ILLINOIS POLLUTION CONTROL BOARD
    December 17,
    1992
    COMMONWEALTH EDISON CO.
    )
    (Dresden Generating Station),
    )
    Petitioner,
    )
    v.
    )
    PCB 92—181
    (Provisional Variance)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    ORDER OF THE BOARD
    (by J.
    C. Marlin):
    This matter comes before the Board on receipt of a Motion to
    File Certificate of Acceptance Instanter filed by Commonwealth
    Edison Co. on December 4,
    1992.
    The Board has not received an
    Agency response.
    The Board granted Commonwealth Edison a provisional variance
    on November 19,
    1992 upon the November 18,
    1992 receipt of an
    Agency recommendation.
    That order required Commonwealth Edison
    to complete and file a Certificate of Acceptance within 10 days
    (by November 30,
    1992 because November 29 was a Sunday).
    The
    motion to file states that Commonwealth Edison did not timely
    file the Certificate’ because it did receive a copy, of the Board’s
    order.
    The Board hereby grants Commonwealth Edison’s motion to file
    instanter.
    We are aware that for reasons we have not yet
    identified,
    a few persons did not timely receive copies of orders
    issued during our November 19,
    1992 meeting.
    IT IS SO ORDERED.
    I, Dorothy M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, do hereby certify that the above order was adopted by the
    Board on the
    /f~
    day of ____________________________,
    1992,
    by a vote of
    7—c
    ~,
    Dorothy N. 9~n, Clerk
    Illinois Po~J&itionControl Board
    0138-0159

    Back to top