    sense.
    If this provision is applied to First Busey’s
    application, the $100,000 deductible would not apply since the
    tanks were not being actively used on July 28, 1989.
    The tanks
    have not been used since prior to April
    1,
    1987 when Heartland
    began to lease the property.
    To determine which deductible applies to First Busey’s
    application we must determine what is the applicable law and when
    an application is “filed.”
    APPLICABLE
    LAW
    The Board has held that the applicable law to be applied is
    that which is in effect upon the date of the filing of the
    application for reimbursement.
    Pulitzer Community News~a~er,
    Inc. v.IEPA, PCB 90—142
    (December 5,
    1989), Marjorie B.
    Canrnbell
    V;
    IEPA, PCB 91—5
    (June
    6, 1991).
    In Pulitzer, the Agency denied the applicant access to the
    fund because at the time of the release, ESDA was not notified.
    The statute requiring notification of ESDA became effective one
    month after the release was discovered.
    The Board held that
    “Pulitzer cannot be required to comply with a regulation
    requiring notification of a release which was not in effect at
    the time of the discovery of the release.”
    Pulitzer, PCB 90-
    142,
    p.4.
    The Agency argues that the law that should be applied when
    reviewing an application for reimbursement is the law that exists
    when the decision is made.
    The Agency further argues that
    Gallatin National Co.
    v. IEPA, PCB 90—183
    (January 18,
    1991)
    supports this argument.
    The Board notes that there are distinct
    factual differences between Gallatin and this case.
    Gallatin
    involved applying current law to the issuance of a permit for a
    landfill operation.
    The most important distinction to be made
    between the issuance of permits and underground storage tank
    determinations is that permits govern actions that will occur in
    the future while in UST cases the clean up of the’site has
    already taken place and the only future action involves
    accessibility to the fund.
    The corrective actions at an
    underground storage site are often performed with reimbursement
    from the fund in mind.
    The regulations require that permit
    decisions be made within a specified time period after an
    application is filed,
    there is no similar time requirement for
    reimbursement decisions.
    Due to the difference between permits
    130—290

    5
    and underground storage tank reimbursements Gallatin is not~
    applicable to the present case.
    The Board finds no reason to go against the holding in
    Pulitzer and Campbell.
    The Board also sees potential problems in
    applying the law in effect when the decision is made to UST
    reimbursement determinations.
    The applicant who submits an
    application prior to a change in the statute would not know when
    the decision is being made and therefore.would not know which
    statute was applied until after the determination was made.
    Since th’e Agency has complete control oi~-erwhen a determination
    is made it could effectively control which law is to be applied
    to an application.
    The Agency makes a determination pertaining
    to access to the fund, applicable deductible and eligibility of
    costs.
    These determinations can be made at different times by
    the Agency.
    If the law in effect at the time the decision is
    made is applied,
    it is conceivable that determinations on
    accessibility and cost recovery would be made under two different.
    statutes.
    FILING OF A COMPLETE APPLICATION
    The Agency argues that an application is not necessarily
    filed when it is received by the Agency or date-stamped.
    The
    Agency contends that the application is not filed until all
    documentation needed to review the application has been received
    by the Agency.
    The Board agrees with the Agency that an
    application cannot be considered filed unless it is complete.
    The Agency cannot proceed in making its determination if the
    information required is not included in the application.
    When
    the Agency finds an application incomplete the applicant should
    be notified in order to remedy the deficiencies.
    An incomplete
    application should either be rejected or the applicant given a
    specified time period to supply the required information.
    However, the question remains as to when an application can be.
    considered complete.
    The determination of when an application can be considered
    complete and therefore filed is a factual determination.
    Therefore, we look at the handling of First Busey’s application
    to make this determination.
    Petitioner’s application contains forms entitled
    Notification for Underground Storage Tanks addressed to the .OSFM
    along with copies of cancelled checks payable to OSFM.
    (Pet.Ex.
    1,
    Ag.
    Rec. pp.
    1-5,
    pp.
    13-15).
    Attached to the form included
    under Tab Al Registration in the application
    (Ag. Rec.
    p.1)
    is a
    note stating:
    Our request to the OSFM for Registration Date and
    certification has been awaiting action for more than
    ten months.
    These documents are submitted ‘in lieu of’
    130—291

