ILLINOIS POLLUTION CONTROL BC ~D
    July 9, 1992
    BERNARD MILLER,
    )
    )
    Petitioner.
    )
    V.
    )
    PCB 92-49
    (Underground Storage
    ILLINOIS ENVIRONMENTAL
    )
    Tank Fund)
    PROTECTION AGENCY,
    )
    Respondent.
    BERNARD MILLER and CHARLES MEYER APPEARED ON BEHALF OF
    PETITIONER; and
    JEANNE HEATON and DANIEL P. MERRIMAN APPEARED ON BEHALF OF
    RESPONDENT.
    OPINION AND ORDER OF THE BOARD (by J. Theodore Meyer):
    • This matter is before the Board on a petition for review
    filed March 30, 1992 by petitioner Bernard Miller pursuant to
    Section 22.18b(g) of the Environmental Protection Act (Act).
    (Ill.Rev.Stat. 1991, ch. 111½, par. 1022.18b(g).) Miller seeks
    review of the Illinois Environmental Protection Agency’s (Agency)
    March 5, 1992 partial denial of reimbursement from the
    Underground Storage Tank (UST) Fund. A hearing was held on June
    5, 1992, in Newton, Illinois. No members of the public attended.
    Neither party chose to file a brief, but relied on closing
    arguments.
    There are two major disputes in this case. The first issue
    is whether costs incurred in association with a planned removal
    of USTs are “corrective action” costs and are thus reimbursable
    by the Fund. The second dispute is whether concrete replacement
    costs are reimbursable by the Fund.
    BACKGROUND
    This case involves the removal of TJSTs and corrective action
    at a former service station at 704 West Jourdan, Newton,
    Illinois. (R. A at 17.)! Mr. Miller operated the service
    station with his brother from 1954 until the end of 1988. (Tr.
    at 40-41.) On December 28, 1990, the Millers entered into a
    “R. A” denotes citation to the Agency record, fiscal file,
    “R. B” indicates citation to the Agency record, technical file,
    and “Tr.” denotes citation to the hearing transcript.
    0135-0053

    2
    contract for the sale of the property, and on December 31, 1990,
    applied to the Office of the State Fire Marshal (OSFM) for a
    permit to remove the existing four USTs. (Tr. at 41; R. B at
    61.) The contract required the removal of the tanks. (Tr. •at
    43-44.) On January 3, 1991, OSFM issued a permit for the removal
    of the tanks. (R. B at 61.) The Millers retained Charles Meyer,
    a registered professional engineer with the firm of J.B. Esker &
    Sons, Inc., to assist in the removal process. (Tr. at 14, 44.)
    Preparation for tank removal began on February 6, 1991. A
    crew from J.B. Esker & Sons removed the concrete slab that
    covered three of the four tanks and the vent lines. (R. B at 13;
    Tr. at 16—17.) On February 7, 1991, the vent lines and, fill
    lines were disconnected and the tanks vented by a crew from Petro
    Maintenance, a subcontractor. When a representative from OSFM
    arrived, he noted an odor to the soil which had been removed from
    around the tanks. (Tr. at 23; R. B at 13.) Mr. Meyer testified
    at hearing that the odor smelled like gasoline, and was coming
    from the soil, rather than the venting or cleaning processes.
    (Tr. at 23-24.) Mr. Meyer then notified the Illinois Emergency
    Services and Disaster Agency (ESDA) that there had been a release
    of petroleum. (Tr. at 24; R. B at 2, 13—14.) After ESDA was
    notified, the tanks were removed. (Tr. at 24—25.) Petro
    Maintenance then cleaned the tanks. All four tanks were removed
    on February 7, 1991. The hole was backfilled with soil and sand,
    and the concrete was removed from the site. (Tr. at 25—26.)
    Replacement concrete pads were subsequently poured in August
    1991. (Tr. at 27, 31.)
    Mr. Miller originally sent an application for reimbursement
    from the UST Fund to the Agency on July 22, 1991. That
    application was returned by the Agency due to incompleteness and
    for clarification. (R. A at 1,15.) On August 21, 1991, the
    Agency received Mr. Miller’s amended application for
    reimbursement. (R. A at 16-24.) The invoices submitted in
    support of the claim for reimbursement covered the period from
    February 1, 1991 to August 1, 1991, and the total amount
    requested was $49,961.17. (R. A at 101.) On March 5, 1992, the
    Agency issued its decision, finding that, after deducting the
    applicable $10,000 deductible (R. A at 81—82), $32,229.27 was
    reimbursable. The Agency listed three separate amounts for which
    reimbursement was denied. (R. A at 101-103.) Mr. Miller filed
    his petition for review with the Board on March 30, 1992.
    DISCUSSION
    In his petition for review, Mr. Miller challenged all three
    items for which the Agency denied reimbursement: $3,725.05 for
    an adjustment in tank removal costs; $3080.00 for concrete
    replacement costs; and $926.85 for an adjustment in costs lacking
    supporting documentation. (Pet. at 1—2; R. A at 103.) However,
    testimony at hearing indicates that Mr. Miller and the Agency
    ‘UI 35-005L~

