ILLINOIS POLLUTION CONTROL BOARD
    August 13,
    1992
    GALESBURG COTTAGE HOSPITAL,
    )
    )
    Petitioner,
    v.
    )
    PCB 92—62
    )
    (Underground Storage
    ILLINOIS ENVIRONMENTAL
    )
    Tank Fund)
    PROTECTION AGENCY,
    )
    Respondent.
    STEPHEN
    F. HEDINGER of MOHAN,
    ALEWET, PRILLAMAN
    & ADANI APPEARED
    ON BEHALF OF PETITIONER.
    OPINION AND ORDER OF THE BOARD
    (by 3. Theodore Meyer):
    This matter
    is before the Board on a petition for review
    filed April 27,
    1992 by petitioner Galesburg Cottage Hospital
    (Cottage Hospital) pursuant to Section 22.18b(g)
    of the
    Environmental Protection Act
    (Act).
    (Ill.Rev.Stat.1991,
    ch.
    111½, par. 1022.18b(g).)
    Cottage Hospital seeks review of the
    Illinois Environmental Protection Agency’s
    (Agency) March 23,
    1992 partial denial of reimbursement from the Underground Storage
    Tank
    (UST)
    Fund.
    A hearing was held on June 29,
    1992 in
    Galesburg,
    Illinois.
    No members of the public attended.
    The only issue in this case is whether costs incurred in
    association with a planned removal of USTs are “corrective
    action” costs and thus reimbursable by the Fund.
    BACKGROUND
    This case involves the removal of USTs at a service station
    located at Losey and Seminary
    Streets, Galesburg,
    Illinois.
    (R.
    at 35.)’
    Cottage Hospital purchased the site in 1979.
    From 1979
    until September 1990, the site was operated as a gasoline
    dispensing service station by Cottage Hospital’s tenant, Mr. Dale
    Bolin.
    (R. at 31.)
    On April 27,
    1990,
    and again on May 14,
    1990, Cottage Hospital’s contractor,
    Illinois Oil Marketing
    Equipment,
    Inc., tested the gasoline lines at the facility.
    The
    line dispensing premium gasoline would not hold pressure, and
    thus failed the tightness test.
    (R. at 75,
    81.)
    The operator of
    1
    “R.” denotes citation to the Agency record, and “Stip.”
    indicates citation to a stipulation entered by the parties at
    hearing.
    0135-0319

    2
    the station, Mr. Bolin, was directed to immediately stop
    dispensing premhun fuel.
    The trustees of Cottage Hospital
    subsequently decided to cease leasing the property as a service
    station and have the tanks removed.
    Mr.
    Bolin was notified of
    this decision on June
    1,
    1990.
    (R.
    at 31.)
    On August
    8,
    1990,
    the Office of the State Fire Marshal
    (OSFM)
    received Cottage Hospital’s application for a permit to
    remove the three tanks at the facility.
    (R.
    at 1.)
    OSFM issued
    that permit for removal of the USTs on August 20,
    1990.
    (R. at
    3.)
    The tanks were removed in September 1990.2
    During the
    course of the removal,
    it was discovered that there had been a
    release of petroleum.
    (Stip.
    at 5.)
    Cottage Hospital notified
    the Illinois Emergency Services and Disaster Agency
    (ESDA)
    of the
    release on September 20,
    1990.
    (P. at 4—5.)
    Cottage Hospital
    subsequently performed remedial activities at the site.
    On July
    31,
    1991,
    the Agency notified Cottage Hospital that no further
    remediation was necessary.
    (R.
    at 30.)
    Cottage Hospital filed its application for reimbursement
    with the Agency on September
    30,
    1991.
    (R. at 31-56.)
    The
    invoices submitted in support of the application covered the
    period from April 26,
    1990 to April
    4,
    1991, and the total amount
    requested was $36,779.07.
    (R. at 146.)
    On March 23,
    1992,
    the
    Agency issued its decision, finding that, after deducting the
    applicable $15,000 deductible,
    $10,539.52 was reimbursable.
    The
    Agency listed three separate amounts for which reimbursement was
    denied.
    (P. at 146—148.)
    Cottage Hospital filed its petition
    for review with the Board on April
    27,
    1992.
    DISCUSSION
    In its petition for review, Cottage Hospital challenged all
    three items for which the Agency denied reimbursement:
    $3,069.98
    for charges incurred prior to notification of ESDA
    (item 1);
    $6,452.20 for tank removal costs
    (item 2); and $1,717.37 for an
    adjustment in handling charges
    (item 3).
    (R.
    at 148.)
    However,
    the stipulation entered by the parties at hearing states that the
    parties have resolved the disputes as to items
    1 and 3.
    (Stip.
    at
    1-2.)
    Therefore,
    the only issue remaining is the disputed
    tank removal costs in item
    2.
    2
    There is conflicting evidence as to the actual date of the
    removal of the tanks.
    The corrective action report states that
    the tanks were removed on September 11,
    1990
    (R. at 6), the
    stipulation states that Cottage Hospital’s witness would have
    testified that the tanks were removed on September 20,
    1990
    (Stip.
    at 5), and the application for reimbursement states that
    the tanks were removed on September 21 and 24,
    1990.
    (P. at 37,
    43, and 49.)
    0135-0320

