ILLINOIS POLLUTION CONTROL
    BOARD
    September 17, 1992
    CITY OF ROODHOUSE,
    Petitioner,
    v.
    )
    PCB 92—31
    )
    (Underground Storage Tank
    ILLINOIS ENVIRONMENTAL
    )
    Fund Reimbursement)
    PROTECTION AGENCY,
    )
    Respondent.
    MR. CHARLES E. MCNEELY,
    APPEARED
    ON BEHALF OF THE PETITIONER;
    AND
    MR. TODD F. RETTIG, APPEARED ON BEHALF OF
    THE
    RESPONDENT.
    OPINION
    AND
    ORDER OF THE BOARD
    (by J. Anderson):
    On February 25,
    1992,
    the City of Roodhouse (Roodhouse)
    filed a petition for review of the determination of the Illinois
    Environmental Agency (Agency) to deny reimbursement for certain
    corrective action costs from the Illinois Underground Storage
    Tank Fund.’
    The appeal to the Board is pursuant to Section
    22.18(g) and Section 40 of the Environmental Protection Act
    (Act).
    (Ill. Rev.
    Stat.
    1991,
    ch. 111 1/2, par.
    1022.18(g)
    and
    1040.)
    Hearing was held on June
    6,
    1992.
    No members of the public
    participated.
    Roodhouse and the Agency filed briefs on July 29
    and August 13,
    1992,
    respectively.
    Roodhouse filed a reply brief
    on August 19,
    1992.
    By letter dated January 21,
    1992,
    the Agency notified
    Roodhouse of its determination that,
    of the $162,333.22 requested
    for reimbursement from the Illinois Underground Storage Tank Fund
    (UST Fund), which covered invoices for the period from January
    1990 to August 1991,
    $35,178.73 was eligible for reimbursement.
    The disallowed amounts included the deductible of $100,000, which
    Roodhouse does not contest.
    The remaining disallowed amounts
    were itemized in seven separate paragraphs in Attachment A of the
    1
    Roodhouse
    intends
    to
    submit
    additional
    claims
    for
    reimbursement.
    On March
    26,
    1992,
    the Board,
    in response to an
    Agency motion to dismiss
    as not ripe,
    held that this appeal
    is
    properly before the Board.
    0
    t 36-0029

    2
    Agency’s notification letter.2
    Roodhouse does not contest the
    first
    2 of the
    7 paragraphs in Attachment A.
    Roodhouse contests
    the amounts listed and explained in paragraphs
    3 through 7 of
    Attachment A, quoted as follows:
    3.
    $1,966.26,_fo
    an
    adlustrnent
    in hand1~
    charges.
    The
    handling charges submitted were greater than 15.
    The
    handling charges were reduced to 15
    resulting in the above
    deduction.
    The owner or operator failed to provide a
    demonstration that the costs were reasonable as submitted.
    (Section 22.18b(d) (4) (C)
    of the Illinois Environmental
    Protection Act)
    4.
    $82.70, for an adjustment in overnight mail charges.
    The
    owner or operator failed to provide a demonstration that the
    costs were reasonable as submitted.
    (Section
    22.18b(d) (4) (C)
    of the Illinois Environmental Protection
    Act).
    5.
    $11,088.47,
    for an adjustment in disallowed travel costs.
    The associated costs are not corrective action costs.
    One
    of the eligibility requirements for accessing the UST Fund
    is that the costs incurred were corrective action costs or
    indemnification costs which were incurred by the owner or
    operator as a result of a release or
    (sic) petroleum, but
    not including any hazardous substance from an underground
    storage tank.
    (Section 22.18b(a)(3)
    of the Illinois
    Environmental Protection Act).
    6.
    $5,676.72,
    for an adjustment in legal defense costs.
    Corrective action does not include legal defense costs.
    (Section 22.18(e)(C)
    (sic
    apparently Section
    22.18(e)’ (1) (C))
    of the Environmental Protection Act).
    One
    of the eligibility requirements for accessing the UST Fund
    is that the costs incurred were corrective action costs or
    indemnification costs which were incurred by the owner or
    operator as a result of a release of petroleum, but not
    including any hazardous substance from an underground
    2
    The
    remaining
    non—reimbursable
    amount,
    as
    stated
    by
    Roodhouse
    (Pet. at
    1) was
    (and by simple subtraction would appear
    to be) costs of $27,154.49 contained in the invoices.
    However, the
    amounts
    disallowed
    by
    the
    Agency
    in
    Attachment
    A
    total
    only
    $26,074.49,
    leaving $1080.00 unaccounted for.
    Also,
    as corrected
    by the Agency
    at hearing,
    $837.50
    should
    be deducted from the
    $1608.29
    in paragraph
    2,
    and
    the
    Agency
    had no
    explanation at
    hearing
    for
    the
    discrepancy
    between
    the
    $11,088.47
    listed
    in
    paragraph
    5
    of
    Appendix
    A
    and
    the
    $11,888.47
    listed
    in
    the
    vouchers. Even correcting for the above amounts,
    there remains
    a
    discrepancy of $1106.50.
    (Pr. at 83, 87, Agency Record at 691.)
    0136-0030