    3
    have reached an agreement on the $926.85 for costs lacking
    documentation. (Tr. at 57, 79.) Therefore, the Board will
    address only the challenged costs for tank removal and concrete
    replacement.
    Tank Removal Costs
    The Agency denied reimbursement of $3,725.05 in tank removal
    costs, stating that the tanks were not removed in response to a
    release, and that therefore the associated costs are not
    corrective action costs. (R. A at 103.), The Agency pointed to
    Section 22.18(e) (1) (C) of the Act, which states in part:
    Corrective action does not include removal of an
    underground storage tank if the tank was removed or
    permitted for removal by the Office of State Fire
    Marshal prior to the owner or operator providing notice
    of a release of petroleum in accordance with applicable
    notice requirements. (Ill.Rev.Stat. 1991, ch. 111½,
    par. 1022.18(e) (1) (C).)
    Mr. Miller argues that the fact that the tank removal was
    planned should not preclude him from applying for reimbursement
    for tank removal costs once a release of petroleum was
    discovered. Mr. Miller notes that the definition of “corrective
    action” was amended by P.A. 87-323, effective September 6, 1991,
    to exclude tank removals where permitted for removal prior to
    discovery of a release. However, Mr. Miller contends that prior
    to September 6, 1991, such a situation would constitute
    “corrective action”, so that his tank removal costs should be
    reimbursed.
    In response, the Agency points out that it is limited to
    reimbursing for expenses that constitute “corrective action”
    under the Act. The Agency notes that OSFM issued a permit for
    the removal of these tanks on January 3, 1991, and that the
    application for reimbursement states that the reason for removal
    was the sale of the property. Therefore, the Agency maintains
    that the tanks were not pulled in response to a release and thus
    the tank removal costs do not constitute corrective action.
    After a review of the record and the arguments of the
    parties, the Board partially reverses the Agency’s determination
    that $3,725.05 in tank removal costs are not reimbursable. TherE
    are two parts to the Agency’s argument that the tank removal
    costs are not corrective action costs. First, the Agency argues
    that Section 22.18(e) (1) (C) of the Act excludes this situation
    from the definition of “corrective action”, because Mr. Miller
    had received a permit from OSFM for removal of tanks before the
    release was discovered. The Agency is correct that Section
    22.18(e) (1) (C), as amended by P.A. 87—323, now specifically
    states that tank removal is not corrective action if the tank is
    0135-0055

