| - TABLE OF CONTENTS
- Specific Dates for Completion of Remedial Actions
- infiltration sources.
- The results indicate no dye was detected in the
- areas.
- Estimated total number of illegalconnections to date
- Estimated percentage of illegalconnections of survey to date 22
- D). The results indicate the following:
- C. Provide 30 day notice forresidents with identified
- November i, 1992
- enters the main 12 inch trunk line Observations
- observations will be recorded.
- of highly intensive rain fall, to determine
- observed, additional SSES activities and/or
- and reported ~ the Illinois Pollution Control
- Board, by September 15, 1993.
- the presence of the Superintendent of Public Works
- connectiOns must be demonstrated.
- Monthly tabulation of totalized flow from ~s
- Infiltration/Inflow assessment or,SSES activities
- will be re-implemented.
- B 62 S 8” 2/28/79 2:10 .074/16/79 1:35 .14 15,100
- 6/18/79 2:30 .10
- .284/16/79 3:10 .28
- 4/16/79
- B 15,100 5,085 10,015 197 Increas
- C 2,796 1,600 1,196 75 Increas
-
- of March through May. Flows are based upon the pump design
- TABLE 5
|
ILLINOIS POLLUTION CONTROL BOARD
January
7,
1993
RESIDENTS
OF
CEDARVILLE,
)
)
Complainant,
PCB 91—194
V.
)
(Enforcement)
)
VILLAGE OF CEDARVILLE,
)
)
Respondent.
ORDER
OF THE BOARD
(by B.
Forcade):
On
September
3,
1992,
the Board issued an interim opinion
and order in this matter.
The Board found that the Village of
Cedarville
(Cedarville) had violated 35 Ill. Adm. Code
306.102(a),
306.303 and 306.304.
The Board noted that Cedarville
had taken some measures in response to the sewer overflows and
had plans for additional actions.
However, the Board concluded
that a finding of violation combined with the potential health
risk resulting from future violations required that a more formal
program be mandatorily implemented.
The Board directed
Cedarville to develop a compliance plan to be submitted to the
Board by October 13,
1992.
The compliance plan was to detail the
steps necessary for Cedarville to aàhieve and maintain compliance
with Sections 306.102,
306.303 and 306.304.
The Board received a compliance plan from Cedarville on
October 14,
1992.
Because there was no indication that
Cedarville had sent of copy of the compliance plan to the
Illinois Environmental Protection Agency (Agency), the Board
forwarded
a
copy
of
the
compliance
plan
to
the
Agency
and
extended the time in which the complainants and the Agency could
comment on the compliance plan until November 20,
1992.
The
complainants did not file a response to the compliance plan.
The
Agency filed its response on November 19,
1992.
As part of the compliance plan, Cedarville reports that the
following activities have occurred in relation to the sanitary
sewer system:
1.
The village has surveyed and observed several manholes
in low lying areas.
Some manholes have been raised to
prevent storm water inflow from entering.
2.
Dye testing was conducted in September,
1992 at suspect
locations.
No dye was detected in the sanitary sewer
system downstream of th~observed areas.
3.
A door to door inspection was conducted for illegal
storm
water
connections.
0138-0227
2
4.
Smoke testing was conducted for the area contributing
to Key Manhole No.
19.
The compliance plan discusses the option of installing a
relief sewer to correct the overflow problem.
The village board
would rather expend funds to solve the source of the problem than
to spend the funds to alleviate the problem.
The village board
believes that the overflow conditions can be alleviated by
attacking the source of the excess inflow.
The proposed compliance plan submitted by Cedarville
involves follow-up of the testing and inspections already done on
the sewer system.
The plan also requires monitoring of the
manholes near Cedar Court for potential surcharging during heavy
rains for a six month period from December 15,
1992 through June
15,
1993.
If surcharging is observed, Cedarville will proceed
with additional SSES activities and/or consideration of a relief
sewer.
As part of the compliance plan,
all new construction will
be inspected to assure that there are no illegal connections.
Monthly tabulation of totalized flow from the sewage treatment
plant will be kept to compare over time.
If a comparison of the
flows indicates an increase in flow,
an inflow/infiltration
assessment will be performed and the appropriate means to correct
the problem will be pursued.
