ILLINOIS POLLUTION CONTROL BOARD
    August
    13,
    1992
    STEPHEN A.
    SMITH, d/b/a ABC
    )
    SANITARY HAULING, JOHN APPL,
    d/b/a
    APPL SANITARY SERVICE, LAWRENCE
    )
    W. BOLLER II, d/b/a AREA GARBAGE
    )
    SERVICE, CHARLES H. MILLER, d/bfa
    )
    C.H. MILLER SANITARY, CHRIS
    )
    JOHNSON,
    d/b/a CHRIS’S SERVICE CO.,
    )
    EDDIE L.
    COOK,
    SR.,
    d/b/a COOK’S
    )
    SANITARY HAULING, DON CORY, d/b/a
    )
    CORY SANITARY HAULING, RONALD E.
    )
    HAYDEN, d/b/a HAYDEN SANITARY SERVICE,
    )
    GORDON FICKLIN, d/b/a ILLINI SANITARY
    )
    SERVICE,
    CHRIS YAGER, d/bfa KLEAN-WAY
    DISPOSAL, GEORGE McLAUGHLIN,
    d/b/a
    )
    MCLAUGHLIN SANITARY,
    CHERYL MANUEL,
    )
    d/b/a ROLLAWAY WASTE,
    RONALD W. MANUEL,
    )
    PCB 92-55
    d/b/a RON MANUEL SANITARY, RUSSELL
    )
    (Landfill Siting
    SHAFFER, d/b/a SHAFFER SANITARY CO.,
    )
    Review)
    WILLIAM
    C. UDEN, d/b/a UDEN
    & SONS
    )
    SANITARY HAULING, and WILLIS SANITARY
    )
    HAULING,
    INC.,
    )
    Petitioners,
    v.
    CITY OF CHAMPAIGN,
    ILLINOIS,
    )
    INTERGOVERNMENTAL SOLID WASTE DISPOSAL
    )
    ASSOCIATION,
    and
    )
    XL DISPOSAL CORPORATION,
    Respondents.
    GLENN A. STANKO,
    of RENO,’ O’BYRNE & KEPLEY, APPEARED ON BEHALF OF
    PETITIONERS;
    TRISHA A. CROWLEY APPEARED ON BEHALF OF RESPONDENT THE CITY OF
    CHAMPAIGN; and
    JEFFREY
    W. TOCK,
    of TOCK
    & MILLER,
    LTD., APPEARED ON BEHALF OF
    RESPONDENTS INTERGOVERNMENTAL SOLID WASTE DISPOSAL ASSOCIATION
    AND XL DISPOSAL CORPORATION.
    OPINION AND ORDER OF THE BOARD
    (by J. Theodore Meyer):
    This matter is before the Board on an April 15,
    1992
    petition for review of the March
    3,
    1992 action of respondent the
    0135-0303

    2
    City of Champaign (Champaign).
    Petitioners Steven A.
    Smith,
    d/b/a ABC Sanitary Hauling,
    et al.
    (collectively,
    petitioners)
    are all engaged
    in the sanitary hauling business in Champaign,
    the City of Urbana, and/or the unincorporated sections of
    Champaign County.
    Petitioners ask this Board to review
    Champaign’s action on a request for site location approval of a
    material recovery/transfer facility.
    The petition for review is
    brought.pursuant to Section.40.1 of the Environmental Protection
    Act (Act).
    (Ill.Rev.Stat.
    1991,
    ch.
    111½,
    par.
    1040.1.)
    This
    Board held a public hearing on the petition for review on June
    15,
    1992,
    in Champaign.
    PROCEDURAL HISTORY
    On September 16,
    1991, pursuant to Section 39.2 of the Act
    and a Champaign city ordinance, respondents Intergovernmental
    Solid Waste Disposal Association
    (ISWDA) and XL Disposal
    Corporation
    (XL)
    jointly filed an application with Champaign for
    siting approval of a material recovery/transfer facility.