    4
    removed or permitted for removal by OSFM prior to notification of
    a release. However, this addition to Section 22.18(e) (1) (C) was
    approved and effective on September 6, 1991, after the disputed
    costs were incurred in February 1991, and after Mr. Miller filed
    his application in summer 1991.2 The Board has previously
    determined that statutory provisions in effect on the date of
    filing of the application for reimbursement are the statutory
    provisions which govern that application. (Pulitzer Community
    Newspapers. Inc. v. Illinois Environmental Protection Agency
    (December 20, 1990), PCB 90—142, slip op. at 4—5.) Therefore,
    the provisions of P.A. 87-323, including the addition to the’
    Section 22.18(e) (1) (C) definition of corrective action, are not
    applicable to Mr. Miller’s application.
    Second, the Agency contends that because the tanks were part
    of a “planned removal” due to the sale of property, the tanks
    were not ‘pulled in response to a release, and therefore the tank
    removal costs are not corrective action. This argument ignores
    the Board’s decision in Enterprise Leasing Co. v. Illinois
    Environmental Protection Agency (April 9, 1992), PCB 91-174.
    ,
    In
    Enterprise Leasing, the Board specifically held that the fact
    that a petitioner had planned to remove tanks does not bar tank
    removal costs from being reimbursed as corrective action costs
    when those activities meet the statutory definition. (Enterprise
    Leasing, slip op. at 5; see also Enterprise Leasing Co. v.
    Illinois Environmental Protection Agency (June 4, 1992), PCB 91-
    174’.) Therefore, the proper inquiry is whether the tank removal
    costs meet the definition of “corrective action”, as that
    definition existed when the application for reimbursement was
    filed, not whether the tank removal, was planned.
    The definition of “corrective action” as it existed when Mr.
    Miller filed his application for reimbursement stated:
    “Corrective action” means an action to stop, minimize,
    eliminate, or clean up a release of petroleum or its
    effects as may be necessary or appropriate to’ protect
    human health and the environment. This includes, but
    is not limited to, release investigation, mitigation of
    fire and safety hazards, tank removal, soil
    remediation, hydrogeological investigations, free
    product removal, ground water rernediation and
    monitorina.
    ~rnogur~
    assessments, the temporary or
    2As noted above, Mr. Miller originally sent his application
    to the Agency on July 22, 1991. That application was returned,
    and Mr. Miller filed an amended application on August 21, 1991.
    In this case, it is immaterial which of these dates constitutes
    the date of filing of the application, because both dates are
    before the September 6, 1991 effective date of P.A. 87—323.
    0135-0056

    5
    permanent relocation of residents and the provision of
    alternate water supplies. (Ill.Rev.Stat. 1989, ch.
    111½, par. 1022.18(e)(1)(C).)
    As the Board noted in Enterprise Leasing, this definition
    presents a two—part test: whether the costs are incurred as a
    result of action to “stop, minimize, eliminate, or clean up a
    release of petroleum”, and whether the costs are the result of
    activities such as tank removal. The Board finds that the tank
    removal costs incurred by Mr. Miller on February 7 (the second
    day of activities at the site) meet both parts of the definition.
    Therefore, the Board finds that the tank removal costs incurred
    on February 7,1991 are reimbursable as corrective action costs.
    However, the costs incurred on February 6, the day before the
    release was discovered, are not corrective action costs and not
    reimbursable. The record indicates that $984 was incurred on
    February 6, 1991. (R. A at 93; Tr. 81—83.) Deducting $984 from
    the $3,725.05 disallowed by the Agency results in $2741.05 in
    reimbursable tank removal costs.
    Concrete Replacement
    The Agency also disallowed $3,080.00 in costs associated
    with the replacement of concrete. The Agency stated in its March
    5, 1992 letter that concrete and asphalt are considered
    “structures”, and that costs associated with the replacement of
    structures are not reimbursable. (R. A at 103~)
    Mr. Miller argues that the Agency’s guidance manual on UST
    cleanups states that costs’ for destruction of structures costing
    less than $10,000 are reimbursable upon certification that the
    removal was necessary to perform remedial action. Mr. Miller
    states that he and his engineer, Mr. Meyer, interpreted this
    provision to mean that the concrete replacement costs would be
    reimbursable since the concrete had to be removed to perform
    remedial action.
    In response, the Agency points to this Board’s previous
    decisions in Platolene 500, Inc. v. Illinois Environmental
    Protection Agency (May 7, 1992), PCB 92—9 and Strubbe v. Illinois
    Environmental Protection Agency (May 21, 1992), PCB 91-105, for
    the proposition that in most cases replacement of concrete is not
    corrective action because it is not an action to minimize, stop,
    eliminate, or clean up a release of petroleum. The Agency
    contends that the evidence shows that the concrete was replaced
    in order to restore the property to its original condition, and
    not incurred as a response to a release.
    After reviewing the record and the arguments of the parties,
    the Board affirms the Agency’s decision that $3,080.00 in
    concrete replacement costs is not corrective •action and therefore
    not reimbursable by the Fund. As we noted in both, Platolene 500
    UI 35-0057

