ILLINOIS POLLUTION CONTROL BOARD
July 30, 1992
SHEREX CHEMICAL COMPANY, INC.,
)
Petitioner,
v.
)
PCB 91—202
(Permit Appeal)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
ORDER OF THE BOARD (by N. Nardulli):
This matter is before the Board on Sherex Chemical Company,
Inc.’s (Sherex) motion for summary judgment filed June 5, 1992.
On June 24, 1992 the Illinois Environmental Protection Agency
(Agency) filed a motion to file its response and cross motion for
summary judgment instanter. The Agency’s motion to file
instanter is granted. On July 5, 1992, Sherex filed its response
to the Agency’s cross motion.
BACKGROUND
The facts are not in dispute. Sherex purchased its Mapleton
facility in 1979 from Ashland Chemical Company (Ashland).
Ashland purchased the property in 1967 from Archer—Daniels—
Midland Company (ADM). While ADM owned the property, it operated
a high pressure alcohol reactor (HPAreactor). ADM cleaned the
reactor with a nitric acid cleaning solution which contained
copper and cadmium. The cleaning solution was disposed of on—
site until 1975 or 1976, after which the solution was sent off—
site for disposal.
The HPA reactor on—site disposal area at the Mapleton
facility was added to Illinois’ State Remedial Action Priorities
List (SRAPL)1 and investigatory efforts were performed by Sherex.
Ashland, Sherex and the Agency agreed to jointly fund a Remedial
Investigation (RI) and also agreed to pursue costs from ADM. The
final RI was completed in May of 1988 at a cost of $300,000.
The RI concluded that the cleaning material had not shown
significant migration and recommended further monitoring and
installation of an additional well.
The Board notes that on June 25, 1992, the Illinois
Appellate Court, Fourth Judicial District, held that
the Agency’s regulations purporting to authorize the
SRAPL are void. (States Land Improvement Corp.
V.
IEPA
No. 4—91—0365, slip op. (June 25, 1992).)
0135-0131
2
In March, 1988, the Illinois Attorney General, at the
request of the Agency, filed a civil action against ADM for the
recovery of response costs. ADM filed a contribution action
against Ashland and Sherex and Ashland and Sherex filed
counterclaims. On January 7, 1991, the federal district court
entered a consent decree agreed to by ADM, Sherex, Ashland, the
State and the Agency governing past and future response costs.
On September 20, 1991, the Agen~yissued Sherex’s RCRA Part
B Permit. The permit designates certain sites at the Mapleton
facility as Solid Waste Management Units (SWMU) subject to
corrective action, including investigation and possible remedial
action. Sherex filed a permit appeal with the Board challenging
the designation of the SWNU5. Pursuant to a stipulation
agreement, Sherex and the Agency have resolved all issues
appealed by Sherex except for item #14 in Section III of the
permit designating the HPA reactor disposal area as a SWMU.
DISCUSSION
The parties agree that there are no genuine issues of
material fact and that the only question remaining is whether the
Agency’s designation of the HPA reactor area as a SWMU is
improper because the Agency has already agreed to the appropriate
remediation in the consent decree which also releases the parties
from future claims. In a permit appeal before the Board, the
issue is whether the disputed permit condition is necessary to
accomplish the purposes of the Environmental Protection Act (Act)
and Board regulations. (Joliet Sand & Gravel v. IPCB (3d Dist.
1987), 163 Ill. App. 3d 830, 516 N.E.2d 955, 958.) Because the
Board is presented with motions for summary judgment, the proper
inquiry is whether, as a matter of law, the designation of the
HPA reactor area as a SWMU is necessary to accomplish the
purposes of the Act and Board regulations in light of the consent
decree. To decide this issue, the Board must compare the
provisions of the consent decree and the permit condition.
The section of the permit governing corrective action
provides that Sherex shall submit to the Agency a “written RCRA
Facility Investigation (RFI) Phase I Workplan to document the
absence or presence of hazardous waste or hazardous constituents”
from the
“SRAPL
site (HPA reactor cleaning solution area).” (R.