    3
    storage tank.
    (Section 22.18b(a) (3)
    of the Environmental
    Protection Act).
    7.
    ~$4,841.O5, for an adjustment in costs associated with the
    attendance of City Council meetings.
    The associated costs
    are not corrective action costs.
    One of the eligibility
    requirements
    f~
    àc~i~isiñgthe
    UST
    iñd~i~that
    the costs.
    incurred were corrective action costs or indemnification
    costs which were incurred by the owner or operator as a
    result of a release or
    (sic) petroleum, but not including
    any hazardous substance from an underground storage tank.
    (Section 22.18b(a) (3)
    of the Illinois Environmental
    Protection Act).
    BACKGROUND
    SUMMARY
    The
    occurrences
    surrounding
    this
    dispute
    are
    quite
    unusual.
    Roodhouse,
    located in Greene County, has approximately 1900
    residents.
    Its water supply consists of two wells, which also
    serve several other small municipalities.
    In late 1989,
    Roodhouse experienced a strong fuel odor in its well water.
    The
    Agency and Roodhouse’s consulting engineer, Benton and
    Associates,
    Inc., were called in.
    (Pr. at 7.)
    Mr. Frank Lewis of
    the Agency investigated the situation.
    Samples were taken, boil
    orders were issued, and, at the suggestion of the Agency,
    residents were even cautioned not to bathe in the water;
    Roodhouse incurred considerable expense hauling in potable water
    in
    a tanker to city hail so residents could pick up water, and
    the water was directly brought to the elderly confined to their
    homes.
    (Tr. at 70.)
    Subsequent investigation verified what was
    suspected early-on
    -
    that the contamination problem at the well
    site was from leakage from close—by underground storage tanks
    (USTs) that had once supplied diesel fuel for the water supply
    pumps prior to a conversion to electric power.
    Later the water
    table rose and eventually the well was usable again.
    (Tr.
    at 13;
    Pet.
    Br. at
    1,
    2.)
    The characteristics of Roodhouse’s wellwater source are
    noteworthy.
    About 500
    gpm
    is pumped from the weliwater source.
    However, because the source is a spring, an additional amount of
    water about equal to that which is pumped spills out and runs
    down to the creek, except that the overflow diminishes during
    extended dry or cold periods.
    Roodhouse had experienced three
    dry years.
    During the contamination event,
    the overflow had
    ceased and the water level had dropped 50 feet of the total well
    depth of 170 feet.
    (Pr. at 16,
    17; Pet. Br. at 1.)
    In Attachment
    A,
    Paragraph
    7
    is misnumbered as another
    paragraph 5.
    We will hereinafter refer to it as Paragraph 7.
    0136-0031

    4
    DISCUSSION
    Roodhouse quickly focused on its water supply problem.
    Starting in January 1990 and throughout that year, there were
    many meetings between Roodhouse’s engineering consultant, Benton
    and Associates, principally Mr. Robert H. Benton, and the City
    ~CbunciI.
    TXiTê
    fl
    h~hdThdWãte~
    ahd~seweb1tS~r
    Roodhouse since about 1984.
    During that time Roodhouse also had hired and met with an
    outside consultant recommended by Mr. Benton, Layne Geosciences
    of Kansas City, Kansas, to investigate the contamination cleanup
    situation and prepare a report.
    The distance from Roodhouse of
    the consulting firm was an issue in this matter.
    Mr. David B.
    Killen, the district manager of Layne Geosciences, was the
    principal person meeting with the Roodhouse City Council,
    visiting the well site, and consulting with the Agency.
    Layne
    Geosciences had dealt nationwide with water supply identification
    and protection and cleanup of soil and groundwater contamination.
    Layne Geosciences is a geotechnical subsidiary of
    Layne
    Western,
    and was formed as an outgrowth of the geotechnical section of the
    parent company.
    Layne Western specializes in well drilling and
    pump maintenance;
    it had performed all the work on Roodhouse’s
    wells for 40 years,
    including the shift from diesel power to
    electric power, and had good records on Roodhouse’s wells.
    Mr.
    Benton felt that Roodhouse’s “best shot” was to hire someone
    related to wells rather than industrial cleanup spills.
    While he
    was aware of, and discussed with the City Council,
    other firms in
    Illinois that might do cleanup work, he felt that the water
    source was a tremendous asset needing protection, and he was not
    aware of anybody who had done a cleanup located at a public water
    supply’s well.
    The City told him to contact
    Layne
    Geosciences.
    (Pr. p.
    9,
    10,
    11,
    13,
    14,
    41,
    45—47,
    51,
    55; Pet. Br., attached
    Affidavit.)
    During the latter part of 1990 a plan of action was
    developed with the approval of the Agency.
    (Tr.
    14.)
    Roodhouse’s
    contamination problem was unusual: the contamination source and
    the pumps were within the same building, within 50 feet of each
    other, and the hydrogeology of
    the
    immediate area was complex.
    Mr. Killen stated that, while it is not uncommon to have his
    company find contamination problems and water problems occurring
    together, he had never seen a contamination source so close to a
    municipal water supply well.
    Mr. Benton, Roodhouse, Layne
    Geosciences, and the Agency decided to hold off groundwater
    remediation until an alternate water supply was in place, so as
    to guarantee that the water supply would not be interrupted
    during the remediation work.
    (Tr. at 57,
    67.)
    Benton and
    Associates engineered the installation of the alternate water
    supply, and Layne Geosciences engineered the remediation of the
    contamination.
    (Tr.
    at 18,
    45.)
    The delay in groundwater
    remediation became an issue in this matter.
    0136-0032

    5
    The water supply part of the plan involved running a
    10 inch
    water line to the City of White Hall
    (White Hall),
    about three or
    four miles away, so that water could be purchased in sufficient
    quantities to stabilize the water level of Roodhouse’s well when
    the water stops overflowing and the water table falls ten feet
    below
    t~ie surf
    ac~p~ if necessary1 to provide a fullwater
    supply in the event that the pumps had to be shut down.
    The
    contract negotiated with White Hall for the purchase of water was
    handled by Mr. Benton and Roodhouse’s attorney, Mr. Charles
    McNeely, and items related to the installation of the pipeline
    were handled by the respective city attorneys.
    (Tr. at 14-19,
    71.)
    Before Roodhouse chose White Hall as their alternate water
    supply, Mr. Benton had, during 1990,
    investigated and prepared
    cost estimates, using a 20 year period,
    for a number of options.
    The options included on-site treatment (installing aerator
    equipment); moving the wells; and purchasing water from another
    municipality when the quality of the existing well water was
    unacceptable.
    Mr. Benton stated that the on-site treatment
    alternative in particular was carefully considered.
    However,
    after discussions with the Agency,
    it was concluded that, due to
    the inability to totally clean up all of the diesel fuel
    contaminant, an odor problem would develop each time the water
    table dropped again.
    The Agency indicated that the purchase of
    water,
    if it was the most cost—effective option, should be
    pursued.
    The City Council selected, as the most cost effective
    solution, the purchase of water from White Hall.
    (Pr. at 14—17,
    72.)
    Mr. Killen testified that Harry Chappell of the Agency
    approved the pipeline option as opposed to an on—site groundwater
    remediation option.4
    (Pr. at 66.)
    In order to bring in the water as well as to clean up the
    site,
    the building in which the UST and wells were located had to
    be removed and replaced, the pump house had to be demolished, and
    new electrical service installed..5
    Cleanup of the contamination
    at the site was delayed for two years,
    until March of 1992, which
    was the amount of time it took to implement all facets of the
    ~ The Agency’s April 1992 organizational chart lists Mr. Harry
    Chappell as overseeing the Agency’s Leaking Underground Storage
    Sites in the Division of Remedial Management in the Bureau of Land.
    ~
    Roodhouse “reluctantly” accepted the Agency’s disallowance
    of
    the costs
    of
    removing
    the
    building
    and
    installing
    the
    new
    electrical equipment,
    the latter because the emergency power was
    torn out when the building was removed
    (Tr. 20.)
    0
    I 36-0033