    3
    The Agency denied reimbursement of $6,452.20 in tank removal
    costs,
    stating that the tanks were not removed in response to a
    release,
    and that therefore the associated costs are not
    corrective action costs.
    (P. at 148.)
    The Agency pointed to
    Section 22.18(e) (1) (C)
    of the Act, which states in part:
    Corrective action does not include removal of an underground
    storage tank if the tank was removed or permitted for
    removal by the Office of the State Fire Marshal prior to the
    owner or operator providing notice of a release of petroleum
    in accordance with applicable notice requirements.
    (Ill.Rev.Stat.
    1991,
    ch.
    111½, par. 1022.18(e)(1)(C).)
    Cottage Hospital argues that the Agency erred in applying
    this limitation on “corrective action” to this case.
    Cottage
    Hospital notes that this limitation, excluding tank removals
    where permitted prior to notification of a release, was added by
    P.A.
    87—323, effective September 6,
    1991.
    Cottage Hospital
    states that the tank removal
    in this case occurred on September
    20,
    1990,
    almost a full year before the effective date of the
    change in the definition of “corrective action.”
    Thus,
    Cottage
    Hospital contends that the amendment cannot be used to defeat
    reimbursement for the tank removal costs.
    Cottage Hospital recognizes that in determining
    reimbursibility,
    the law to be applied is the law in effect on
    the date of the filing of the application for reimbursement.
    (First Busev Trust
    & Investment Co.
    V.
    Illinois Environmental
    Protection Agency
    (February 27,
    1992),
    PCB 91—213; Pulitzer
    Community Newspapers
    v.
    Illinois Environmental Protection Agency
    (December
    20,
    1990),
    PCB 90-142.)
    Cottage Hospital does not
    dispute that only corrective action costs can be reimbursed,
    but
    contends that the Agency has erroneously applied a definition of
    “corrective action” which was not in effect until well after all
    corrective actions in this case were completed.
    Cottage Hospital
    maintains that this situation is like the situation in Pulitzer
    Community Newspapers, where the Agency similarly denied
    reimbursement on the basis of statutes and regulations which did
    not exist at the time the corrective action was undertaken.
    Cottage Hospital states that the Board explained in Pulitzer
    Community Newspapers that the statute in effect at the time of
    filing the application is applicable,
    but in determining whether
    those provisions were complied with,
    the statute in effect at the
    time the actions were undertaken is applicable.
    (Pulitzer
    Community Newspapers (February 28,
    1991), PCB 90-142.)
    Therefore, Cottage Hospital argues that only the costs of
    corrective action are reimbursable, and that in determining
    whether the actions undertaken in this case are corrective
    action, the law in effect at the time the actions were undertaken
    is determinative.
    The Agency argues that there are two reasons that the tank
    0135-0321