    (C.
    1-
    467.)1
    ISWDA, which is an Illinois municipal joint action agency
    whose members are Champaign, Urbana, and Champaign County, was
    identified as the owner of the proposed facility.
    XL,
    an
    Illinois corporation, was identified as the operator of the
    facility.
    (C.
    6.)
    The facility is proposed to be located on a
    25 acre site within Champaign’s city limits,
    immediately north of
    a forging company and immediately west of a railroad right-of-
    way.
    (C.
    10.)
    Hearings on the application were conducted by an
    appointed hearing officer on December 16,
    17,
    19,
    and 20,
    1991.
    Oral public comment was heard on January 2,
    1992,
    and written
    comments were accepted through February 3,
    1992.
    The Champaign City Council held study sessions on the
    application on February
    13 and 20,
    1992.
    On March 3,
    1992, the
    city council considered Council Bill No.
    92—58, entitled. “An
    Ordinance Granting Site Approval to the Material
    Recovery/Transfer Facility (ISWDA—XL)”.
    (C.
    1612-1625.)
    The
    council was advised that the statutory deadline for final action
    on the application was March 15,
    1992.
    (C.
    1626—1627.)
    One
    council member, Gary Shae,
    read a letter stating that he had
    decided to abstain because of an ex parte communication which had
    such an influence on him that he was unable to ignore it and make
    a decision based on the record.
    (C.
    1628.)
    The vote on the
    proposed ordinance was one vote “yes”, two votes
    “no”,
    and six
    abstentions.
    (C.
    1634-1635.)
    The city council’s rules of order
    The record of the local proceedings will be denoted by
    “C.”, references to the transcripts of the
    June
    15,
    1992
    Board
    hearing will be indicated by “Tr.”,
    and references to the
    exhibits introduced at that Board hearing will be denoted by
    “Pet. Exh.”.
    0 I35-030L~

    3
    require that all ordinances be passed by affirmative votes of no
    less than five members.
    (Pet.
    Exh.
    2,
    §2.64(c).)
    The mayor,
    Dannel McCollum, declared
    a temporary loss of quorum, based on
    the six abstentions.
    (C.
    1635.)
    Pursuant to the council’s rules
    of order,
    a temporary lack of quorum results in postponement of
    the matter under consideration until the next regular meeting.
    (Pet.Exh.
    2,
    S 2.64(j).)
    The next meeting was scheduled for
    March 17,
    1992,
    two days after the March
    15 decision deadline.
    A
    motion to reconsider the vote failed, with four “yes” votes,
    four
    “no” votes,
    and one abstention.
    (C.
    1638-1640.)
    On March 16,
    1992,
    counsel for ISWDA and XL advised Champaign that the
    applicants considered the application to be approved as of March
    15,
    1992 “as a result of the City of Champaign’s lack of taking
    final action within the 180 days allowed by Ill.Rev.Stat. ch.
    111½, par.
    1039.2(e).”
    (C.
    1608.)
    Petitioners filed the instant
    appeal on April
    15,
    1992.
    STATUTORY
    FRAMEWORK
    At
    the
    local
    level,
    the
    siting
    process
    is
    governed
    by
    Section 39.2 of the Act.
    Section
    39.2(a) provides that local
    authorities are to consider as many as nine criteria when
    reviewing an application for siting approval.
    These statutory
    criteria are the only issues which can be considered when ruling
    on an application for siting approval.
    Only if the local body
    finds that all applicable criteria have been met by the applicant
    can siting approval be granted.
    The local decisionmaker must
    make its decision within 180 days.
    Section 39.2(e)
    states in
    part:
    If
    there
    is
    no
    final
    action
    by
    the
    county
    board
    or
    governing body of the municipality within 180 days
    after the filing of the request for site approval the
    applicant may deem the request approved.
    (Ill.Rev.Stat.1991,
    ch.
    111½,
    par.
    1039.2(e).)