    6
    project involved in connecting a water line to White Hall.6
    During this two year period,
    the weliwater source supply became
    sufficient to avoid another contamination occurrence.
    (Pr. at
    89.)
    At hearing, there_was considerable testimony_about the
    ~
    Coii~il,
    including
    f?s
    committee
    meetings,
    and
    getting
    its
    approval
    at
    various
    stages
    of
    remediation
    steps
    along
    the
    way.
    (e.g.
    Pr.
    at
    18-21,
    25,
    53-58,
    64,
    65,
    108.)
    Mr.
    Benton
    noted
    that
    Roodhouse’s
    meeting
    pattern
    was similar to 36 local governments with whom the firm has had
    projects over the last five years, and that most of these entail
    night meetings.
    (Pr. at 19.)
    Mr. Benton stated that this pattern
    is in accordance with the advice he receives from every city
    attorney his firm works with,
    adding:
    We have to have City Council approval to approve the
    plans to submit to the EPA for permits, construction
    permits.
    We have to have City Council approval for
    advertising for bids,
    too.
    And obviously,
    if they are
    going to have their approval, we have to explain it to
    them, and we have to explain it to them before it’s
    finalized, because we can’t come to them and say here
    it
    is, approve it or disapprove it.
    .
    .
    (the
    City Counsel
    (sic)
    is the elected body that has to make that
    decision.
    (Tr.
    at 21,
    22.)
    Mr. Killen had similar observations:
    A typical City Council meeting would be to revise a
    draft of the remedial investigation plan based on some
    of our conversations with EPA.
    We come back, tell the
    City this is our current draft, please look it over,
    give us your opinions, whatever.
    (Tr. at 64.)
    Mr. Kip Proefrock,
    a city alderman, testified that the Mayor
    and the six alderman serve part time;
    all but one, who is
    disabled, have other full time jobs.
    Thus,
    of necessity, all
    City Council meetings took place in the evening.
    The City
    Council met twice monthly in regular session and in a workshop in
    alternate weeks.
    He testified that there were many meetings with
    6
    In that actual groundwater remediation had not commenced
    when Roodhouse’s
    petition was
    filed
    on
    February
    25,
    1992,
    the
    invoices
    in
    this
    case
    do
    not
    cover
    those
    costs.
    The record
    indicates that remediation was ongoing at the time of the June 6,
    1992 hearing.
    0136-00314

    7
    Mr. Killen or Mr. Benton, who were present to provide
    explanations and recommendations.
    Mr. Proefrock stated that Mr.
    Killen was present at several of them and Mr. Benton at many of
    them between January of 1990 and April of 1991.
    He further
    stated that it was Mr. McNeely, Roodhouse’s attorney (and
    representing Roodhouse in this instant matter), who negotiated
    the~contract~witkr~White~
    the landowners.
    Mr.
    Proefrock also stated that no claims were
    made against Roodhouse throughout the whole episode.
    (Tr. at 68,
    71,
    73.)
    Reimbursement of Mr. McNeely’s costs became an issue.
    Mr. McNeely has been Roodhouse’s city attorney for 13 years.
    He testified and proffered an affidavit concerning the nature of
    his legal work and his attorneys fees with regard to the
    pipeline.
    At the direction of the City Council, he negotiated
    the contract with White Hall,
    which required a number of
    redrafts; obtained legal descriptions of various parcels;
    negotiated, drafted and redrafted a total of
    10 separate
    easements
    with
    the
    landowners;
    and
    incurred
    out—of—pocket
    expenses
    such
    as
    for
    photocopying,
    recording
    the
    easements,
    and
    title searches.
    His invoices also show a number of conversations
    with Agency personnel1
    including conversations about the Layne
    Geosciences contract.’
    He asserted that none of his billings
    were in connection with defending any claim.
    (Tr. at 73-79; Pet.
    Ex.
    1, attached to transcript.)
    Aaencv Testimony.
    Mr. Douglas Oakley was the principal witness
    for the Agency.
    Since January,
    1990,
    he has supervised two
    accountants and one office associate in the remedial projects
    accounting procurement unit.
    The unit processes leaking
    underground storage tanks
    (LUST) reimbursement applications and
    invoices.
    Mr. Oakley was responsible for reviewing the documents
    submitted by Roodhouse and provided the disallowed amounts listed
    in Attachment A,
    except for those
    in paragraph 7,
    of the Agency’s
    January 21,
    1991 letter to Roodhouse.
    (Tr. at 80-83.)
    As earlier
    noted, Paragraphs
    3 through 7 are appealed.
    Paragraph #3.
    Regarding the handling charges of $1966.26 in
    Paragraph #3 of Appendix A, Mr. Oakley stated that this referred
    to the 15
    handling charges, disallowed because the associated
    basic charge was ineligible.
    (Tr. at 84,85.)
    Paragraph #4.
    Regarding the overnight mail charges of
    $82.70 in Paragraph #4 of Appendix A, Mr. Oakley stated that,
    for
    reasons of cost effectiveness, the Agency normally does not pay
    for such express charges unless lab samples taken from the actual
    contamination site are involved.
    (Tr. at 85,
    86.)
    ~‘
    Roodhouse later stipulated that there is one phone call that
    would not be reimbursable, in that it concerned whether the actual
    cost of right-of-way would be reimbursable.
    (Pet.
    Br. at 11.)
    0136-0035

