1. December 17, 1992
      2. an Illinois Corporation,
      3. Petitioner,
      4. 2. $31,350.06, for an adjustment in non—corrective action
      5. DISCUSSION
      6. A. If the concrete had not been replaced, there would be a
      7. The Agency denied reimbursement of $17,746.00 in insurance
      8. that?
    1. omissions and pollution lability.
      1. Tr. at 384, 385.
      2. Mr. Schneider explained how MET prorated its overhead coststo this project.
      3. (sic) portion.
      4. Tr• at 381, 382
      5. the charges for insurance coverage.
      6. used by 5171 but maintains that
      7. the rates are consistent with loaded rates.

ILLINOIS POLLUTION
CONTROL BOARD
December 17, 1992
SOUTHERN FOOD
PAR1~, INC.,
an Illinois Corporation,
Petitioner,
v.
PCB
92—88
(Underground
Storage
ILLINOIS
ENVIRONMENTAL
)
Tank Reimbursement)
PROTECTION AGENCY,
)
)
Respondent.
EDWARD DWYER AND KAmERINE
HODGE, RODGE
& DWYER, APPEARED ON
BEHALF
OF
PETITIONER;
DANIEL MERRIMAN AND
JAMES
RICHARDSON APPEARED
ON
BEHALF
OF THE
ILLINOIS ENVIRONMENTAL PROTECTION AGENCY.
OPINION AND
ORDER
OP THE
BOARD (by B. Porcade)
:•
On June 11, 1992, Southern Food
Park,
Inc.,
(EPPI)
filed a
petition for review of an
Underground
Storage ~ank
Reimbursement
Determination for
its facility located at 700 W..t Main, Benton,
Franklin
County, Illinois.
The
petition for reviów
was
filed
pursuant to 22. 18b(g) of
the Environmental Protection Act
(Act).
(Ill. Rev. Stat. 1991, ch. 111 1/2 par. 3022..1*b(g).)
Hearings were held in Benton, Illinois on
October
6 end
7
1992
No members of the
public
were
prss.nt~at..the
hearing..
SFPI
filed
its final
brief
on
November
10,1992
The
Illinois
Environmental Protection Agency (Agency)
filed it. final
brief
on
November 30, 1992, along with a motion tofu. tb.
final
brief
instanter. In a December 3, 1992
order, the Board. granted
the
motion to file the
Agency’s
brief
instanter.
BACKGROUND
Man—Dee Mart, a
division of
Southern Food
Park,
Inc., owns
and
operates the
Han-Dee
Mart
convenience
store and
service
station
in
Benton,
Illinois.
A release
of
petroleum
from the
piping between two 1,000 gallon tanks occurred on or before June
21, 1989
SFPI
contracted with the engineering
consulting firm
of )Iassac
Environmental
Technologies (MET) to rem.diat. the site.
MET
submitted
an application for reimbursement from the
Underground Storage
Tank Fund
to
the
Agency on
behalf
of
SFPI.
The
Agency, in reviewing SFPI’s submission of invoices
covering the
period
from
June
23, 1989 to
May
20, 1991, denied
reimbursement of eight cost
items. SPPI
is appealing
the
Agency’s denial of reimbursement of the following costs as. listed
in the Agency’s letter of May 14, 1992:
0138-0069

2
1. $22,500.00, for costs associated with
the
replacement
of concrete and/or asphalt. These
costs are
not
corrective action costs.
2. $31,350.06, for an adjustment in non—corrective action
costs. The
associated
costs
are
not
corrective action.
ccc
4. $17,460.00, for an
adjustment
in
ineligible
insurance
charges.
The
associated charges
are
not
corrective
action.
5. $6,132.53, for an
idjustm.nt
in costs
lacking
____
supporting documentation. The owner
failed to provide
demonstration that
these
:
costs were reasonable
as
submitted.
Rec.
Al
at81,82.’