    When reviewing a local decision on the criteria,
    this Board
    must determine whether the local decision is against the manifest
    weight of the evidence.
    (McLean County Disposal v. County of
    McLean
    (4th Dist.
    1991),
    207 Ill.App.3d 352,
    566
    N.’E.2d 26.)
    Additionally,
    the Board must review the areas of jurisdiction and
    fundamental fairness.
    Section
    40’.l of the Act requires the Board
    to review the procedures used at the local level to determine
    whether those procedures were fundamentally fair.
    (E & E
    Hauling,
    Inc.
    v. Pollution Control Board
    (2d Dist.
    1983),
    116
    I1l.App.3d 586,
    451 N.E.2d 555,
    562, aff’d
    in part
    (1985)
    107
    Ill.2d
    33, 481 N.E.2d
    664.)
    0135-0305

    4
    DISCUSSION
    Compliance with Local Siting Ordinance
    Petitioners
    first
    contend
    that
    Champaign
    improperly
    accepted
    and
    filed
    the
    siting
    application.
    Petitioners point to
    Champaign’s ordinance establishing the procedural framework for
    siting proceedings in the city.
    Among other requirements, that
    ordinance requires that an application for siting approval
    include a statement that the applicant has presented the proposed
    site to Champaign County “for a determination of compliance with
    the Champaign County Solid Waste Management Plan,
    if such plan
    has been adopted..”
    (Pet.
    Exh.
    1,
    §2(C) (13).)
    Petitioners note
    that the instant application contended that Champaign
    County
    had
    delegated the required determination to ISWDA.
    Petitioners filed
    a motion to strike the application.
    That motion was denied.
    Petitioners now argue that acceptance of the application was
    improper, that since ISWDA is one of the applicants for siting
    approval
    it can hardly summarily conclude that it had been
    delegated the authority to make the determination, and that the
    motion to strike the application should have been granted.
    In response, ISWDA and XL maintain that Champaign County has
    indeed delegated to ISWDA the power to implement the county’s
    solid waste management plan, including determining whether a
    particular siting application complies with that plan.
    Additionally, ISWDA and XL contend that petitioners have not
    alleged any violation of the Act which would raise a
    jurisdictional issue, and have not shown any prejudice which
    would show a violation of fundamental fairness.
    ISWDA and XL
    argue that the motion to strike was properly denied.
    This Board has previously held that we are without statutory
    authority to compel enforcement of a local ordinance, and that
    review of the sufficiency of an application is limited to
    jurisdictional issues-—whether the application met the
    requirements of Section 39.2(a)
    of the Act.
    (Citizens for
    Controlled Landfills v. Laidlaw Waste Systems
    (September 26,
    1991), PCB 91—89 and 91—90
    (cons.), slip op.
    at 5—6; ~
    Gallatin
    National
    Co.
    v.
    Fulton County Board
    (June
    15,
    1992), PCB91—256,
    slip op.
    at 17.)
    Of course, ‘where a petitioner contends that an
    alleged failure to comply with
    a. local ordinance rendered a
    proceeding fundamentally unfair, the Board will review the
    alleged failure on that basis.
    In this case, petitioners admit
    that they do not contend that this
    is a jurisdictional issue.
    (Reply Br. at 3.)
    Instead, they state that, although they do not
    believe that any showing of prejudice is necessary,
    such
    prejudice is evident in this case.
    Petitioners state that the
    absence of Champaign County’s imprimatur is a factor upon which
    petitioners have relied in opposing the application.
    Petitioners
    state that
    if nothing else,
    they have been misled.
    0135-0306

    5
    Assuming that petitioners’ contention raises a fundamental
    fairness issue, the Board finds that petitioners have failed to
    demonstrate any prejudice.
    Section 39.2(a)
    clearly requires that
    the local decisionmaker determine whether an application complies
    with any applicable solid waste management plan.
    That duty
    cannot be delegated to any other decisionmaker.