    8
    Paragraph #5.
    Regarding the travel costs of $11,088.47 in
    Paragraph #5 of Appendix A, Mr. Oakley stated that, because they
    felt that the costs were unreasonable, the Agency disallowed
    them.
    These charges involved the services of Layne Geosciences.
    Certain meal charges were disallowed because of the absence of
    receipts,
    but
    most of the charges1 for_items related_to
    transportation,
    were
    disallowed because “...from our viewpoint,
    the
    actual
    remediation
    of
    the
    site
    did
    not
    start until March of
    ‘92,
    and
    for
    two
    years
    to
    a
    tune
    of
    $11,000
    of
    transportation
    costs, that seemed unreasonable.”
    (Pr. at
    89,
    90.)
    Regarding “unreasonable”,
    Mr. Oakley stated that there are
    written guidelines “in-house”
    (Tr. at 95), not available to
    applicants,
    as to when travel is reimbursed and when it is not,
    but that “It’s basically what we consider to be reasonable travel
    costs.”
    (Tr. at 95.)
    He stated that normally travel only by automobile is
    reimbursed, at a rate of 50 cents a mile, for such activities as
    preliminary site investigation.
    However, reimbursement was
    disallowed for Layne Geosciences: because its expenses were
    higher due to the distance (Kansas City); because of the Agency’s
    responsibility to clean up hundreds of sites throughout the State
    with a limited amount of money; and because the remediation
    didn’t start for two years,
    until 1992.
    He acknowledged that he
    was unaware that the Agency wanted the backup water supply in
    place so the water supply would not be interrupted.
    However, he
    stated that this would not have altered his decision because
    “...the wells have replenished themselves and the only time there
    is any contamination or any problem is when the water level drops
    to a certain point.”
    (Tr. at 94-97.)
    When asked how the time
    of remediation startup makes a difference in reimbursability,
    Mr.
    Oakley again responded only the “we felt costs associated with
    this remedial investigation were unreasonable.”
    (Tr. at 97.)
    In response to a question from the hearing officer as to
    what objective criteria were used to determine what costs were
    reasonable, Mr. Oakley replied that they rely on comparisons with
    similar job sites derived from in—house lists gathered from
    audits over the last two years involving hundreds of
    reimbursements.
    Regarding Layne Geosciences’ travel costs,
    however, Mr. Oakley stated that he had never seen “$162,000.00 in
    costs incurred prior to turning one shovel full of dirt”.
    When
    asked whether he has ever reviewed an application where the
    contamination was also at the source of the water supply, Mr.
    Oakley replied that he considers the costs related to the source
    of the water supply as “pre remedial”, not actual remediation
    costs.
    He then stated that it wasn’t because such costs weren’t
    corrective action, but stated again that they were unreasonable
    because “they were incurred before one shovel of dirt was turned
    for remediation”.
    (Tr. at 101,
    102.)
    0136-0036

    9
    As referenced earlier
    (see Footnote 2),
    Mr. Oakley had no
    explanation for the discrepancy between the $11,088.47 amount
    disallowed in Appendix A and the $11,888.47
    on the actual invoice
    voucher.
    (Pr. at 86,
    87, Agency Rec. Book A, at 693.)
    Paragra~ph#6.__Regardi~
    the_le~g~
    costs_of_$~7~.7~in
    Paragraph #6 of Appendix A, Mr. Oakley testified that those
    charges were disallowed because the “law requires that we do not
    pay legal costs.”
    (Pr. at 91.)
    After being shown the Board
    regulations that refer only to legal defense costs as not being
    reimbursable, Mr. Oakley acknowledged that right-of-way
    acquisitions and contract negotiations costs would not fit into
    the regulatory definition of legal defense costs.
    However, he
    stated that,
    as a matter of Agency policy,
    it is the Agency’s
    position that,
    irrespective of the reason for the legal costs,
    legal costs are not reimbursable at the present time.
    (Tr. at
    93,
    94.)
    Paragraph #7.
    Regarding the City Council attendance costs
    of $4,841.05 in Paragraph
    #
    7, Becky Lockart testified for the
    Agency.
    Ms. Lockart has been the project manager in the LUST
    section since July of 1990.
    She reviews applications and claims
    for reimbursement and technical site data regarding corrective
    action.
    (Tr. at 103,104.)
    Ms. Lockart testified that the costs
    for Layne Geosciences and Benton and Associates to attend City
    Council meetings are not reimbursable because they are not
    corrective action costs.
    She verified that the costs referred to
    are found in the Agency Record in Book A,
    pp.
    618-623.
    (Pr. at
    103—105,
    108.)8
    g
    A review of the vouchers and Agency notes indicates that:
    Mr. Benton attended 10 meetings, all in 1990,
    incurring associated
    costs of
    $1621.10; and Mr. Killen attended 8 meetings,
    incurring
    associated costs of $3219.90.
    The subjects covered by Mr. Benton
    are addressed above.
    The Layne
    Geosciences meetings included:
    location
    of
    the
    UST’s;
    scope
    of
    work;
    meetings with the
    City
    Council and Agency, Mr.Benton and Mr. McNeely involving preparation
    of draft report, recommendations, and presentation of formal soil
    remediation
    plan
    to
    Roodhouse
    and
    the
    Agency;
    contracts with
    subcontractors,
    landfill
    selection,
    site
    preparation,
    formal
    allocation of tasks among Layne Geosciences, Benton Associates, and
    subcontractors, and presentation of health and safety plan.
    (Also
    see Agency Rec. Book A, at 685.)
    Mr. McNee.y’s
    meeting costs were
    not included in Paragraph #7, but instead were denied in paragraph
    #6.
    A review of the Mr. McNeely’s voucher indicates that the bulk
    of his time charged was spent in contract negotiations and easement
    acquisition; a total of $461.18 was submitted for attendance at two
    Council workshops in December, 1990 and March,
    1991.
    (Agency Rec.
    Book A, at 242—246.)
    0136-0037

    10
    With regard to costs incurred by the engineers when
    consulting with the Agency,
    Ms. Lockart stated that the
    consultations with Mr.
    Lewis may not be reimbursable because he
    does not work for the LUST section, but that the costs of
    consulting with Mr. Chappell may be.
    When asked how Roodhouse is
    to formulate a corrective action plan to submit to the Agency
    without coi~suItationvith ~tt~~en~ineerT1Is.Lo~kar~t
    respohd~d
    that she believes that it is the function of the engineer, not
    Roodhouse,
    to compile the corrective action plan.
    She
    acknowledged that the regulations require the owner to submit the
    plan and that she was not familiar with the Open Meetings Act of
    Illinois.
    (Pr. 107,108.)
    ARGUMENTS
    Before summarizing the arguments regarding the detailed
    amounts disallowed, we will first repeat the relevant portions of
    the definition of corrective action in Section 22.18(e) (1) (C) of
    the Act:
    “Corrective action” means an action to stop, minimize,
    eliminate or clean up a release of petroleum or its
    effects as may be necessary or appropriate to protect
    human health and the environment.
    This includes, but
    is not limited to, release investigation, mitigation of
    fire and safety hazards, tank removal, soil
    remediation, hydrogeological investigations,
    free
    product removal, groundwater remediation and
    monitoring,
    exposure assessments, the temporary or
    permanent relocation of residents and the provision of
    alternate water supplies.
    .
    .
    Corrective action does not
    include legal defense costs.
    Legal defense costs
    include legal costs for seeking payment under Section
    22. 18b.
    Roodhouse and the Agency ask the Board to view the situation
    from markedly different perspectives, which we summarize in some
    detail below.
    Engineering costs.
    Paragraphs #3,
    #4,
    #5, and #7.
    Regarding Paragraph #3, the Agency agrees that the
    reimbursement of the 15
    handling charges would accompany any
    reimbursement of costs the Board determines should be made.
    (Agency Br.
    at
    3,
    4.)
    Regarding Paragraph #4, the Agency argues that the overnight
    mail charges of $82.70 are unreasonable because they are in a
    category of costs that are not an efficient and effective use of
    the Fund and that it only accepts express mailings of lab samples
    from the site.
    It also argued that the documentation gives no
    indication that the use of overnight mail was essential,
    and Mr.
    0136-0038