The Act allows for
reimbursement from
the
fund ~for costs of
corrective action or
indemnification.”
(Bction
22.1$b(a).)
Corrective action
is
defined
in
Section
22.10(e) (1) (C) of
the
Act
as:
•..sn action to stop,
minimize, clii mats, or
clean
up
a release of
petroleum :or
iti
effects as may be
necessary or appropriate to protect
h”~’i
health and
the
environment. This includes -but 1 ~mot
.
limited to,
release investigation, mitigation of f~.~èndlafity
hazards, tank
removal,
soil r.a.diation,,
hydrogeological investigations, free prod~ict*~va1
and groundwater
remediation and monitoring, ~xpo.ur.
assessments,
the temporary
or p.raaniñt~eloaation
of
residents
and
the provision of
altsrMti~atr’
supplies.
The definition of corrective action presents a
two part test:
whether the costs are
incurred
as a result of an
action
to “stop,
minimize,
eliminate, or
clean up a
release
of
petroleum
or
its
effects”
and whether
the costs
are
the
result -of such activities
as release investigation, tank
removal,
soil -~.diation,
•tc.
(See Enterprise
Imasinp
v.
IEPA (June
4, 1992), P~ 91—174.)
Section 22.18b(d) (4) specif i.e the requirements for a claim
for reimbursement from the
fund.
One
requirement
of -the claim
1
References to the
Agency
record will be cited as Rec. Al
and
Rec. al where Al references
Part
1, Book A
of the fiscal file
and
81 references Part 1, Book B of the fiscal file.
The
transcript
will be referenced as Tr.
0138-0070

3
f
or reimbursement
is that:
The
owner
or operator provided
an accounting
of all
costs, demonstrated the costs to be
reasonabl.
and
provided either
proof
of
payment
of such costs or
demonstrated
the
financial need
for
joint
payment
to
the owner
or
operator and the oimer’ a or
operator’s
contractor
in order to
pay
such costs.
Section
22.iSb(d) (4) (C).
DISCUSSION
Replacement of Concrete
Prior to discussing the arguments presented
in this case the
Board
notes
its
prior holdings
concerning
the
reimbursement of
the
costs for replacement of concrete. ‘In
PlatOlens
500.
Inc. v~.
~
(May 7, 1992), PCB 92—9, ___PCB
,~theoard held
that in
most
cases
the replacement of
oancret~I~ót~irrectiv. action
and
is not
reimbursable.
(Se.
also ~
~(Kay
21,
-
1992),
PCB
91—105, PCB, Warren’s Service
v.-I~~Jufle
4, 1992),
PCB 92—22, _PCB
and Bernard
Miller (July
9, 1992),
PCB
92—
‘49, _PCB_,
Ma~ETn
Oil Marketina
#64 v. ~EPA
(August
13,
1992), PCB 92—53,
_PCB____
SPPI
recognizes
the
prior Board decLaiMs ,thding the
replacement of concrete is
not
corrective action ‘rand
therefor. is
not reimbursable.
However, SFPI argues that the Board’s holding
was
limited to
the
particular
facts in .a~
ai*
eM
that the
Board noted
that under some circumstances ~~*~plaasnt
of
concrete
may
be reimbursable. BFPI
cont~i’~tthe
hgsncy
sisapplied the
Board’s
findings on the x~1*Ld~:~ntfor
the
replacement of. concrete by applying a
itrie’it
that the
replacement of concrete is not
reimbursable
SFPI
argues
that
based
on the
facts
or
thts ci..
that the
replacement of concrete at this
particular site ~s
Corrective
action. Larry Schneider of
~METtestified thit
~
remains even if the
soil objective i.
satisfied.
,
(Tr.
at
342.)
Be
further
noted that at this
particular site
the contamination
extended
under a
public roadway and as is o~sE~practice tb.e
area under
the
rOad
was not excavated. (Tr.~1t 343
~) ~
wall.
where
the
contamination did exist were lined
with high
density
polyethylene membrane (HDP) and
the seams where the sheets ~et•
were
joined with
special tap.. (Tr.
at 344.)