    In other words,
    regardless of whether ISWDA or Champaign County has the authority
    to make the statement required by the local ordinance,
    the
    Champaign City
    Council was still obligated to make the final
    determination as to compliance.
    Petitioners clearly could have
    presented proof that the application did not comply with the
    plan, no matter what the county might have indicated.
    Petitioners’
    contention that they were “misled” does not
    demonstrate prejudice
    from
    any
    failure
    to
    obtain
    the
    statement
    required by the local ordinance.
    The Board finds no violation of
    fundamental fairness.
    (~gGallatin National
    (June 15,
    1992),
    PCB 91—256,
    slip op. at
    17.)
    Final Action
    Petitioners
    next
    argue
    that,
    considering
    all
    actions
    by
    the
    city
    council
    in
    combination, the city council took “final action”
    on
    the
    application in a timely fashion, such that the request for
    siting
    approval
    should
    not
    be
    deemed
    approved
    pursuant
    to
    Sect•ion
    39.2(e).
    Petitioners
    cite
    McHenry
    County
    Landfill
    v
    Illinois
    Environmental
    Protection
    Agency
    (2d
    Dist.
    1987),
    154 Ill.App.3d
    89,
    506
    N.E.2d
    372,
    where
    the
    appellate
    court
    stated
    that
    the
    “final
    action”
    which a local decisionmaker must take within the
    statutory
    deadline
    “need only be sufficiently final to justify an
    appeal
    to
    the
    (Board.
    (McHenry
    County
    Landfill,
    506
    N.E.2d at
    378.)
    Petitioners also cite a concurring opinion
    in Guerrettaz
    v.
    Jasper County
    (January 21,
    1988), PCB 87—76, where two Board
    members addressed the issue of “final action”
    in the context of a
    tie vote.
    Petitioners argue that the city council’s action in
    this
    case
    includes
    all
    of
    the
    elements
    of
    “final
    action”
    identified
    in
    McHenry
    County
    Landfill and Guerrettaz.
    Petitioners maintain that:
    1)
    all of the council’s actions
    through March
    3,
    1992 were within the statutory deadline;
    2)
    the
    vote on the original motion to approve siting and the vote on the
    motion for reconsideration concluded Champaign’s adjudicative
    process such that an appeal would not be disruptive;
    and 3)
    legal
    consequences could and did result from the March
    3 vote,
    in that
    the application failed to command a majority.
    Thus,
    petitioners
    allege that the applicants failed to satisfy their burden of
    proof
    so that the application was denied.
    Petitioners contend
    that if the application is
    deemed approved, the facility would be
    sited without an affirmative vote by the majority of the city
    council members.
    Petitioners allege that such a result is
    unconscionable.
    In response,
    ISWDA and XL argue that it is clear that the
    city council did not take final action prior to the expiration of
    0135-0307

    6
    the statutory decision period.
    ISWDA and XL contend that none of
    the cases cited by petitioners are supportive of their argument
    that
    final
    action
    was
    taken,
    since
    none
    of
    the
    cases
    involve
    a
    situation where the vote on whether to approve an application was
    continued to a date beyond the 180 day limit.
    ISWDA and XL
    maintain that the city council’s vote on the ordinance to approve
    siting was really a “non—vote”,
    since the abstentions resulted in
    a loss of quorum.
    ISWDA and XL argue that this “non—vote” and
    the subsequent denial of the motion for reconsideration were by
    their very nature not final actions,
    since by council rule,
    the
    “non—vote” continued the action to the next regular council
    meeting.
    ISWDA and XL assert that the city council’s actions on
    March
    3 did not conclude the adjudicative process such that an
    appeal would not be disruptive, because Champaign had up to and
    including March 14 to hold a special meeting and take final
    action on the application.
    ISWDA and XL further contend that the
    only legal consequence that resulted from the city council’s
    March
    3 actions was that action on the siting decision was
    continued to March
    17.