    6
    per the instructions of Mr. Kyle Rominger,
    IEPA.
    Mr.
    Strong, who was primarily responsible for preparing the
    application, testified concerning these forms and the note.
    I put this on the sticker because
    I had not been able
    to get the document which was referred to in the
    administrative instructions for this form from the
    office of the state fire marshal and having worried
    about it--by worried I mean phoning the fire marshal
    and’ others to get a complete file.
    I called the Agency
    to an action person who turns out from this notice to
    be Mr. Kyle Rominger and
    I said we’re ready to submit
    except that we’re gonna have to submit.
    .
    .
    .It’s
    interesting that just before
    I talked to Mr. Rominger
    I
    talked to the fire marshal action person for providing
    the document to me and I thought it had been lost.
    Ten
    months is a long time and they said no,
    it’s right
    here.
    It’s coming up.
    It’ll come up.
    And
    of course
    it hasn’t come up yet.
    We still do not have that
    document.
    So it’s lucky
    I did work out with Mr.
    Rominger a substitute procedure.
    (Tr.
    61,
    62)
    Karl Kaiser, project manager with the Agency performed an
    initial review of the petitioner’s application on June 20,
    1991.
    At hearing, Mr Kaiser testified as to his findings and subsequent
    actions regarding his initial review of this application:
    Q.
    What was your conclusion in June of 1991 as to this
    application?
    A.
    At that particular time I considered this application
    incomplete.
    Q.
    Why was that?
    A.
    It needed verification of proof of registration and fee
    payment and it had some inconsistencies in the tank
    information.
    Q.
    How did you attempt to clarify these questions that you
    had in your mind?
    A.
    I requested the information that I would need to clarify
    these items from the office of the state fire marshal.
    (Tr.
    73)
    The Agency received the requested information from the OSFM on
    July 26,
    1991.
    (Ag.
    Rec.
    38
    & 39).
    130—292

    7
    First Busey’s application was incomplete because it did not
    contain the required information concerning the tank
    registration.
    Mr. Strong was unable to obtain the required
    information from the OSFN to complete the application, therefore
    he contacted the Agency who provided an alternate means of filinç
    the application.
    It is undisputed that Mr. Rominger,
    of the
    Agency, provided Mr~Strong with a substitute procedure to submit
    the application without the required information from the OSFM.
    Mr. Rominger’s instructions to submit the forms “in lieu” of the
    required, documents represents the Agency’s acceptance of the
    application as submitted.
    The receipt of the information from
    the OSFM cured the deficiencies in the application discovered by
    the Agency in their initial review.
    The petitioner’s application was next reviewed by the Cost
    Authorization Decision Group of the Agency sometime between
    August
    8 and August 14.
    Cindy Davis, Southern subunit manager
    with the Agency, testified as to the findings of this review:
    We decided that the application was not complete
    because it did not have a statement from the
    owner/operator stating that he did not have prior
    knowledge of the release
    Our old application does
    not have that question asked and in a previous
    Pollution Control Board decision, which was Sparkling
    Springs Mineral Water,
    the Board suggested and strongly
    suggested that we ask the owner/operators to provide
    proof that they did not have any prior knowledge.
    (Tr. 101)
    The Agency subsequently developed a new application form in July
    of 1991 that required the owner/operator to demonstrate the there
    was no actual or constructive knowledge of the release prior to
    July 28,
    1989.
    (Tr.
    102)
    (Res.
    Ex.
    1).
    In reviewing old
    applications, the Agency notified the applicant and requested the
    applicant supplement the application by providing a statement
    concerning prior knowledge.
    (Tr.
    103).
    When the Petitioner originally filed its application, the
    Agency did not require documentation concerning prior knowledge.
    The new application requiring documentation was developed in July
    of 1991, more than two months after the original application was
    filed.
    In Pulitzer the Board accepted the date that a letter
    requesting reimbursement was sent to the Agency as the date the
    application was filed because reimbursement forms had not yet
    been developed by the Agency.
    However, the Board cautioned that
    the circumstances in Pulitzer were unusual and therefore much of
    the discussion pertained only to those cases which fall intoa
    “gap” period where procedures are not soundly in place.
    A “gap”
    130—293