162-63.) The requirements for the RFI Phase I Workplan are
outlined in Attachment A which provides that the purpose of Phase
I is to demonstrate conclusively whether or not any release of
hazardous wastes or constituents has occurred from the SWNU. (R.
184.) If the Agency determines that the data submitted in the
Phase I Workplan establishes that no release occt~rred, no further
action is required. (R. 163.) If the Agency concludes a release
did occur, Sherex must submit a Phase II Workplan to determine
the extent of migration. (R. 163.) The Agency will determine
whether corrective action is necessary based upon the Phase II
0135-0138
3
Workplan. (R. 163.) These provisions are sta;~iard “boiler-
plate” language in RCP.A Part B Permits. (Pet. Mot. for Suinm.
Judg. Ex. E Dep. James Moore at 63.)
The consent decree recognizes that there was an actual and
threatened release of copper and cadmium, which are hazardous
substances, from the SRAPL HPA reactor disposal area at the
Napleton site. (Pet. Mot. for Summ. Judg. Ex. C at 3.) The
parties agreed that the State would be reimbursed for past and
certain future response costs and that ADM, Ashland and Sherex
will share past, future and contingent response costs.
(~
at
4.) The decree provides that the State or its designee may
undertake a monitoring program to determine the levels of cadmium
and copper in the groundwater and that the Agency, in
consultation with the other parties, will determine which wells
to sample, the method of sampling and the schedule for sampling
and analysis.
(I~
at 6.) The decree creates a fund allowing
the state to perform further response action, possibly including
the construction of a slurry wall.
(~
at 7—10.) The release
section of the decree, which is the focal point of the Agency’s
cross motion for summary judgment, provides as follows:
In consideration of the mutual promises and undertakings
contained herein, the parties agree that upon entry of this
Consent Decree, they hereby release each other.. .froin any
and all claims of any party to the disposal of spent nitric
acid wash from the !WA reactor at the Mapleton site,
including all claims which were raised or which could have
been raised with respect thereto.
Further, nothing in this Consent Decree shall be construed
as a release of any right to bring an action to redress
violations of this Consent Decree or of any applicable State
or Federal laws or regulations or to obtain response costs
with respect to the migration of hazardous substances from
the Site or to the Site from another site.
(j~
at 13—15.)
Sherex contends that the language of the consent decree bars
the Agency from requiring any corrective action for the SRAPL HPA
reactor site unless such action is required by the consent
decree. The Agency contends that the release language quoted
above preserves the Agency’s right to designate the SRAPL site as
a SWMU subject to corrective action.
The second paragraph of the release language quoted above
preserves the right to bring an action to enforce the terms of
the consent decree or an action to enforce any applicable laws or
regulations. This language simply preserves the Agency’s ability
to bring an enforcement action to address violations of the Act
0135-0139
4
or regulations. Designation of the SRAPL site as a SWMU during
the permitting process is not an “action to redress violations”
of the laws or regulations. Contrary to the Agency’s contention,
this release language does not preserve the right to impose
permit conditions.
The first paragraph of the release quoted above provides
that the parties have agreed to release each other from any
“claims” relating to the disposal of acid nitric wash at the HPA
reactor disposal area which were raised or could have been
raised. However, the Agency’s authority to impose a permit
condition is not a claim. The Board finds that this language by
itself does not preclude the Agency from imposing permit
conditions relating to the HPA reactor area.
Based upon a review of the release provisions, the Board
finds that this language preserves the Agency’s ability to bring
certain enforcement actions and that the release does not
preclude the Agency from imposing permit conditions. Apart from
the release provisions of the decree, however, the Board is still
left with the question of whether the remaining provisions of the
decree prevent the Agency from requiring further response action
with regard to the SRAPL HPA reactor site.
The consent decree governs corrective action necessitated by
the release of cadmium and copper which was present in the nitric
acid solution used in cleaning the HPA reactor and disposed of
on-site at the Mapleton facility. The parties agree that this
consent decree was entered into after adding the HPA reactor
disposal area to the SRAPL and the completion of the Remedial
Investigation (RI) funded by Ashland, Sherex and the Agency. The
subject matter of the decree and the challenged permit condition
is identical. Both the decree and the permit condition concern.
the release of cadmium and copper from the HPA reactor disposal
area. The consent decree sets forth the Agency’s agreement as to
the appropriate corrective action to be performed at the SRAPL
HPA reactor disposal area. The challenged permit condition
requires that Sherex perform certain studies investigating the
occurrence of a release from the SRAPL HPA reactor disposal area.