    ISWDA and XL maintain that the facility
    was neither approved nor disapproved on March
    3,
    and that there
    was no tie vote that could be interpreted as final action under
    the dicta of the Guerrettaz concurring opinion.
    ISWDA and XL
    state that the Board must recognize and honor the plain language
    of Section 39.2(e), recognize that the city council did not take
    final action within the 180 day deadline,
    and hold that the
    siting application has been approved.
    Champaign also argues that the city council’s March
    3
    actions did not conclude the adjudicative process,
    since the
    direct effect of the vote on the motion to approve the
    application was to place the item on a subsequent council agenda.
    Champaign further contends .that the legal consequences of the
    March
    3 actions resulted from the expiration of the 180 days,
    and
    not from the actions themselves.
    Finally, Champaign notes that
    the statute does not make siting automatic only if there is ~
    action by the local decisionmaker.
    Rather, the application is
    deemed approved if there
    is no final action.
    Champaign states
    that the city council took action on this application, but that
    it did not take “final action” within the statutory period.
    After a review of the statute, the record, and the arguments
    of the parties, the Board finds that Champaign did not take final
    action within the statutory 180 day decision period.
    As ISWDA
    and XL point out, McHenry County Landfill involved a case where
    the application was originally denied by the county, and after
    appeal to this Board,
    was remanded back to the county to correct
    an error.
    Thus,
    the applicant argued that the decision had not
    been’ made within the statutory time period
    (then 120 days).
    The
    appellate court held that the initial county decision constituted
    the final action required by Section 39.2(e).
    The Guerrettaz
    concurring opinion cited by petitioners
    is dicta, since that case
    was actually decided on the grounds that the required notice of
    0 135-0308

    7
    the filing of the application was deficient.
    The majority
    opinion
    never
    discussed
    the
    question
    of
    “final
    action”
    or
    the
    effect
    of
    the
    tie
    vote
    in
    that
    case.
    (Guerrettaz
    v.
    Jasper
    County (January 21,
    1988),
    PCB
    87-76.)
    In
    fact,
    none
    of
    the
    cases discussed by petitioners resolve the situation presented by
    this
    case.
    Even assuming that this Board should apply the “three step”
    analysis advanced by petitioners, the Board finds that the
    actions taken by Champaign do not constitute “final action.”
    The
    March
    3 action was taken within the statutory decision period.
    However, the Board rejects petitioners’ claims that the vote on
    the motion to approve the application and the vote on the motion
    for reconsideration concluded Champaign’s adjudicative process
    such that an appeal would not be disruptive.
    Under the city
    council rules,
    the vote on the motion to approve the application
    automatically continued the item to the next regular council
    meeting.
    Additionally, Champaign could have scheduled a special
    meeting to consider ‘the matter at any time up to March 15.
    Given
    these two facts,
    it seems clear that the March
    3 votes cannot be
    construed to have concluded the city council’s adjudicative
    process.
    Likewise, the March
    3 votes did not have legal
    consequence, except to place the matter on the agenda for the
    March
    17 meeting.
    As Champaign notes,
    it is the expiration of
    the 180 day deadline which had legal effect, not the votes
    themselves.
    The Board simply cannot see how a series of actions,
    none of which was conclusive in itself, can result in “final
    action” on the application.
    Section 39.2(e)
    clearly states that
    if
    a
    local decisionmaker
    does
    not
    take
    final
    action
    within
    180
    days,
    “the
    applicant
    may
    deem the request approved.”
    (Ill.Rev.Stat.
    1991,
    ch.
    111½, par.
    1039.2(e).)
    Therefore,
    the Board rejects petitioners’ claim that
    the application was denied because the application failed to
    command
    a
    majority
    vote.
    The
    statutory
    language
    also
    repudiates
    petitioners’
    argument
    that
    an
    approval
    without
    an
    affirmative
    vote
    by
    a
    majority of council members would be unconscionable.
    Section
    39.2
    gives
    local
    governments
    the
    power
    and
    the
    responsibility
    to
    rule
    upon
    an application for siting approval.