The Agency in its comment states that a program of locating
and eliminating the sources of infiltration and inflow is not
effective for solving the type of problem that exists in
Cedarville.
The Agency contends that when such programs are
instituted,
the sources of the infiltration and inflow are too
numerous to effectively eliminate and solve the problem.
In
support of its conclusion the Agency references a July 1980
Technical Report issued by the United States Environmental
Protection Agency
(USEPA) entitled Evaluation of
Infiltration/Inflow Program.1
The Agency believes that to solve
the problem Cedarville must provide a means of delivering sewage
out of Cedar Court.
The Agency recommends that Cedarville
construct a relief sewer or a pumping station to serve the area.
While the Agency’s comment raises a genuine concern on the
adequacy of the compliance plan, the Board does not find that the
concerns of the Agency warrant altering the compliance plan as
submitted by Cedarville.
Cedarville has already completed many
of the activities contained in the compliance plan.
The results
o~.the inflow/infiltration assessm~.t performed in 1979 showed
inflow/infiltration levels below the USEPA level which would have
required additional studies.
Cedarville realizes that the
addition of a relief sewer may be~necessary if the proposed
The Agency did not supply of copy of this report with its
comments and the Board has not obtained a copy of the report.
0138-0228:
3
actions do not reduce the excess flow in the sewer system.
The
Board has not been presented with sufficient factual information
to determine if the magnitude of the inflow/infiltration is such
that a relief sewer is required.
Cedarville has already made
some progress in reducing the number of illegal connections to
the sewer system.
There is no indication that additional sewer
ovèrflows have been experienced by the residents.
The last
reported sewer overflow occurred on August 19,
1990.
The Board accepts the compliance plan as submitted and
directs Cedarville to adhere to the provisions of the compliance
plan.
The Board directs Cedarville to continue to monitor its
progress in eliminating excess flow in the sewer system.
The
Board further instructs Cedarville to examine the possibility of
installing a relief sewer system or pumping station in the area
of Cedar Court if it becomes apparent that the inflow/
infiltration problem is too expansive to eliminate at the source.
The Board notes that the complainants have the right to
petition this Board for relief if Cedarville fails to follow the
compliance plan or overflow from the sewers reoccurs.
ORDER
1.
The Board hereby accepts the compliance plan submitted by
Cedarville.
A copy of the compliance plan is attached to
this order and incorporated by reference as though fully set
forth herein.
2.
Cedarville shall implement the provisions of the compliance
plan.
3.
Cedarville shall cease and desists from further violations
of 35
Ill. Adm. Code 306.102, 306.303 and 306.304.
4.
This docket is hereby closed.
IT IS SO ORDERED.
Section 41 of the Environmental Protection Act
(Ill.
Rev.Stat.
1991,
ch.
111 1/2, par 1041) provides for appeal of
final orders of the Board within 35 days.
The Rules of the
Supreme Court of Illinois establish filing requirements.
(But see
also 35 Ill.
Adm. Code 101.246, Motions for Reconsideration,
and
Castenada
V.
Illinois Human Rights Commission
(1989),
132
Ill. 2d
304, 547 N.E.2d 437.)
0l38-Q229
4
I, Dorothy N. Gunn,
Clerk of the Illinois. Pollution Control
Board, hereby certify that
e above order was adopted on the
_____________day of
,5~t~_iti~~
,
1993,
by a vote of
Dorothy N. ~nn,
Clerk
Illinois Pd)/lution Control Board
0138-0230
ILLINOIS POLLUTION CONTROL BOARD
RESIDENTS OF
CEDARVILLE,
)
)
Complainant,
)
VILLAGE
OF CEDARVILLE,
Respondent.
PCB
NO.
91-194
(Enforcement)
)
)
)
)
)
ft~
aCTI49921
1:11
9
L~
NOTICE
OF FiLiNG
TO:
(See attached
Service List)
Please
be advised
that
on October
13,
1992,
the attached
Village of Cedarville Sewer
System
Compliance
Plan
was filed
with
the
illinois
Pollution
Control
Board,
by
Federal
Express
mailing,
in
accordance
with
the
Interim
Opinion
and
Order of
the Board
dated
September
3,
1992.
Dated:
October
13,
1992
HINSHAW
&
CULBERTSON
220 East
State
Street
P.O.