~e
.xplzinsd ‘how
the concrete serves to minimize
the
effects
of a release
as
follows:
A.
If
the concrete had not been replaced, there would be a
greater
likelihood that
water
would come in contact.
Whatever the, source of that water
from
either runoff
above
grade
or from rainfall would have, come in contact
0138-00.71

4
with constituents of concerns still present either
along the perimeter of the
property
or within the
boundaries of
the
base
of
the property,
and
it’s a
possibility that
those
would be
picked
up in solute
with the water, moved into
other areas that
currently
have not
experienced
contamination. He
argues
that the
concrete reduces
the likelihood that
water will enter
the contaminated area
and move contamination
into
groundwater
or areas
which
were not
previously
contaminated.
Q. How would
the
replacement of
the concrete
minimize
the
affects (sic) of
that release and the
remaining
contamination?
A. The concrete would
have
significantly
— —
does
significantly
reduce
the impact because
it
catches the
water before it can filter into the
soil and
moves
down
into ‘the storm
drain
system and
-carries
it
away, end
therefore that water
doesn’t impaCt
or pick up
any
of
the
constituents
that
were still at the site.
Tr.
‘at
345’.
SPPI argues
that
the Agency, in reviewing the
application,
did not perform a site-specific review but
a~pliSdan inflexible
policy
in determining the
reimbursibility of. concrete
replacement. SPPI argues
that the replacea.~t
of
~ancrete at
this
site was corrective
action because the concrete ainiaized
the effect of the release by providing a barrisr~bstwesn
surf
ace
water
and
contamination.
SFPI further argues. that
the Agency did
not present• any testimony to rebut SPPI’
$ contention
-
that,
the
concrete
served as a
barrier.
The
Agency
argues that the language
of
the
itatute controls
the
determination of what is reimbursable. The Agency
contends
that a site specific review was performed. (Tr. at 216.) The
Agency contends that even if the Agency
did not use ~the
proper
method in reaching its determination, it
does not
alter
the
reimbursement determination.
The Agency asserts that
it i.
the
reimbursement determination
that
is at
issue
.before the Board
and
not the Agency’s method of reviewing
reimbursement claims.
The Agency con$*nda
that based
on
the faCts
of
this case,
SPPI has
not shown
ti*~
replacement of
concrete
at the
site
was
corrective
act
~~n.’ The
Agency
motes
that the
resaining
contaminants wexe already off—site and were
separated from
the
excavation site by
the HDP. The
Agency also contends that
concrete is subject to cracks, raising the question of the
effectiveness of the concrete to act as a
barrier.
The Agency
also notes that groundwater presented
rio
problem or concern
during the excavation. ‘(Tr. at 410.)
The
Agency also content
0138-0072’

5
that the ‘use of concrete in
this situation does not differ
tr~
most
other sites.
The Agency
contends
that the, main
purpose in
replacing the concrete was to enable SPPI to continue operation
as a gasoline station. The
Agency
notes
that the ‘consultant to
SFPI testified that concrete was replaced for restoration’
purposes. (Tr. at
393, 394, 399.)
While
the
Board
has
previously held
that under
sone
circumstances it
may
be shown
that
the
replaoesr~t
of
concrete
constitutes corrective action,
the Board find. that the
circumstances of
this
case do not support
a
finding
of
corrective action.
The
facts
.
surrounding the r.plao.a-nt
of
the
concrete at this site present no unusuaIc1&c~tances ~aM the
concrete was
essentially
replaced for restoration purposes.
In Platolene, the Board discussed the
difference between
corrective action and restoration.
In
the process
of removing u~rgrei’’
~*thrage
tanks and
subsequent
resediation of the
sits there are
a variety of tasks to be
performed.