    11
    Killen’s testimony did not elaborate on its reasonableness.
    Roodhouse did not argue the overnight mail point specifically,
    but merely noted in its summary in its Brief that the charges
    relate to submitting data to the Agency and to shipping equipment
    between the their office and the site.
    (Pet.
    Br. at 13; Agency
    Br. at 4.
    5.)
    Regarding the engineering costs associated with Paragraphs
    #5 and #7
    (travel and City Council meetings), Roodhouse asks the
    Board to understand the circumstances when the crisis occurred.
    In January of 1990 there was no drinking or bathing water,
    the
    source of contamination was uncertain,
    and what was needed to
    alleviate the problem unknown.
    Asserting that it was truly an
    emergency situation,
    RoodhOuse did not have the luxury of taking
    a period of time to interview several firms, having had no way of
    knowing that the problem would at least temporarily remedy
    itself.
    Also, Roodhouse asserts it had good reason to hire Layne
    Geosciences, and it should not be penalized for doing so.
    Its
    decision was based on: Layne Western’s familiarity with,
    and
    records on, the wells; Mr. Benton’s belief that Layne Geosciences
    would provide the best services; his knowledge as Roodhouse’s
    water and sewer engineer; his previous experience with Layne
    Western’s geotechnical capability; and his great concern about
    the risk to Roodhouse’s wells,
    a valuable asset.
    Roodhouse also
    points out that it was under intense pressure from the public and
    the Agency to get potable water restored.
    (Pet.
    Br. at 2-4.)
    Roodhouse asserts that it needed Layne Geosciences’
    professional judgment and guidance on regulatory expectations and
    technical scope, because of the unusual situation involved in
    this case as regards both the hydrogeological characteristics and
    the proximity of the UST to the wells.
    Roodhouse relied on the
    knowledge of its personnel,
    its meetings with the Agency, and its
    visits to the well site.
    Roodhouse acknowledges that it probably
    did incur higher than normal travel costs, but argues that there
    was good reason for hiring the firm, that any engineer has to
    travel to the site, and in this case the visits were
    multipurpose,
    i.e., meetings with Roodhouse officials,
    site
    visits, and meetings with Agency representatives.
    The City
    Council meetings were necessary because Layne Geosciences could
    not make the decisions for the City.
    Roodhouse points out that
    the Agency apparently disallowed
    ~fl
    the travel costs of Layne
    Geosciences, including plane fares, meals and car rentals
    “because we felt they were unreasonable”, and it was simply
    unable to explain the discrepancy between the $11,088.
    47 and the
    $11,888.47 figures.
    (Pet.
    Br. at 5.)
    Roodhouse argues that Mr.
    Oakley’s explanation of “unreasonable” goes around full circle.
    (Pet.
    Br. at 5—7.)
    Roodhouse submits that Layne Geosciences could not have
    formulated a corrective action plan without site visits,
    consultations with the Agency, and meetings with City officials.
    0136-0039

    12
    Roodhouse points out that preliminary site investigation would
    normally be reimbursable, at $0.50 per mile travel costs, but one
    of the stated reasons for non—approval in this case is that the
    Agency is dealing with a limited amount of money,
    a reason which
    Roodhouse asserts does not assist in determining whether the site
    investigation is reimbursable.
    Roodhouse disputes the other
    A~~óbJé1àri7~thi?
    the
    distance from the site made the
    engineering firm incur higher than usual expenses.
    Roodhouse
    asserts it had reasons for hiring the firm, that the travel
    distance to Chicago would not have been much less than the
    distance to Kansas City, and that the Agency didn’t put into
    evidence what a reasonable cost would be
    it just kept saying
    that in this case they were unreasonable.
    Roodhouse also
    challenges the “reasonable” basis for the Agency’s not allowing
    any travel costs whatsoever.
    (Pet.
    Br. at
    7,
    13; Pet Reply Br.
    at 1,2.)
    Regarding Mr. Benton and his firm’s interactions with the
    City Council, Roodhouse argues that the planning involved would
    affect the city for many years,
    and that the prior decision
    stages needed in deciding on a course of action were just as
    important as executing it.
    Even if it were legally possible,
    Roodhouse asserts that it would be poor government to simply turn
    over the project to its engineer.
    Roodhouse emphasizes that,
    as
    a municipality subject to the Illinois Open Meetings Act (Ill.
    Rev. Stat.
    1991, ch.102, par.
    41 et seq.), it could not conduct
    its business in private.
    Roodhouse disputes Ms. Lockart’s
    assertion that it was the function of the engineer, not the City,
    to compile the corrective action plan.
    It argues that no
    professional employed by a municipality operates in a vacuum and
    that meetings are necessary.
    (Pet.
    Br. at 8—10.)
    The Agency first states that the corrective action in
    Roodhouse, when completed, will involve remediation of the public
    water supply as well as provision of the alternate water supply,
    and then notes that the reimbursement requested involve costs
    incurred prior to the start of “actual remediation activity”.
    It
    particularly singles out the decision to hire an engineering firm
    from Kansas City.
    The Agency then states that the categories of
    disallowed costs represent unreasonable and non—corrective action
    costs.
    It then argues that the purpose of the Fund should be
    limited in scope to only reimbursement for direct corrective
    action activities, and that an overly expansive definition of
    corrective action and reasonableness threatens to subvert the
    intent and purpose of the Fund”.
    (Agency Br. at 1-3.)
    Regarding the travel costs, the Agency first claims that
    there is a “nexus” between corrective action costs and
    reasonableness,
    citing Paul Rosman v. IEPA, PCB 91—80 (December
    19,
    1991, at 6), where it says “(we
    find that a sufficient nexus
    exists between reasonable costs as articulated in Section
    22.18b(d) (4) (C)
    and cost associated with corrective action.”
    The
    0136-00140