    8
    existed when First Busey’s application was being reviewed by the
    Agency.
    The Agency developed a new reimbursement form in July of
    1991, based on recommendations in Sparkling Spring Mineral Water
    V.
    IEPA, PCB 91-9
    (May 9,
    1991).
    For reimbursement applications
    received on old forms after July of 1991, the Agency requested
    the applicant to supplement the application with proof that there
    was no prior knowledge of the release.
    This transitional period
    of adopting the new form created a “gap” period.
    Upon developing
    the new form all.the applications pending before the Agency,
    in
    which knowledge of the release was at issue, required additional
    information before a decision could be made.
    First Busey was
    unable to submit a complete application because •the new forms
    requiring proof that no prior knowledge existed where not
    available at the time First Busey filed its application for
    reimbursement.
    An applicant cannot be expected to comply with the
    requirements for an application that are not in effect at the
    time that the application is filed with the Agency.
    An
    application is considered complete if it meets the requirements
    in place. at the time that the application is received by the
    Agency.
    First Busey’s application was complete on July 26,
    1991
    when the Agency received the tank registration information from
    the OSFN because the application contained the information
    requested by the current reimbursement form.
    The new form
    requiring proof that there was no prior k.nowledge was not
    available at the time the application was submitted to the
    Agency.
    CONCLUSION
    The Board finds that the Petitioner’s application should
    have been considered as filed complete on July 26,
    1991 and the
    applicable provisions of the statute in effect on that date
    applied to determine the Petitioner’s appropriate deductible.
    The applicable law to be applied to this application is PA 86-
    958, effective December 5,
    1989.
    Since the tanks were not in use
    on July 28,
    1989 or registered before that date the $100,000
    deductible does not apply.
    This matter is remanded to the Agency
    to apply the appropriate deductible to First Busey’s application
    and determine which costs are recoverable.
    The Board also notes that it has decided to remand to the
    Agency those Agency determinations of eligibility which did not
    reach the issue of reimbursability of costs and deductibility.
    In Ideal Heating v.
    IEPA, PCB 91—523,
    (January 23,
    1992)
    the
    Board held that such incomplete determinations are not
    appealable.
    The Board applies this principle only in cases where
    no hearing has been held.
    Because a hearing was held in this
    case, the Board, therefore,
    has decided this case on the merits.
    130—294

    9
    The above Opinion constitutes the Board’s finding of fact
    and conclusions of law in this matter.
    ORDER
    The October 4,
    1991 Agency determination of a $100,000
    deductible on Petitioner’s application is hereby reversed and
    this matter is remanded to the Agency.
    IT IS SO ORDERED.
    aC.
    Marlin abstained.
    Section 41 of the Environmental Protection Act
    (Ill.Rev.Stat. 1991 ch.
    111 1/2, par.
    1041) provides for the
    appeal of final orders of the Board within 35 days.
    The Rules of
    the Supreme Court of Illinois establish filing requirements
    I, Dorothy N. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby cer~if
    hat the abo~y~
    Opinion and Order was
    adopted on/the ~
    day of
    _____________________,
    1992 by a
    vote of
    (42~
    .
    j
    ~orothy
    M. Gup~’~,Clerk
    Illinois Poli~tionControl Board
    130—295

    Back to top