Box
1389
Rockford,
IL
61105
(815) 963-8488
HARRISNOF/pjd
VILLAGE
OF CEDARVILLE, Respondent
BY
HINSHAW
&
CIJLBERTSON
PRiNTED
ON RECYCLABLE PAPER
0138 O23~
vs.
~ST~’7E
t~
HJJNC:S
Pn!
Iirno;~
£flNTROL
Bn~PJ!
SERVICE
LIST
Dorothy M.
Gunn, Clerk
Illinois Pollution
Control Board
Suite
11-500
100 West
Randolph Street
Chicago, IL
60601
Kenneth Anspach,
Esq.
200
West Adams Street, Suite
1700
Chicago,
IL
60606
John H.
Vogt,
Esq.
1002 State
Bank Center
Freeport, IL
61032
Mr.
Scott
Harris
130
Cedar Court
Cedarville,
IL
61013
Mr.
Robert
E. Stewart
Ms. Marlene
L. Stewart
115 Cedar Court
Cedarville,
IL
61013
Mr. Tim Hoefle
Ms. Cathy Hoefle
120
Cedar Court
Cedarville, IL
61013
Mr. Francis McAuiiffe
Ms.
Joyce McAuliffe
110 Cedar Court
Cedarville, IL
61013
Mr. Allen Schlueter
Ms.
Sandra Schlueter
140
Cedar Court
Cedarville, IL
61013
Mr. Robert
Crouse
Ms.
Sylvia Crouse
135
Cedar Court
Cedarville, IL
61013
Mr.
Larry
Weilman
Ms. Holly Weliman
125 Cedar Court
Cedarville, IL
61013
0138-0232
Mr.
Edward H.
Brackemyer
Ms.
Cathy Brackemyer
112 Cedar Court
Cedarvilte,
IL,
61013
Ms.
Karen
M.
Homer
100 Cedar Court
CedarvUle, IL
61013
Mr.
Larry
Lawson
Ms. Sandra Lawson
55
Cedar Street
Cedarville, IL
61013
01
3Th-0233
VILLAGE
OF
CEDARVILLE
SEWER
SYSTEM
COMPLIANCE
PLAN
ILLINOIS
POLLUTION
CONTROL
BOAR!)
PCB 91—194
October
13, 1992
0138~023.5
TABLE OF CONTENTS
HISTORICAL
INFILTRATION/INFLOW REPORTS
AND
DISCUSSION
SEWER
SYSTEM EVALUATION SURVEY
ACTIVITIES
CONSIDERATION OF RELIEF
SEWER
PROPOSED COMPLIANCE
PROGRAM
Evaluation of
the
Source
of. Sewer
Overflows
and
Assessment of Present State
of
the
Sewerage
System
Specific Steps to Eliminate
the
Identified Problems
Specific Dates for Completion of Remedial Actions
Long
Term Monitoring Methods
MTACJ*(ENTS
Attachment A
-
Infiltration/Inflow Assessment
Attachment B
—
Cedarville Sewer System Map
0138-0236
Infiltration/Inflow
Assessment
of
the Cedarvillo
SSVSX
System was conducted and
reported
as
part
~t
us
C.darVill
Facility Plan dated October
1,
1979.
Att*chment
A
pcSS*I~~
Section III
-
Infiltration/Inf~iovAssessment
as presented
1*
the
referenced
Facility
Plan.
£tta~aent
s
presents
~ithIbit
B from that report, ccaprtsing the
Cedarvill. sanitary
S~
System
and
shoving the
Key
Manholes
refarenoed In the
Infiltration/Inflow
Assessment.
The
results
of
that
assesaa.nt indicate that ?r~mkLIme
D (flow entering
Key
Manhole
Mo. 19 tram
the
out)
has
a
high percentage increase
inflow
during
both
infiltratios
6
inflow conditions, while Trunk Line C (flaW entering Z.y
Manhole
No. 19
from
the north)
has
a
hish Perc.ntaae
increase
during
inflow
conditions.
All
other
trunk
liii..
indicated increases, from 65 to 197 .peroent, with resulting
overall
system
estimated
increases
of six percent and .i~t
percent of tb. annual dry weather
flow
for
infiltratime
esS
inflow,
respectively.