    13
    Agency also argues that while Rosman states that the proceeding
    would be fundamentally unfair if a petitioner were unaware of an
    issue,
    in this case Roodhouse was well aware that such a nexus
    existed. In support, the Agency cites to the Agency’s completed
    invoice voucher form (dated 12/12/91, Agency Rec. at 693
    sent
    with the Agency’s January 21,
    1992 letter.
    The form included a
    ~
    claims that reimbursing such costs are not an efficient and
    effective use of the Fund.
    (Agency Br.
    at 5.)
    The Agency next argues that there are circumstances where
    “certain activities must be considered outside the scope of
    corrective action”.
    (Agency Br. at 6.)
    The Agency asserts that:
    This case is one of first impression.
    Until this point
    the Board has not been faced with a decision in which
    the Agency disallowed certain costs because they were
    not an efficient and effective use of the Fund.
    However, the Fund has never faced the present fiscal
    situation in which requests for reimbursement greatly
    exceed the ability of the Fund to meet those requests.
    This situation mandates the Agency closely scrutinize
    requests for reimbursement.
    (Agency Br. at 6.)
    The Agency argues that these costs are outside the scope of
    corrective action costs and are not costs that “the Fund is best
    suited to reimburse”.
    (Agency Br. at 6.)
    The Agency argues that
    Layne Geosciences’ travel, meeting and preliminary costs were
    “remarkably higher and unreasonable” than other requests received
    by the Agency and request an “incredibly expansive definition of
    corrective action.”9
    As an analogy, the Agency uses as an
    example an instance of high charges for backhoe equipment, where,
    based on Agency experience it could determine what was
    reasonable.
    The Agency concludes that “the
    Fund must be
    preserved in order that it may be used for true corrective action
    purposes”, and that Roodhouse’s costs in Paragraph 5 and
    7 “are
    not true corrective action costs”.
    (Agency Br. at
    6,
    7).
    ~
    The Agency singles out two reimbursement forms that reflect
    hotel room movie charges of $13.90, which Roodhouse concedes should
    not be reimbursed.
    In apparent reference to Mr. Benton’s testimony
    (Tr.
    at
    24-31),
    the Agency asserts
    that Roodhouse newly raised
    Paragraph #2
    (pre-ESDA notification costs) as an issue; Roodhouse
    then stipulated it did not, and noted that it only wanted to point
    out that the Agency’s subtraction was incorrect.
    The Agency also
    pointed
    to
    the
    disallowances
    for
    lack
    of
    receipts
    or
    double
    receipts mentioned at hearing, which Roodhouse does not contest.
    (Pr. 88,
    89; Agency Br. at 2,
    6,
    7; Pet. Reply Br.
    at 2.; Agency
    Rec. Book A, summary at 624—687.)
    0136-00141

    14
    Legal Costs. Paragraph #6.
    Roodhouse argues against the Agency’s basis for its
    disallowance of its legal costs,
    i. e., because the costs are
    legal defense costs and therefore illegal.
    It cites to the
    definition of “legal defense costs”
    at 35
    Iii. Adm. Code
    731.192:
    “Legal defense cost”
    is any expense that an owner or
    operator or provider of financial assurance incurs in
    defending against claims or actions brought,
    By USEPA or the State to require corrective action or
    to recover the costs of corrective action;
    By or on behalf of a third party for bodily injury or
    property damage caused by an accidental release; or
    By any person to enforce the terms of a financial
    assurance mechanism.
    Roodhouse next argues that:
    by definition “corrective
    action” includes alternate water supplies; the Agency approved
    the construction of the 10 inch water line between Roodhouse and
    White Hall; and all of the attorney’s legal costs are related to
    matters not involving legal defense costs.
    Roodhouse disputes
    the Agency’s position of disallowing all legal costs,
    defense or
    otherwise.
    It argues that if the legislature intended to limit
    reimbursement of all legal costs, the word “defense” between
    “legal” and “costs” in the definition of corrective action would
    not be in there.
    (Pet.
    Br. at 10-12.)
    The Agency challenged the use of the regulatory definition
    of legal defense costs for this purpose, asserting that the
    regulatory definition applies only to the financial
    responsibility requirements of Subpart H, and that only the
    language in the definition of “corrective action” in the Act
    quoted
    above) applies.
    (Agency Br.
    at 8.)
    Roodhouse responds
    that the Agency is arguing that “legal defense cost” has one
    meaning in the regulations, but another when used in the statute.
    Roodhouse asserts that,
    to the contrary, the cover page for the
    regulations refers to Leaking Underground Storage Tanks; and the
    legislature added “legal defense costs” to the Act in 1991, and
    presumably was already aware of the pre—existing regulations.
    (Pet. Brief at 11-12; Pet. Reply Br. at 2,
    3.)
    In its arguments,
    the Agency relies only on the term “legal
    defense costs” in the Act,
    (i.e.
    disregarding the specific
    definition of that term in the regulations as irrelevant).
    Without giving an alternative definition, the Agency instead
    argues that the language in the statutory definition of
    corrective action language provides “guidance but does not set
    0136-00142