    The statute clearly contemplates a situation,
    such as this,
    where
    the local decisionmaker fails to take final action within the
    statutory
    deadline.
    The
    remedy
    provided
    by
    the
    legislature
    is
    that the application is deemed approved.
    This case fits the
    statutory scheme perfectly:
    Champaign failed to take final
    action within 180 days, and therefore the application for siting
    approval is deemed approved.
    The Board notes that petitioners argue that. if the
    application is deemed approved, petitioners have been denied
    fundamental fairness.
    Petitioners contend that:
    1)
    they were
    denied a decision based on the weight of the ‘evidence and, the
    relevant
    criteria,
    and
    were
    not
    given a statement of reasons for
    0 135-0309

    8
    the
    decision;
    2)
    the
    provision
    allowing for “deemed approved” was
    manipulated in a fashion not intended by the legislature,
    because
    the mayor “engineered” the abstentions when it was clear that the
    application would be rejected; and
    3) approval is being claimed
    for an applicant and a facility which no longer exist.
    None of
    these arguments, however,
    leads to a conclusion that the
    procedures used by Champaign were not fundamentally fair.
    Petitioners’
    first claim,
    that they were denied a decision
    based on the criteria and a statement of reasons for the
    decision, once again ignores the statutory provisions of Section
    39.2(e).
    Quite simply,
    the statute does not provide for these
    protections ma
    situation, such as this,
    where the local
    decisionmaker fails to take final action within 180 days.
    Instead, as discussed above, the application is deemed to be
    approved.
    The second claim, that the abstentions were improperly
    “engineered”, ignores a long line of case law that one cannot
    invade the mind of the decisionmaker.
    (Land and Lakes Co.
    v.
    Village of Romeoville
    (June
    4,
    1992), PCB 92—25, slip op.
    at 4;
    Dirnagglo v. Solid Waste Agency of Northern Illinois
    (January 11,
    1990), PCB 89-138, slip op.
    at
    5: City of Rockford’ v. Winnebago
    County (November 19,
    1987), PCB 87—92,
    slip op. at
    9,
    aff’d
    (2d
    Dist.
    1989)
    186 Ill.App.3d 303,
    542 N.E.2d 423.)
    The extensive
    discussion of conversations between the mayor and the council
    members before the March
    3 meeting is irrelevant.
    The inquiry is
    whether there was final action,
    not whether some council members
    may have been encouraged by another voting member of the council
    to vote
    a particular way.2
    The Board points out that petitioners
    do not claim that the abstentions were based on improper ex parte
    contacts from those outside the decisionmaking body.
    Finally,
    the argument that approval is being improperly claimed for an
    applicant
    and
    facility
    which
    no
    longer
    exist
    does
    not raise a
    fundamental fairness issue.
    As stated above, the Board is to
    review the fundamental fairness of the procedures used by the
    city council.
    Nothing the city council did,
    or did not do,
    relates to any subsequent problems between the applicants.
    In sum, the Board finds that Champaign failed to take final
    action on the application within 180 days of the filing of the
    2
    The Board specifically rejects petitioners’ statements
    that “the reasonable inference from the objective facts is that
    the 180—day provision was manipulated by the use of abstentions”,
    and “if
    the council members abstained for some other legitimate
    reason, then it was incumbent upon the respondents to adduce
    those reasons in order to rebut petitioners’
    case.”
    (Reply Br.
    at 9.)
    As stated above, one cannot invade the mind of the
    decisioninaker.
    Except for the limited situations
    ,
    such as ex
    parte contacts,
    a council member’s reasons for his or her vote
    are irrelevant.
    0135-0310

    9
    request.
    Therefore, pursuant to Section 39.2(e)
    of the Act, the
    application is deemed approved.
    Constitutional Claims
    Petitioners next argue that the statutory provisions
    providing for “deemed approved”,
    as applied to petitioners, deny
    them due process of law and equal protection of the law,
    in
    violation of the federal and state constitutions.