~o.s
of the
functions can
clearly be classified as jther
corrective action or restoration.
Ce.
Under
the
facts
of this case,
sctLons~that
occurred
prior to
backfiliing
the
excslitien wits
would
be
considered
as corrective
action end
e ‘setions
which occurred after
backfilling wou1d~søonsider.d
restoration.
The Board further noted
that thes. general ~!uIU~tI1
mel
universally apply to
all
factual situatLcm.~I”
that‘the
particular facts surrounding the
action and
~ ~po.e
of the
action will ultimately
determine ,wbethsr ~* ~ttt~d*r
‘action is
corrective action or restoration.
(Vj~~~
ta~y
‘7-, ‘3992), PCB
92—9.)
SFPI ‘s analyBis on
how
the replacement of ‘Ocncrete is
corrective
action would apply to
most rea.diatien sites.
It is
common
for
some level
of
contamination to zemain’la
*he soil -even
after
remediation is
performed.
Th.
amount
of
Contamination
remaining
in
the area required
the use of ~P to I.O1St.,-*he
contaminated
area under the
roadway from -the ar.*.~øf.th..arvio.
station
where
the
contaminated
soil
had been ‘remov~I~*aplaced
with
backfill.
The layer of
BDP material used *t
this sits
already
served the
purpose
of
isolating the ‘contaminated areas
and minimizing the
transport
of
contaminants
through
the
flow
of
water. The bottom and sides of
the
excavation pit
were lined
with high density polyethylene
and
the concrete
yea
placed
atop
the backfill in the excavation
pit.
While the concrete
say
create a
cap to prevent water from
entering
the soil end
transporting contaminants, the
Board finds that given
the type
of
OI38O~~3

6
remediation done at
this site, any effect of
the
concrete as a
barrier,
is minimal. The
Board further
notes
that
the area of
high contamination was off—site under the
roadway and
the area
under the concrete satisfied
the
clean—up objectives.
The
concrete that was replaced in this
matter created
a
cap above the
area that was backfilled with unconta*inat.d
sOil and isolated
from
the remaining
contamination by
a layer of 1W?.
The
Board
believes
that in
this
case,
the main
intent
of
replacing
the
concrete at
the
sits
was
to
restore the area’ to
its
previous condition in order to
continue
.
operation as a gas
station
At the
time
that
the concrete was laid, the clean up
objectives at the site had been meet. •tbe C~ste
‘~
did
wotatop,
minimize,
eliminate or
clean up a
release of
petroleum or. its
effects.
The amount
of
contamination
at
the
site wa. the
same
before
and
after the concrete was
installed.
‘In addition, SFPI argues
that
the
doctrine
of
.stoppel
is
applicable to this
matter
Mr
.
chnsid.r, :~s ~smsultant,
testified
that
the replacement of concrete ~s;emiabers.d
-
in
other projects in
which
he
has been a consultant.
.-~(~.i*t338,.)
Re
further stated
that
the replacement of concrete
iia$áncluded
in the corrective action
plan
approved by the Aqency.i4Tr.
at
334.) He also contends that at no
time
did the Agency represent
to him that it was.
improper
or
unacceptable,to replace
the
concrete. (Tr. at 348.)
SFPI
argues
that. th.,*gancy..oannot
ignore the
ongoing
ccuunications
relatioi*.hip between the Agency
and
the
applicant
where
the
applicant sought the.
royal
at
every step of the rea.diation from the Agency end~me1i.d~on
the
Agency’s
consent
in
carrying out
corrective action measures.
SYPI
also notes
that the Board baa expresaed’~ite~omoern~over’
the
Guidance Manual misleading the public. (B.rnard~a4
li5~ VA~1IPA
(July
9, 1992),
PCB
92—49.)
SPPI
further arges$~hat the
appellate court held that
there
is a Jine of
~~eees-bol4ingthat
even
though ,a rule
is
improperly promulgated,
-it-mmy:be
binding
upon
the governmental agency. (Wynn v.