    6
    and Strubbe, the Agency’s guidance manual does clearly allow for
    reimbursement for the dismantling and reassembly of structures,
    and includes concrete or asphalt paving as a structure. However,
    because the Agency did not promulgate the guidance manual
    according to the Illinois Administrative Procedure Act, the
    manual has no legal or regulatory effect in proceedings before
    the Board. The Board must determine whether concrete replacement
    is reimbursable by applying the statutory definition of
    corrective action.
    As the Agency correctly points out, in both Platolene 500
    and Strubbe the Board found that the replacement of concrete
    under most circumstances is not corrective action, because it is
    not an action to stop or minimize a release. However, under
    certain circumstances concrete replacement costs may be proven to
    constitute corrective action costs. The specific facts of each
    case will determine whether concrete replacement is corrective
    action. In this case, the Board finds that Mr. Miller has
    presented no evidence that the concrete replacement was an action
    to stop, minimize, eliminate, or clean up a release of petroleum
    in order to protect human health and the environment. Instead,
    the replacement of the concrete in this case restored the
    facility to its original condition. As the Board stated in
    Platolene 500, “while restoration actions may b.e beneficial to
    the property owner and society, they do not serve to stop or
    minimize the leak or protect human health or the environment.”
    (Platolene 500, slip op. at 7.) Therefore, the Board affirms
    that Agency’s determination that the concrete replacement costs
    are not reimbursable.
    The Board is concerned’ that the Agency’s guidance manual is’
    misleading petitioners to believe that concrete replacement costs
    (as opposed to reassembly costs) are reimbursable as a matter of
    course, when in most cases such costs are not reimbursable. This
    is the fourth case raising this issue that the Board has ruled
    upon in the past two months. (Platolene 500, Inc. v. Illinois
    Environmental Protection Agency (May 7, 1992), PCB 92-9; Strubbe
    v. Illinois Environmental Protection Agency (May 21, 1992), PCB
    91—105; and Warren’s Service v~. Illinois Environmental Protection
    Agency (June 4, 1992), PCB 92-22.)
    CONCLUSION
    In sum, the Board finds that $2,741.05 in tank removal costs
    are corrective action costs and are therefore reimbursable. The
    Board affirms the Agency’s decision that $984.00 in tank removal
    costs incurred on before the release was discovered, and
    $3,080.00 in concrete replacement costs, are not reimbursable.
    This opinion constitutes the Board’s findings, of fact and
    conclusions of law.
    , •
    0135-0058

    7
    ORDER
    The Board hereby reverses the Agency’s March 5, 1992
    determination that $2,741.05 in tank removal costs is not
    reimbursable. The Agency’s determinations that $984.00 in tank
    removal costs incurred before the release was discovered, and
    $3,080.00 in concrete replacement costs are not reimbursable are
    hereby affirmed. This case is remanded to the Agency for
    disbursement of the $2,741.05 amount, consistent with this
    opinion and order. This docket is closed.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act
    (Ill.Rev.Stat. 1991, ch. 111½, par. 1041) provides for the appeal
    of final’ Board orders. The Rules of the Supreme Court of
    Illinois establish filing requirements.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the abo e opinion and order was
    adopted on the
    ~7~t
    day of
    ________________,
    1992, by a vote
    of ~—O
    .
    ‘/
    ~
    ~.•/
    ~.
    /~ ~-
    ~AJ
    ~Dorothy N. Gt~nn, Clerk
    Illinois Pollution Control Board
    0135-0059

    Back to top