The
conclusion
of
the
asgesament
was,
that
the total
system I/I
was
below
th*
USEPA
criteria,
such
that
a
Sower
System Evaluation
Survey
was
not
rquir.d..
The Cedarville Sanitary Sewer System was constructed in
1972, a relatively young
system
in relation to the age
or
many municipal
systems
which
era
now requiring major
infrastructure rehabilitation.
Furthermore,
the
system
La
constructed with
Armco
Truss Pipe, a composite pipe
1.
0138-0237
Consisting of
an ABS plastic honeycomb structur, tilled vi
lightweight concrete, which is installed
in
ten
foot
lengtI
vith solvent welded joint
couplings.
This piping
system
minimizes the
number
of
joint.
in
comparison with typical
clay sever pipe
systems.
Television
inspection
of
the.
system
conducted for the
Village
of C.darvilla ha. not
determined
any
obvious structural defects such
as
cracked
pipe,
separated
joints,
or
root
intrusion.
Thus,
the
sanitary
sewer
main piping
is
relatively
non-suspect
of
being
a major infiltration
source.
This
does
not preclude
the
individual
house
services
from
being
potential
infiltration sources.
Inflow
sources
into
the
system could
includi
such
things as the following:
1.
Manholes
in
low
lying
areas
or
ditches
which
could
become
su~a.rged.
2.
Direct
connections
from
storm
sewers or inlets.
3
Illegal private
connections
from
roof
drAin.,
foundation
drains,
and
storm water
cusp
pumps.
SEWER
SYSTEM
EVALUATION
SURVEY
ACTIVITIES
In
regard
to
th.
above
inflow
sources,
the
following
activities have occurred:
2.
•
The
Village
has surveyei and
observe4
.
.ev.ral
manholes
in low lying areas.
Th.s. t~ave
been
raised
to
prevent
storm
water inflow from
entering.
2.
0138-0238
2.
Table
1 presents a summary of
dye testing
conducted in September,
1992 at suspect
locations.
The results indicate no dye was detected in the
sanitary sewer system downstream of
the
observed
areas.
3.
The village personnel have conducted
door
to door
surveys
to
inspect
homes for illegal storm water
connections.
The
results of the survey completed
through October
7, 1992 are
as
follows:
Surveys completed
24~
Total homes to survey
312
Percent of surveys coapisted
Illegal connections found
34
Percent illegal connections of
completed surveys
13.0
Estimated number
of
illegal
connections
disconnected’ prior
to survey
20
Estimated total number of illegal
connections to date
Estimated percentage of illegal
connections of survey to date
22
Table
2 presents a
summary
of smoke testing
conducted
for the area contributing to
Key
Manhole
No.
19 (Trunk Line
D).
The results indicate the following:
1.
Two
homes
at
which
the
house
service
connections
indicate poor
joints
or
cracked
piping
allowing
smoke to emit from the ground.
3.
0138-0239
2.
The tour inch cast iron service entering Manhole
No.
25 should be grouted to eliminate seepage.
3.
Follow-up observations must be conducted at thre
homes to determine
the
cause
of smoke entering the
basement.
This
could’
be
from
dry
traps
in
the
plumbing
allowing smoke to pass
through,
or
from
illegal storm water connections.
CONSIDERATION
OF
RELIEF SEWER
The
Village
Board
understands
the
concept
of
a
relief
sewer to relieve surcharging conditions near
Cedar
Court.
However, this remedy would not solve the
source of the
problem, but ‘rather would expend
funds
to alleviate ‘the
resulting
condition.
The
Board
vouj.d
rather
expend
funds
to
solve the source of the problem, unless it is ‘determined
that the source
is
wide
spread
throughout
the
system
such
that
major ‘rehabilitation
or
replacement
of
sAnitary
sewer
mains would be required.
However, at this time this does
not appear to be the case.
The
results of
the activities
conducted to date have
shown
illegal storm
water
connections
to
be a
known
major
source.
The
results
of
disconnecting
these sources should
first be monitored to determine if this
will alleviate the
problem.
This
can be determined
throucth
a program to monito. flows md surcharging during various
x~infa11events.
It i. impossible to predict the effect of
disconnecting the illegal qonnections on possible future
surcharging at Cedar Court should another rainfall of the
4.
O138~o24Q
magnitude previousiy
~
~
backwater valves on service connections along Cedar Court
will provide protection in that event.
