DISSENTING OPINION (by J.C. Marlin)
)
)
)
)
)
)
)
)
PCB 91—174
(Underground Storage Tank
Fund Reimbursement
Determination)
I decline to join the majority’s opinion and order in this
case. I do not believe the petitioner, having decided to remove
the tank, becomes eligible to receive reimbursement from the fund
for the cost of tank removal, because contamination is later
found. The petitioner’s costs of tank renioval are not
“corrective action” costs in that instance.