    Petitioners
    note a series of appellate court decisions holding that
    constitutional guarantees of due process do not apply to
    participants in site approval proceedings, but state that those
    conclusions are “arguable.”
    In any event, petitioners contend
    that
    they
    stand
    in
    a
    markedly
    different
    position.
    Petitioners
    note
    that
    existing
    flow
    control ordinances would require them to
    use
    and
    pay
    for
    the
    proposed facility.
    Thus,
    petitioners contend
    that
    they
    have
    a
    property interest for due process purposes.
    Illinois
    case
    law
    is
    quite
    clear
    that
    .objectors
    to
    a
    proposed
    facility
    do
    not
    have
    a
    constitutionally protected
    interest
    in
    the
    continued non—existence of such a facility on
    another’s
    property,
    and
    that
    the
    grant
    of
    site
    approval
    does
    not
    trigger
    the
    application
    of
    due
    process
    guarantees.
    (E
    &
    E
    Hauling,
    Inc.
    v.
    Pollution
    Control
    Board
    (2d
    Dist,.
    1983),
    116
    Ill.App.3d
    586,
    451
    N.E.2d
    555,
    563—564,
    aff’d
    (1985),
    107
    Ill.2d
    ‘33,
    481
    N.E.2d
    664;
    Fairview
    Area
    Citizens
    Taskforce
    v.
    Pollution
    Control
    Board
    (3d
    Dist.
    1990),
    198
    Ill.App.3d
    541,
    555
    N.E.2d
    1178,
    1180;
    Tate
    v.
    Pollution
    Control
    Board
    (4th
    Dist.
    1989),
    188
    Ill.App.3d
    994,
    544
    M.E.2d
    1176,
    1193.)
    Petitioners’ claim that
    these
    decisions
    are
    “arguable” does not “~onvincethe Board to act
    differently
    in
    this
    case.
    As
    to
    petitioners’ contention that they have a property
    interest
    for
    due
    process
    purposes,
    the
    Board
    points
    out
    that
    it
    is
    not
    the
    siting
    decision
    which
    arguably affects any property
    interest,
    but
    the
    local flow control ordinances.
    As ISWDA and XL
    point
    out,
    flow
    control
    is not involved in siting decisions under
    Section
    39.2,
    and
    siting
    approval
    of
    the
    material
    recovery/transfer
    facility
    does
    not
    require
    that
    petitioners use
    the facility.
    The flow control ordinances are separate and
    distinct
    from
    the
    local
    site
    approval
    process,
    and
    ‘this
    Board
    cannot review those local flow control ordinances.
    Finally, the
    Board rejects petitioners’ claim that Section 39.2 creates two
    classifications of objectors in local site approval proceedings
    (based upon the diligence or lack thereof of the local
    decisionmaker),
    such
    that the statute violates the equal
    protection
    clause.
    Criteria
    and
    Manifest
    Weight
    Petitioners state that any review of the evidence in this
    case,
    as
    it
    applies
    to
    the
    nine
    criteria
    of
    Section
    39.2(a),
    0135-0311

    10
    should use a weight of the evidence standard.
    Petitioners claim,
    however, that approval of the application cannot even survive
    scrutiny using a “manifest weight” standard.
    ISWDA and XL cite
    the Board’s decision in Board
    of
    Trustees
    of
    Casner
    Township
    v.
    County of Jefferson (January 10,
    1985 and April
    4,
    1985), PCB 84—
    175
    and
    84—176
    (Cons.)
    (Casner
    Township),
    and
    contend
    that
    “approval of the applicable criteria” was not against the
    manifest weight of the evidence.
    In
    Casner
    Township,
    the
    Board
    was
    presented
    with
    the
    first
    instance
    where
    a
    local
    decisionmaker
    failed
    to
    reach
    a
    decision
    on
    a
    siting
    application
    within
    the
    statutory
    decision
    period
    (then
    120
    days),
    so
    that
    the
    application
    was
    deemed
    approved
    by
    operation
    of
    law.