PROPOSED
COMPLIANCE
PROGRAII
I.
Evaluation of the Source of Sewer Overflows
and
Assessment of
Present
State of the
Sewerage
System
Dye testing,
sewer televising,
and
manhole survey.
have found no
méjor
sources of extraneous
infiltration/inflow.
Sack.
testing
has determined
several
possible
sources to be
checked
further.
The
door
to
door
survey
has
determined
a
number
of illegal
connections which in aggregate could greatly
increase
extraneous storm water flow into
the
system
II.
Specific Steps to Eliminate the Identified Problems,
and,
III.
Specific
Dates
for
Completion
of
Remedial
Actions
II. Remedial Action
III. Completion
Date
A.
Complete door-to-door survey
for illegal stormwater
October
31, 1992
:
B.
Follow-up observations to
determine
reason
for
smoke
entering basements of three
homes
‘
October 31, 1992
C.
Provide 30 day notice for
residents with identified
illegal storewater connections
to
have
corrections
made.
Also
provide
30
day
notice
to
residents
in
violation
of
backwater valve ordinance
November 1, 1992
‘
5.
0138-02~.i
II. Remedial Action
III. Completion ‘Date
D.
Grout
c.I.
service
entering
)~
No.
25.
Smoke
test
Trunk
Line
C.
November i,
1992
E.
Re-inspect
residences
which
received 30 day notices for
compliance.
December 15,
1992
IV.
Long Term Monitoring Methods
A.
Short term monitoring
for
potential surcharging
in
manholes
near
Cedar Court.
During
a
six
month
period
commencing
December
3.5,
1992
and
running
through June 15,
1993,
whenever
local
rainfall
in
excess
of
15
inches
in
24 hours is
forecast
or
appears
imminent, Village
personnel
will observe for
any
surcharge
conditions in Manhole No.
12
where
Cedar
Court
enters the main 12 inch trunk line
Observations
will be made at
four
home intervals until two
hours after cessation of
heavy
rain, and
observations will be recorded.
If
no
surcharge
is
observed,’
euture
observations
will
only
be
conducted
during
periods
of highly intensive rain fall, to determine
whether any surcharging
occurs.
If, surcharging is
observed, additional SSES activities and/or
~nsiderationof a relief sewer will be
‘und
~taken
and reported ~
the Illinois Pollution Control
Board, by September 15,
1993.
6.
01 38-02I~2
B.
Program
to
eliminate
new
sources
of
excess
infiltration/inflow
in
the
future.
New sources of excess iflfiltratjon/jflflOW
would most likely be created
from new building
construction where illegal storawater
connections
could be made.
This will
be policed by
having
all
new building permits require a
final
inspection in
the presence of the Superintendent of Public Works
and
the
‘liOensed plumber in
which
no illegal
connectiOns must be demonstrated.
C.
Program to detect
increases
of flow in
the
•evaqs
system due to rain, and
frequency
of
inspections
Monthly tabulation of totalized flow from ~s
sewage treatment
plant
will be kept to compare
flows over time.
In addition, daily
flows
on day.
when rainfall in excóss of 1.5 inches
is
r.ceiw.d
in 24 hours, will be
tabulated
for comparison
~
time.
These comparisons will
take
into account
any
known
increase in
dry
weather’ flows due to
increased population
served
or
new
commercial/industrial
sources
of
flow.
If comparisons
indicate an obvious
increase
in flows during rainfall or
snow melt,’ new
extraneous
sources ‘will be suspected, and
Infiltration/Inflow assessment or,SSES activities
will be re-implemented.
7.
0138-02143
TABLE
1
SUMMARY
OF DYE
TESTING
RESULTS
VILLAGE
OF
CEDARV1LLE,
ILLINOIS
SEPTEMBER
1992
Observation
‘
‘
Location
No Dye
No
Dye
Dyed nk
west & soitheast corners of
Washington
&‘MIll Streets.
Checked
MH-6.
Dyed inlet
e
aoithwest
corner of C~kRidge Drive
&
Mill Street
and inlet across from (~k
Ridge
Drive on
Mi
Street.
Chec’~d110-67.
No
Dye
‘
Dyed inlet
‘~th~
southeast
corner of Oak
& Mill
Streets.
Checked M0-67.
