    On January 15, 1993, General Che~iica1Corporation (General
    Chemical) filed a waiver of the decision deadline. General
    Chemical extended the decision deadline for forty—eight days.
    General Chemical notes that it has agreed to a forty-five day
    extension of the filing of the Agency’s
    r.coaaemdation.
    The
    filing of the Agency recommendation is specified in the Board’s
    procedural rules. The Agency recommendation
    is
    required to be
    filed within 30 days of the filing of the petition. (Section
    104.180) The Agency’s recoantendation on’ this variance petition
    is due on February 1, 1993. Modifications to the Board’s
    procedural requirements may not be aade without approval frog the
    Board. The Agency has not filed a request for
    an
    extension for
    the filing of its recommendation. The Agency is requested to
    file a motion for an extension of the filing of the Agency’s
    recommendation or to file the Agency recommendation in accordance
    with the Board’s rules.
    IT IS SO ORDERED.
    I, Dorothy
    M.
    Gunn, Clerk of the Illinois Pollution Control
    Board, hereby ce ty that the above order was adopted on the
    ~‘j
    4A’
    day of ____________________, 1993, by
    a
    vote. of
    (~O
    Dorothy N. G~t~, Clerk