    4
    removal costs incurred by Cottage Hospital are not corrective
    action costs, and thus not reimbursable.
    First, the Agency
    contends that because Cottage Hospital made a business decision
    to remove the tanks, the tanks apparently would have been removed
    whether or not a release was subsequently discovered.
    Thus, the
    Agency asserts that the removal of the tanks was not “an action
    to stop, minimize, eliminate,
    or clean up a release of petroleum
    or its effects..”
    (Section.22.18(e)(1(C)
    of the Act),
    and was
    not therefore corrective action.
    Second, the Agency points to the amendment of the definition
    of “corrective action” in P.A. 87—323, effective September 6,
    1991, excluding tank removals if removed or permitted for removal
    by OSFM prior to notification of a release.
    The Agency argues
    that if this amendment applies to Cottage Hospital’s application
    for reimbursement, it is clear that the tank removal costs are
    not corrective action,
    since Cottage Hospital obtained its
    removal permit one month before any notification to ESDA of a
    release.
    The Agency cites this Board’s decision in First Busey
    Trust
    & Investment Co.
    v. Illinois Environmental Protection
    Agency
    (February 27,
    1992), PCB 91-213,
    for the proposition that
    the law to be applied is that which was in effect at the time the
    Agency received the applicant’s completed application.
    Thus,
    the
    Agency maintains that the tank removal costs are not corrective
    action, and therefore are not reimbursable.
    After
    a review of the record and the arguments of the
    parties, the Board reverses the Agency’s determination that
    $6,452.20 in tank removal costs are not reimbursable.
    Initially,
    the Board again rejects the Agency’s argument that the removal
    costs are not reimbursable because the tanks were removed as the
    result of a business decision, and thus are not corrective action
    costs.
    The Board has twice held that the fact that a petitioner
    had planned to remove tanks does not bar tank removal costs from
    being reimbursed as corrective action costs when those activities
    meet the statutory definition.
    (Miller v. Illinois Environmental
    Protection Agency
    (July 9,
    1992), PCB 92-49;
    Enterprise Leasing
    Co.
    v.
    Illinois Environmental Protection Agency (April
    9,
    1992
    and June 4,
    1992),
    PCB 91-174.)
    The proper inquiry in this case
    is whether the tank removal costs meet the definition of
    “corrective action.”
    Thus,
    the Board must determine whether P.A.
    87—323 applies to this case.
    The Board finds that the Agency’s reliance on First Busey to
    apply the P.A. 87-323 amendment to this case is misplaced.
    First
    Busey involved a change in eligibility requirements
    (a change in
    deductibles), not a statutory change which concerned prior
    activity.
    It is true that when determining eligibility for
    reimbursement, the applicable law to be applied
    is that which
    is
    in effect on the date of the filing of the application for
    reimbursement.
    (Cite First Busey, Campbell, Rockford Drop Forge,
    and change in definition of petroleum case(?))
    However, where a
    0135-0322

    5
    statutory amendment involves prior activity or a certain course
    of conduct, the law to be applied is the provisions in effect at
    the time that the course of conduct occurred.
    That is exactly
    what this Board did in Pulitzer Community Newspapers.
    Inc.
    v.
    Illinois Environmental Protection Agency (December 20,
    1990 and
    February 28,
    1991), PCB 90—142.
    Pulitzer Community Newspapers iflvolved an Agency denial of
    reimbursement because the costs were incurred prior to
    notification of ESDA that a release had occurred.
    The Board
    reversed the Agency’s decision, because neither the statute nor
    the regulation requiring notification of ESDA within 24 hours
    after the discovery of a release were in effect at the time the
    release was discovered.
    The Board concluded that it would have
    been impossible for Pulitzer to give notice to ESDA in accordance
    with the statute and the regulation,
    since those provisions did
    not become effective until approximately three months after the
    release.
    (Pulitzer Community Newspapers
    (December 20,
    1990),
    PCB
    90-142,
    slip op.
    at 4-5; Pulitzer Community.Newspapers
    (February
    28,
    1991),
    PCB 90—142,
    slip op.
    at 2.)
    The Board stated:
    The applicable criteria for determining Pulitzer’s
    eligibility fer reimbursement are those criteria set forth
    at Section 22.18b(d)(4)(D), which became effective July 28,
    1989 with the enactment of P.A.
    86—125,
    because these
    provisions were in effect at the time Pulitzer filed its
    application for reimbursement on November 21,
    1989.
    P.A.
    86-125 requires that an applicant satisfy certain criteria
    to be eligible for reimbursement.
    One of those criteria is
    that “(t)he owner or operator notir~edthe State of the
    release of petroleum in accordance with applicable
    requirements.”
    The Board focused on the date of discovery
    of the release for purposes of determining what notification
    duties applied to Pulitzer.
    (Pulitzer Community Newspapers
    (February 28,
    1991), PCB 90—142, slip op.
    at 2.)
    The facts of this case are directly analogous to the
    situation presented in Pulitzer Community Newspapers.
    Cottage
    Hospital obtained its permit to remove the tanks
    in August 1990,
    and actually removed those tanks in September 1990.
    ESDA was
    notified of the release on September 20,
    1990.
    All of these
    dates were long before the September 6,
    199.
    effective date of
    P.A.
    87-323, which added the provision that tank removal costs
    are not corrective action costs if the tank was removed or
    permitted for removal by OSFN prior to notification of the
    release.
    There was no way for Cottage Hospital to know that it
    must provide proper notification (to ESDA) before obtaining the
    OSFM permit.
    Applying P.A. 87-323 to Cottage Hospital’s
    application for reimbursement would illogically require Cottage
    Hospital to conform its conduct to requirements which were not
    effective until almost a year after the conduct was done.
    Thus,
    in order to determine whether the tank removal costs are
    0135-0323