    15
    the boundaries of the correct definition of legal defense costs”.
    (Agency Br. at 8.)
    The Agency further argues that it is an
    unacceptably expansive view of corrective action to consider
    representation of a municipality as corrective action costs, that
    the Fund was designed for reimbursement of costs directly
    involved in remediation of a site; that other costs should not be
    rèT~iedEo
    as
    iei~ethe~ffecUvenessof the Fund”; and
    that the Board must be guided by the “principals
    (sic)
    of
    reasonableness and effectiveness” in supporting the Agency’s
    position.
    (Agency Br. at 9.)
    Roodhouse responds that the Agency is asking the Board to
    ignore the wording of the Act, that corrective action by
    definition provides for alternative water supplies, and that the
    Agency’s decision, not supported by the facts or law,
    is now
    “grasping at straws” to justify its decision.
    Pet. Reply Br. at
    3,
    4.)
    BOARD DISCUSSION
    Regarding the Paragraph #4 express mail charges, the Board
    finds that Roodhouse failed to present sufficient proof that the
    express mail costs were reasonable expenses.
    We note that the
    Agency did not simply reduce the amount to allowable mail
    charges, or submit other evidence to support its assertion
    regarding the lab samples.
    However, we also note that Roodhouse
    did not argue these points or attempt to justify the mailing
    either.
    The Board will next address what the Agency asserts at one
    point is a case of first impression, particularly as it involves
    Paragraphs
    #
    5 and #7.
    First, the Agency’s reasons for denial in paragraphs #5 and
    7 were identical,
    i.e.
    t)he
    associated costs were not corrective
    action costs.
    In its testimony and brief, although phrased
    differently at various times, the Agency appears to be arguing
    that its consideration of efficient and effective use of the Fund
    is an acceptable basis for denial of reimbursement as
    unreasonable, and, thus,
    costs not involved directly in
    remediation activities are not corrective action costs if the
    sufficiency of the Fund is at risk.
    There appear to be two
    thrusts to the Agency’s argument: that it may limit what is
    corrective action if the sufficiency of the Fund is at risk and
    that it may determine when the sufficiency of the Fund is at
    risk.
    The Board must first emphasize that the Agency is,
    as is the
    Board,
    a creature of statute, and that the Board must first look
    to the statute in assessing the basis for an Agency
    determination.
    The Agency gives no statutory, regulatory or case
    law support for the principle it is espousing.
    01 36-00k3

    16
    The only support cited by the Agency is Rosman.
    The
    Agency’s reliance on Rosman is misplaced.
    The discussion in
    Rosman of the connection between corrective action costs and
    reasonableness arose in conjunction with a claim that the
    Agency’s letter did not meet the requirements of Section 39(a).
    In Rosman, the Agency couched its denial of reimbursement for
    -certa i-n
    costs-
    -as
    not—being-
    reasonable”
    when—i-n—fact—those -costs
    were allegedly not “corrective action” costs.
    The Board held in
    that case that there was a sufficient link between the
    reasonableness and corrective action, so that the Agency’s letter
    was not “fundamentally unfair’! because it gave sufficient notice
    of the reason for denial.
    Here, the Agency’s letter denies reimbursement because the
    costs are not “corrective action”.
    The Agency now apparently
    wants to argue that the costs are not “reasonable”.
    We reject
    the Agency’s argument insofar as it implies that Rosman would
    apply in a reverse situation and also regardless of the facts.
    We point out here that the Agency’s “unreasonable” argument also
    has a novel twist:
    the “nexus” argument here is founded solely on
    the need to make efficient and effective use of the Fund.
    The Act defines what constitutes corrective action and
    specifically lists a number of activities that constitute
    corrective action, and some that do not, as already noted.
    Insofar as the Agency appears to argue that it can supersede the
    statutory listing per se, we disagree.
    (Aurora Metals Division.
    Aurora Industries,
    Inc.
    v.
    IEPA,
    (July
    1,
    1982), PCB 82—12, 47
    PCB 315.
    (See also In the Matter of Execptions from Definitions
    of VOM,
    (July 30,
    1992), R91—24, pp.
    8—9.)
    We also reject any Agency argument that it has some implicit
    authority to either deny or limit reimbursement based on the
    sufficiency of the Fund.
    The statute specifically articulates
    the circumstances under which the sufficiency of the Fund comes
    into play.
    (Ill. Rev.
    Stat.
    1991,
    ch.
    111 1/2, par.
    22.18b(d) (1),
    (d) (2).)
    Section 22.18b(d)(1) addresses a situation where the
    Comptroller shall make payment of amounts a~~roved
    by the Agency
    if sufficient money exists in excess of amounts appropriated “for
    administering the activities of the Agency, the State Fire
    Marshal and the Department of Revenue relative to the Fund.”
    If
    money later becomes available, such payments may be made.
    Section 22.18b(d)(2) states that “(in
    no case shall
    the Fund or the State of Illinois be liable to pay claims or
    requests for costs of corrective action or indemnification if
    money in the Fund is insufficient to meet such claims or
    requests.”
    0136-001414

    17
    The Agency also argues that the Board is now for the first
    time facing a decision as to whether the Agency may disallow
    certain costs as being unreasonable because they are outside the
    scope of corrective action based on efficient and effective use
    of the Fund.
    The Agency asserts that the Fund has never faced
    its present situation where its income is insufficient to meet
    ~
    S~I~n
    22. 18b
    of
    the
    Act includes an articulation of what must be satisfied to be
    eligible for monies from the Fund (Section 22.18b(a), defines the
    limits on Agency payments, e.g.,
    the deductibles
    (Section
    22.18b(b)-(d), and lists what the applicant must submit to
    receive the full or partial claims (Section 22.18b(d)(4)).
    We
    also note that Section 22.18c addresses payment limits not at
    issue here,
    e.g.,
    limits on payments per occurrence
    ($1,000,000)).
    The only place where the word “reasonable” is
    used in this context is in 22. l8b(d) (4) (C), which requires,
    in
    pertinent part that:
    The owner or operator provided an accounting of all
    costs, demonstrated the costs to be reasonable
    and
    provided either proof of payment of such costs or....
    This language does not address the sufficiency of the Fund
    at all and does not give the Agency either a mandate or the
    authority to determine the size of the payment based on the
    “efficient and effective” use of the Fund.
    We also point out that, even if the Agency were to have such
    authority,
    it has given the Board no inkling as to the condition
    of the Fund that would trigger such limitations, or the rules
    under which the Agency would allocate the payment limitations.
    What would be the risk point that would trigger such Agency
    actions?
    How would the cuts be made,
    e.g.,
    on the basis of date
    of application?
    Could the Agency elect to pay 10 cents on the
    dollar?
    While the Agency is authorized under Section 22.18b(f)
    to adopt “reasonable and necessary rules for the administration
    of this Section”, the Agency has not done so.”
    Mr. Oakley
    acknowledged that the Agency uses internal documents not publicly
    available for its determinations.
    The Board concludes that the Act does not allow the Agency
    to determine the scope of corrective action costs based on the
    sufficiency of the Fund and then deny payment because the costs
    10
    We observe that we have previously seen a similar concern
    about
    depletion
    of
    the
    Fund.
    (AKA
    Land.
    Inc.
    v.
    Illinois
    Environmental Protection Agency (March 14, 1991), PCB 90—77, p. 4.)
    11
    Administrative Procedure Act, Ill.Rev.Stat. 1991,
    ch. 127,
    par. 1003.09.
    0136-00145