No
Dye
Dyed
inlet at U~
southwest
corner of Second
Street &
Mill
Street, mid bilets on both sides
of Mill Street
across
from
lift
Station
A. (1ic~krd
MR north of Lift
Station
AN.
0138
TABLE
2
SUMMARY
OF
SMOKE
TESTING
RESULTS
VILLAGE
OF
CEDARVILLE,
ILLINOIS
SEPTEMBER
1992
NO.
LOCATION
OBSERVATIONS
‘
1
•
30 Adams Street
Smoke came out
of qround around
sidewalk
&t
back
of
house.
2
•
50
Adams
Street
.
Smoke
cams
out
of ground west
side
of
concrete
patio
at back
of house.
3.
Lot
285 Walnut Street
Smoke cams
out
of
uncapped
cleanout east sid. of house.
4.
MM #25
Water
leaking in
around 4”C.l.
service
5.
45 Stephenson Street
Smoke
cue in basement.
6.
65 Stephenson Street
Dark brown
house
east
side
of
Lafayette
“~reet.Second house
~h of Washington
Smoke
cam.
in
basement.
Smoke
came out
of
chimney. B,...
like
there
is
smoke
in
basnt.
I:~WPffl.ES\rr~~Q3l27O&~
‘.~J
0138-02145
A7TAcRME~A
INFTLTRXI1ON/INPLOW ASSESSM~’r
(EXCERp’r~
FROM
CEDARvru~
FAcILiTY PLAN, OCTOBER
1, 1979’
0138-0246
III.
INFILTRATION/Ii4FLOW ASSESSMENT
Introduction
Under the current requirements of the Federal
Water po13utio
Control
Act,
construction
grants
for
treatment
works say
not be
awarded
unless
itis
established
that the wastewater
collection
system discharging into the treatment works
is not
subject t’
Nexcessivew
infiltration/inflow.
Sewer system inflow occurs when
systems
collecting storvatel
runoff are directly connected to the sewer
system.
Inflow
can
be
detected and estimated by
measuring
flows
at
key
points in the
sewer
system during rainfall, and calculating
any
increase in
flow
over
normal
dry
weather
flows.
Sewer system infiltration
occurs when soil conditions
and
groundwater levels are such that
they
enhance
the
conveyance
of
surface water seepage
and
groundwaters into
the system
through
poor joints
and
cracks in the seWer pipes
and
maitholes.
Normal
procedures
for
determining
the possible existence of excessive
infiltration
are
to
determine
wastéwater flowrates during
periods
when groundwater tables are high
and
soils
are
saturated but no
inflow producing
storm
event is present,
and
comparing them with
normal dry weather flows.
Determination of possible excessive infiltration/inflow in
the sanitary sewer system is required prior
to release of
Federal
grant funds
for construction of treatment plant improvements.
Sources of information used
in determining infiltration/
inflow
are treatment plant flow records,
water pufltpage.record5,
reports of
sewage backups
j
~Ose~e~~sor
streets, and field
flow measurements at key points in the system for various
climatological conditions.
Since there is no continuous flow recording equipment at
the
treatment
plant,
this
data
was
~
available
for
study
of
past
flow
patterns.
In
order
to
obtain information for this
study, elapsed
time
meters
on
a
lift
station
which serves
approximately
one
third of the village were utilized
to~gather
representative information of daily~flows
over a
3
month period.
Charts were ~ireparedto assist village personnel
in keeping
daily records.
Flow Measurements
Key manholes for flow measurements were selected from
available sewer system maps.
The key manholes selected divide
the total system into 5 major sub—systems in order to help
pinpoint any problem areas.
A field ‘inspection of these select
manholes
was
made
on February 28, 1979,
at
which
time ‘flow
measurements for average dry weather
conditions
were
collected.
The
numbers
of
the
key
manholes.
are as
shown
on
the
map in
Exhibit S of the Appendix.
The conditions of
manholes which
were entered were recorded.
Both depth of flow and weir
measure-
ments
were
taken.
These
results
are
su~narizedin Table 2.
On
April 16,
1979
a second set of flow
measurements
were taken for
high groundwater conditions.
These results are also su”~marized
in Table
2
Storm inflow flow xneasurem~nts
were
taken
on
June
18,
1979.