    The
    Board
    was
    then
    faced
    with
    the
    question
    of
    whether
    the
    Board
    has
    jurisdiction
    to
    hear
    an
    appeal from a
    “deemed
    approved”
    result.
    After
    briefing on the issue, the Board
    found
    that
    it
    does
    have
    jurisdiction to hear such appeals.
    In
    its order deciding that issue, the Board stated:
    The
    county
    (board
    is deemed to have approved the
    application by operation of law and the applicant
    should find himself in the same position he would have
    been had the (county
    (board
    approved the request by
    written decision.
    Specifically, the same presumptions
    and burdens of proof apply here and the Board will
    review the record using the manifest weight standard
    articulated in earlier (siting
    cases.
    (Casner
    Township (January 10,
    1985),
    PCB 84—175 and 84—176
    (Cons.),
    slip
    op.
    at
    8.)
    However,
    when
    making
    the
    final
    decision
    in
    the
    case,
    the
    Board
    held that procedural irregularities at the local hearing rendered
    the proceedings fundamentally unfair, and remanded the case to
    the local decisionmaker.
    (Casner Township,
    (April
    4,
    1985), PCB
    84-175 and 84-176. (Cons.).)
    Thus, the Board never actually
    reviewed the record.
    After further consideration, the Board finds that we erred
    in determining that we should conduct a review of the record
    where
    a siting decision has been deemed approved.
    The statute
    provides that an application
    is automatically deemed approved, by
    operation of law, when a local decisionmaker fails to reach a
    decision within the statutory timeframe.
    Therefore, by
    definition,
    there is no local decision on the criteria for this
    Board to review.
    Section 40.1 and the accompanying case law are
    clear that this Board’s function is to review the local decision,
    not to make an initial determination as to whether the applicable
    criteria of Section 39.2(a) have been met.
    It is impossible to
    apply a ‘manifest weight of
    the’ evidence review to a non—existent
    decision.
    Thus,
    the Board overrules Casner Township, to the
    extent that that decision states that in a deemed approved
    situation this Board will review the record for compliance with
    ‘0135-0312

    11
    the applicable criteria.
    The Board specifically reaffirms its
    findings in Casner Township that we’ have jurisdiction to hear
    appeals from a “deemed approved” result.
    The Board can,
    and’
    must,
    review
    the
    areas
    of
    jurisdiction
    and
    fundamental
    fairness
    in such “deemed approved” cases.
    However, the Board cannot
    review a non—existent decision on the criteria.
    This opinion constitutes the Board’s findings of fact and
    conclusions of law.
    ORDER
    The Board finds that the City of Champaign failed to take
    final action on the September 16,
    1991 application for site
    approval filed by the Intergovernmental Solid Waste Disposal
    Association and XL Disposal within 180 days of the filing of that
    application.
    Pursuant to Section 39.2(e)
    of the Act, the
    application is deemed approved.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act
    (Il1.Rev.Stat.
    1991,
    ch.
    111½
    ,
    par.
    1041) provides for the
    appeal of final Board orders.
    The Rules of the Supreme Court of
    Illinois establish filing requirements.
    (But see also 35
    Ill.Adm.Code 101.246 “Motions for Reconsideration” and Castenada
    v.
    Illinois Human Rights Commission
    (1989),
    132 Ill.2d 304,
    547
    N.E.2d 437.)
    B.
    Forcade concurred, and J. Marlin abstained.
    I,
    Dorothy N. Gunn,
    Clerk
    ‘of the Illinois Pollution Control
    Board, hereby certi~ythat the abov
    opinion and order was
    adopted on the /i~
    day of
    ,
    1992,
    by a vote
    of
    4-’~,.
    ~
    Dorothy
    M.
    4’unn,
    Clerk
    Illinois
    P~lution
    Control
    Board
    0135-0313

    Back to top