The Board concludes that because the Agency has entered into
a consent decree agreeing to the corrective action measures to be
performed at the SRAPL HPA reactor site as a result of the
release of cadmium and copper, it is barred from imposing a
permit condition designating that same site as a SWMU subject to
investigation and corrective action.
Moreover, the Board finds that, as a matter of law, the
challenged permit condition requiring investigation into whether
a release has occurred and possible corrective action is not
necessary to accomplish the purposes of the Act and regulations.
While the parties have focused on the release provisions of the
0135-ORO
5
consent decree, they have failed to focus on whether the
challenged condition is necessary to accomplish the purposes of
the Act and regulations. As noted above, this is the proper
inquiry in a permit appeal before the Board. Here, this inquiry
must be addressed in the context of a motion for summary
judgment.
Citing 35 Ill. Adm. Code 724.201, the Agency does make the
general assertion that the condition is consistent with the
Board’s regulations. However, Section 724.201 merely provides
that owners and operators seeking hazardous waste disposal
permits must institute corrective action for all releases from
SWMUs. This general provision does not support the Agency’s
imposition of the challenged permit condition in light of the
investigative and remedial actions taken by the parties to the
consent decree. •The instant condition is not necessary because a
release has already been identified, a RI has been performed
assessing the extent of migration and appropriate corrective
action has been established. To require, by way of a permit
condition, actions which have already been undertaken pursuant to
a consent decree does nc~thingto further the purposes of the Act
or regulations. Theref.re, the Board reverses the Agency’s
imposition of the permit condition designating the SRAPL HPA
reactor site as a SWMU subject to corrective action. Sherex’s
motion for summary judgment is granted. The Agency’s cross
motion for summary judgment is denied. The Agency is instructed
to strike the challenged condition from Sherex’s RCRA Part B
Permit.
The Board notes that the stipulation entered into by Sherex
and the Agency provides that “the parties will request a
continuance of the hearing as it concerns three itents)...to
allow Sherex to complete its the sic) proposed sampling and
analysis plan...and in order to allow the Agency to complete its
review of) Sherex’s sampling and analysis results.” However,
the stipulation also provides that the stipulation will. be
implemented by means of a permit application filed by Sherex
-after completion of the sampling results. Sherex also states in
its memorandum in support of summary judgment that “ajfter
completion of the sampling the parties hope to be able to resolve
all remaining issues. If not, the hearing will resume.” (Mem.
at 3 fn. 3.) Sherex’s motion for summary judgment does not
indicate that it is a partial motion for summary judgment, but
rather states that the issue concerning the designation of the
SRAPL HPA reactor site as a SWNU is the “only issue currently
pending in its appeal of the RCRA Part B Permit”.
~
at 1.)
Although the parties have agreed to continue the hearing in this
docket, they have also agreed that any issues stemming from the
three “sampling items” will be dealt with via a new permit
application. The Board concludes that the instant order disposes
of all remaining issues in this docket and, therefore, this
docket is closed.
0135-01
I~
1
6
IT IS SO ORDERED.
B. Forcade concurs.
Section 41 of the Environmental Protection Act (Ill. Rev.
Stat. 1991, ch. 111 1/2, par. 1041) provides for the appeal of
final Board orders within 35 days. The Rules of the Supreme
Court of Illinois establish filing requirements. (But see also,
35 Ill. Adm. Code 101.246, Motions for Reconsideration, and
Casteneda
V.
Illinois Human Rights Commission (1989), 132 Ill. 2d
304, 547 N.E.2d 437.)
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby cert~fythat the above order was adopted on the
~
day of
____________
,
1992 by a vote of
~-~‘
Dorothy N. G~(j’in, Clerk
Illinois PolU/ution Control Board
0135-01142