A storm front moved through the area beginning at 7:30 A.M.
continuing until 1:30
P.M. producing a steady rainfall for the
Dl 38-Q2148
TABLE
2
VILLAGE OF CEDARVILLE
INFILTRATION/INFLOW STUDY
FLOW
MEASUREMENTS
Depth
of
Weir
Line
MN
Dia.
Date
Time
Plow(Ft.)
RatCtCPD!
A
62 £
2/22/79
1:50
,05
3,750
4/16/79
1:15
.06
9,495
6/18/79
2:20
.06
8,100
B
62
S
8”
2/28/79
2:10
.07
4/16/79
1:35
.14
15,100
6/18/79
2:30
.10
C
19
N
8”
2/28/79
3:00
.03
1,600
4/16/79
2:20
.04
2,796
6/18/79
2:45
.03
12.075
D
19 £
8”
2/28/79
3:15
.05
3,360
4/16/79
2:00
.10
10.000
6/18/79
2:55
.10
*
12
E
12”
2/28/79
3:50
.10
10,000
4/16/79
2:35
.17
—
6/18/79
3:05
.14
28,495
E
4
N
8”
2/28/79
4:15
.08
1,500
4/16/79
2:55
.19
14,450
6/18/79
3:55
.20
13,990
1 a
12”
2/28/79
4:45
.28
4/16/79
3:10
.28
6/18/79
4:10
.32
61.500
Overflows Weir
No Measurement Taken
0138-0249
6.
duration, with a total rainfall accumulation of 0.5
inches.
Flow measurements were taken between 2:20 P.M.
and 4:10 P.M.
beginning at the upstream
key
manholes and continuing toward tt
treatment plant.
‘The results of these flow
measurements are
summarized in Table
2
Analysis of Flow Measurement Data
Tables 3 and
4
present
s~~aries
~fthe
infiltration and
inflow quantities indicated from the instantaneous flow measurei
where “instantaneousTM refers to non-continuous flow measurement.
Infiltration
-
Table
3 presents the measured instantaneous
infiltration for each of the trunk sewers.
The resulting total
infiltration flowrate is 37,546
gpd.
Trunk line D indicates a
436
increase over the measured dry weather flow, while all othe
lines increased by ‘less than
200.
TABLE
3
Instantaneous Infiltration into
Trunk
Sewers
4/16/79
Trunk
Wet Weather
Dry Weather
Instantaneous
Line
Flow
(gpd)
Flow
(gpd)
Infitration(gpd)
Remarks
A
9,495
3,750
5,745
153
Increa~
B
15,100
5,085
10,015
197
Increas
C
2,796
1,600
1,196
75
Increas
D
18,000
3,360
14,640
436
Inr’eas.
E
4,450
8,500
5,950
70
Increas~
Total
37,546
gpd
a
f38-o’25o
Inflow
-
Table
4 presents the measured inflow quantities fo11~
ing the rain event.
The resulting total instantaneous inflow
rate is 44,870 gpd, or 1870 gallons
per
hour.
Assuming
that
tb~
duration of this flowrate is
4
hours results in an inflow per
event
of
approximately
7,500
gallons.
TABLE
4
Instantaneous milow into
Trunk
Sewers
6/18/79
Trunk
Storm Inflow Dry Weather
Instantaneous
Line
Flow
(gpd)
Flow
(qpd)
Inflow
(gpd)
Remarks
A
8,100
3,750
4~,350
116SIncrease
B
15,000
.+
5,085
9,915
+
195
Increase
C
12,075
1,600
10,475
655
Increase
D
18,000
+
3,360
.
14,640
±
436
Increase
E
13,990
?,500
5,490
65
increase
Total
44,870
gpd
*
1,870
gph
Instantaneous ?lowrate x Estimated Duration
—
Total’ Inflow per *wa
.1,870 gph x
4
hours
7,500 gallons
Analysis of Lift Station Results
Table
5 presents the average daily pumpage through the
lift station
in 15
day time increments for the 3 month
period
of March through May.
Flows are based upon the pump design
ratings of 150 gpm at 70’ TDH although actual flows may vary
slightly.
During the first
15’ days of March the ground was
frozen and snow covered, so that the average daily pumpage of
12,910 gallons represents dry weather flows.
Thawing began ~
0138-025
I
8.