    6
    reimbursable as corrective action costs, the Board must apply the
    definition of “corrective action” as it existed when the costs
    were incurred,
    i.e.
    in September l990.~
    That definition of “corrective action” stated:
    “Corrective action” means an action to stop, minimize,
    eliminate,
    or clean up a release of petroleum or its effects
    as may be. necessary or appropriate to protect human health
    and the environment.
    This includes, but is not limited to,
    release investigation, mitigation of fire and safety
    hazards, tank removal, soil remediation, hydrogeological
    investigations,
    free product removal, ground water
    remediation and monitoring, exposure assessments, the
    temporary or permanent relocation of residents and the
    provision of alternate water supplies.
    (Ill.Rev.Stat.
    1989,
    ch.
    111½,
    par. l022.18(e)(1)(C).)
    As the Board noted in Enterprise Leasing and in Miller,
    this
    definition presents a two—part test:
    Whether the costs are
    incurred as a result of action “to stop,
    minimize, eliminate,
    or
    clean up a release of petroleum”,
    and whether the costs are the
    result of activities such as tank removal.
    The Board finds that
    the tank removal costs incurred by Cottage Hospital
    meet both
    parts of the definition.
    Therefore,
    the $6,452.20
    in tank removal
    costs are reimbursable as corrective action costs.
    Finally,
    the Board notes that the Agency argues
    in its brief
    that the tank removal costs are not reimbursable
    because,
    assuming that the release was discovered at the time of the tank
    tightness tests, Cottage Hospital failed to notify ESDA within
    24 hours of the discovery of the release.
    However,
    this reason
    for denying reimbursement was not included in the Agency’s final
    decision.
    (R.
    at 146—148.)
    As the Board has previously held,
    the Agency
    is bound on review by the reasons given in its letter
    communicating its decision.
    The Agency cannot,
    at the Board
    level, raise new reasons for denying reimbursement.
    (Clinton
    County Oil Co.
    v.
    Illinois Environmental Protection Agency(March
    26,
    1992), PCB 91-163,
    slip op.
    at 3;see also Pultizer Community
    Newspapers
    (December 20,
    1990), PCB 90—142.)
    Therefore, the
    ~ The Board recognizes that in Miller
    v.
    Illinois
    Environmental Protection Agency
    (July 9,
    1992),
    PCB 92-49,
    it
    stated that the proper inquiry was whether the tank removal costs
    met the definition of “corrective action” as that definition
    existed when Miller’s application for reimbursement was filed.
    However, that case involved an Agency denial for reimbursement of
    costs because the tank removal was “planned”,
    not the application
    of the language of P.A. 87—323,
    since Miller’s application was
    filed before the effective date of P.A.
    87—323.
    01 35-832k

    7
    Board will not consider this argument.
    CONCLUSION
    In sum, the Board finds that $6,452.20 in tank removal costs
    are corrective action costs and are therefore reimbursable.
    In
    determining eligibility for reimbursement, the applicable law is
    that which is in effect on the date of the filing of the
    application for reimbursement.
    However, where a statutory
    amendment involves prior activity or a certain course of conduct,
    the law to be applied are the provisions in effect at the time
    that the course of conduct occurred.
    The Agency’s determination
    that the tank removal costs are not reimbursable is reversed.
    This opinion constitutes the Board’s findings of fact and
    conclusions of law.
    ORDER
    The Board hereby reverses the Agency’s March 23,
    1992
    determination that $6,452.20 in tank removal costs is not
    reimbursable.
    This case is remanded to the Agency for
    disbursement of the $6,452.20 amount, consistent with this
    opinion and order.
    This docket is closed.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act
    (Il1.Rev.Stat.
    1991,
    ch.
    111½, par.
    1041) provides for the appeal
    of final Board orders.
    The Rules of the Supreme Court of
    Illinois establish filing requirements.
    (But see also 35
    Ill.Adm.Code 101.246 “Motions for Reconsideration”, and Castenada
    v.
    Illinois Human Rights Commission
    (1989),.132 Ill.2d 304,
    547
    N.E.2d
    437.)
    P.
    Flemal and B.
    Forcade concurred,
    and J.
    C.
    Marlin
    dissented.
    I, Dorothy M.
    Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opinion and order was
    adopted on the
    /3—i.-
    day of
    _______________,
    1992, by a vote
    of
    ~
    ii
    ~
    ~t.
    /t~L~~’
    Dorothy M//Gunn,
    Clerk
    Il1inois~y’ollutionControl Board
    0135-0325

    Back to top