    18
    are unreasonable because the Fund must be preserved.
    The Agency
    cannot decide who does or does not get paid by shifting the scope
    of what constitutes corrective action depending on the
    availability of monies from the Fund.
    The Agency does not argue that the specific travel_costs
    ith~Cd b~théé
    iñeeiing ~i~~ire
    not cärré~?iveaction
    costs per se as regards the nature of the specific work performed
    or
    the
    expenses
    incurred,
    (as
    it inferred in its example of the
    high backhoe charges).
    Except for some costs not really in
    dispute, the Agency denied Layne Geosciences’ costs in their
    entirety essentially because their total was simply too high and
    would deplete the Fund.
    The Agency on the one hand recognized
    the unusual circumstances, but then argued that the costs were
    beyond the norm of the usual situation.
    The Agency’s explanation
    for refusing to pay travel costs as not being corrective action
    is either inconsistent or unacceptable.
    The Agency never
    explained why the definition of corrective action would not
    include Layne Geosciences activities or pointed out wherein the
    statute denial of payment would be justified.
    On the other hand,
    Roodhouse has persuasively argued that it was justified in
    selecting the firm,
    especially under the unusual circumstances
    found here.
    The Agency participated in the decision to delay
    actual remediation so as to install an alternate water supply,
    the latter project clearly listed in the definition as eligible
    for corrective action.
    Regarding the meetings with the City Council, we again note
    that the Agency did not argue that the specific meeting costs
    incurred by the engineering firms were not corrective action
    costs per se as regards the nature of the specific work performed
    or the expenses incurred.
    In addition to its arguments relative
    to preserving the Fund,
    the Agency essentially argues that
    corrective action does not encompass technical meetings with the
    City Council as decisionmaker, and that such meetings constitutes
    an overly broad view of corrective action.
    Under the facts and
    circumstances of this case, however, we conclude otherwise.
    There was nothing ministerial or routine about the meetings in
    this case,
    and we cannot envision how the complex corrective
    actions could have proceeded without the City Council decisions,
    or how the Council could have made the decisions responsibly,
    decisions involving taxpayers money, without being technically
    and legally informed on an ongoing basis, or how these decisions
    could have been discussed and made other than in an open meeting.
    We conclude that these activities, under the circumstances here,
    constitute corrective action.
    The Board reverses the Agency’s denial of corrective action
    costs in Paragraphs #5 and #7 and, accordingly, reverses the
    Agency’s denial of the associated 15
    handling charges activities
    denied in Paragraph #3.
    01 36-00k6

    19
    Legal costs.
    Paragraph #6.
    The Agency denied these costs on the basis that corrective
    action does not include legal defense costs,
    and in testimony
    asserted that it was legally forbidden to pay Roodhouse’s costs.
    Although at times the
    Agency
    seemed
    to
    be arguing otherwise,
    ~orrectivection—as—den’in’hestatute—express1y~tncIudes
    the provision of alternate water supplies, and the Agency itself
    was involved in the decision to secure alternate water from White
    Hall.
    Also, the Agency does not argue that the specific costs
    incurred were excessive per se.
    Regarding legal costs, the
    definition of corrective action expressly forbids the use of the
    Fund for “legal defense costs”, not “legal costs”.
    The
    definition does not list legal costs as corrective action costs,
    but it does not disallow them either.
    The Agency argues that the Board regulations defining “legal
    defense costs” cited by Roodhouse are not controlling and that
    the statute provides only guidance.
    The Agency does not dispute
    that the definition in the regulations would not apply to
    Roodhouse’s attorney’s activities.
    The problem with the Agency’s
    argument is that it gives no meaning of its own as to ‘what
    constitutes legal defense costs, the basis for its denial.
    To
    the contrary, the Agency in effect has, as a matter of present
    policy,
    stated that it will not pay any legal costs at all, so as
    to preserve the Fund.
    Aside from the “preserving the Fund”
    issue,
    the Agency in effect has defined corrective action as
    excluding
    nfl. legal
    costs, not just legal defense costs.
    However, that is not what the statute says.
    For guidance, the
    Board will take notice of the definition of legal defense costs
    in its own regulations.
    That definition would not include
    Roodhouse’s attorney’s activities.
    We note that the Agency never
    argued that the definition was unacceptable, rather it argued
    that it was not binding.
    In the absence of any other
    enlightenment from the Agency, we find that the Agency erred in
    denying Roodhouse’s legal costs on the basis that they were the
    “legal defense costs” forbidden by the statute.
    This includes
    the denied meeting costs.
    We are not disputing the Agency’s statement that the Fund
    is
    insufficient to cover the reimbursement requests.
    However, in
    that eventuality, the statute has already provided how the costs
    are to be paid.
    If the Agency or others feel that the Fund
    should be allocated differently, and that the Agency should have
    the authority to make this decision, it must seek to ‘amend the
    statute.
    Finally,
    during the course of this proceeding, there were
    certain agreements regarding adjustments in the costs claimed or
    denied and in the 15
    handling charge which we would expect to be
    computed by the Agency in consultation with Roodhouse.
    However,
    there were two inconsistencies identified where the record
    0136-00141

    20
    appears to give
    a clear answer.
    First,
    in the absence of any
    Agency explanation for the discrepancy regarding the $11,088.47
    in Paragraph #5, we reviewed the vouchers and the Agency’s margin
    notes and concluded that they support Roodhouse’s assertion that
    the correct total in Paragraph #5 should be $11,888.47, not
    $11,088.47.A1so,regardingParagraph#2~ we agre
    that_there_is
    iiübtraction error in the corrected amount asserted by the
    Agency in this record.
    This opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter
    ORDER
    In reference to Attachment A of the Illinois Environmental
    Protection Agency’s letter of January 21,
    1992, the Board affirms
    the Agency’s denial in Paragraph #4 and reverses the Agency’s
    denial in Paragraphs #3, #5,
    #6, and #7.
    Consistent
    with
    the
    above
    opinion,
    the
    matter
    is
    remanded
    to
    the
    Agency
    for
    approval
    of
    Roodhouses’
    costs.
    IT
    IS
    SO
    ORDERED.
    Board Member
    B. Forcade dissented.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above o inion and order was
    adopted on the
    /7i~ day of
    ~J~c
    ,
    1992, by a vote of
    L—i.
    0136-00148
    Control Board

    Back to top