TABLE
5
VILLAGE OF CEDARVILLE
LIFT STATION
PUNpA~
Pumpage
~LnGPD
Month
Period
!!~gh
Avera~
Marc)~1979
1
—
15
9,900
16,650
12,910
16
—
30
18,450
47,475
27,091
I
-
15
12,825
26,325
17,283
16
-
3O
11,025
20,925
14,254
I
-
ii
7,650
22,882
12,78’
O138~O252
9.
March 16, with the following 15 day period having an
average
daily infiltration/inflow of 14,181 gallons through the
lift
station.
Assuming that this is representative of one—third of
the total
system
results
in
a
total
system
jnfjjtratjon,FjnfIow~
of 14,181 x 3
42,543 gallons
per
day which compares quite
well with the average
instantaneous
infiltration for
that per~
of
37,546
gpd.
As
can
be
seen
froaTable
6
,
the
average
infiltration/inflow was reduced to 13,119 gpd
during
the
first
part of April,
and
daily
flows were
back to normal dry
weather flows by the month
of May.
The
last column in
Tab1e~
indicates
the
estimated
total
system
I/I for each
period, ~
has
a
result
of
approximately
0.9
million
gallons
of
infi1tratio~
inflow due to anowmelt
and
high groundwater ‘conditions.
Estimated Total Annual Infiltration/Inflow
The results of the previous’
sections
indicate quantitl
~
infiltration/inflow.due
to
various
sources
as
I~i~”rizedbe1~
Estimated
Annual
Source
Amount
(Million Gallons)
General Infiltration
0.9’
Stormwater Inflow
1.2
Total
.2.1
These results indicate
essentially
equal
amounts
of infil-
tration and inflow.
The present average wastewater flow of
40,000 gpd results in
a total annual dry weather
flow of
14.6
million gallons.
Thus the estimated infiltration and
inflow
quantities amount
to
6
and
8
respectively, for a total
of 14t
of the annual dry weather flow.
Dl
38-0253
TABLE
6
VILLAGE OF CEDARVILLE
Ik~FIL?RATION/INFLOWMALYSIS
Lift
Station
Pumpage
in
GPD
Lift
Station
Total
System.
Estimated
Month
Period
Low
High
Average
Ave. I/I
Ave.
I/I
Total
I/I
~rch
1—15
9,900.
16,650
12,910
0
0
0
C..,
16—30
18,450
47,475
27,091
14,181
42,543
630,145
a,
I
c~
~ri1
1—15
12,025
26,325
17,283
4,373
13,1.9
196,785
16—30
11,025
20,925
14,254
1,344
4,032
60,480
895,410
gal.
The small amount of estimated stormwater inflow indicates
that there are no major storrnwater drainage system connections
to the sanitary sewer system.
The possible sources of the estimated quantity of general
infiltration include
poor
pipe joints, cracked or broken $ewer
pipe, seepage into manholes, poorly installed house service
lines, root intrusion,
and
other
effects of age and
dsterior*ti~
of the sewer system.
The locations of these
various
sources are
most likely scattered throughout the
system.
Infiltration/Inflow per Inch
—
Mile
Table
7 presents a suituary of the
size
and’ length of
sanitary sewer mains from the J~4Aand estimated
length
of
house
services in the Village of Cedarville.
TABLE
7
Description
Length
Inch Die. x
Mile
8” Sewer Main
16,664
25.25
12” Sewer Main
4,050
9.20
4” House Service
11,400
8.64
Total
43.09 Inch—Nil.
The highest weekly average infiltration/inflow through the
lift station occurred from March 29—April
4,
with an average
daily I/I as follows:
Ave.
Daily Punipage
~
29,886 gal.
Dry Weather Pun*page
F
12,910
I/I
through lift station
16,976
gpd
X
3
I/I
f.or
Total
System
=
.50,928 gpd/43.O9
1182 gpd/j
.0138-0255
12.
Per
PRM
78-10 issued by the
USEPA,
a
maximum
jnfiltrat
rate
of
less
than
1500
gpd/in.—mi.
can be considered as
flOfl
excessive, and a cost-effective
analysis
comparing
rehabilit
versus transporting
and
treating is not required.
0$ 38-0256
ATTAQIMENT
B
0138-0257
C’,
a,
I
Ui