Color
(4th Dist. 1987),
159 Ill.App.3d 719, 512 N.E.2d 1066.) The
elements
of
proof are
demonstrating the NuserN relied on
the manual to
his or
‘her
detriment and
that there was no notice of a
change in policy, or
custom. (Wynn at 724—725.)
The
Agency argues
that
as a
general rule principles
of
equitable estoppel
do
not normally apply.
against govsziasnt but
may be ‘pplied
to the
government
only in rare :‘snd
UnUU*1
circumstance
to prevent fraud or
gross injustice. (Dean Foods Co.
v. PCB
(2nt~
Dist. 1986), 143 ill.
App.
3d
322,492 N.E. 1344)
‘The Agency
does
not find any special
circumstances
that
would
invoke the doctrine of estoppel in
this matter.
The Agency
asserts that
the Board has previously held
that
the acceptance of
a corrective action plan cannot be
construed
as approval for
reimbursement. (Martin Oil liarketina #64
v.
IEPA (August 13,
1992), PCB ‘92-53.) The Agency
further
contends that
SPPI’s
DI 38-OO7I~

7
interpretation of the Guidance Manual
is in
error
and
notes
that
the
Board
has previously held that the manual
has
no
legal or
regulatory
effect and will not be considered by the
Board. The
Agency
further
argues that even if estappel was applicable, SF71
has not
shown
detrimental reliance, a
necessary element
of
estoppe..
The
Board
has previously refused to allow
reimbursement
under
an eatoppel
theory
argument. The Board held
that ~al3.owing
for reimbursement which is not
a correctiv, action
would be in
violation of the statute.”
(Strube
(Kay 21,.
1992) PCB 91—205.)
The Board
does
not find
any unusual facts in this
matter that
would warrant the
use
of
satoppel
to prevent tr*nd and gross
injustice.
The
Board
does
not
find that ‘SF71 ~reliad
on
the
manual to its detriment,
there
is no
indication
that the concrete
would not have
been
replaced if
SF71 bad known reimbursement
would not have been
allowed. Further,
the Board does
not
recognize the manual
as a rule and has
not interpreted
the
language
of the manual. (Strube
(May
31, 1992) ~PCB 91—305.) In
Martin
Oil (August 13, 1992) PCB
92-53, the
bard held that the
approval of a corrective action plan
.
osn,iot be construed as an
approval
for reimbursement.
The
Board
finds
that
estoppel is
not
applicable in this case
and
even if
estcppel were
applicable.
SFPI has not proven
the
elements of
estcçpsl.
The Board finds that the cost of the
replacement
of
concrete
is this matter is
nOt reimbursable
because
the replacement of
concrete has not been shown .‘to be a
corrective
action
The Board
affirms the Agency’s denial of
reimburs~nt.
Renlacément of
Tank
System
The
$31,350
06 is
comprised
of costs for parts ‘and .quip.snt
associated with
reinstalling
the tank system. The costs denied
reimbursement
include testing of
the
system (pressure,
tightness
and proctor density testing), parts for the
electrical
system
and
piping for the
tank
system.
The leak
at this site was from the associated piping feeding
into one of the
underground tanks.
SFPI contends that to remove
the
contaminated
soil,
it
was necessary to
r~~vethe
‘storage
tanks, the associated piping and the electrical system.
SF71
asserts
that in removing the
tanks,
the associated piping and
the
electrical system, it was
necessary
to cut so.. parts asking them
unusable for reassembly. SF71
contends
that sound engineering
practice requires
that certain parts such as piping and
electrical
items be
replaced with new parts.,
instead
of reusing
old parts. SF71 also contends that the
system
testing was
required
for
recertification of the tank
system and
necessary
for
proper installation.
SF71 argues
that
the
removal of the
tank
system was required to remediate the
contaminated
soil. Because
the removal was required for remediation, SF71
argues
that the
0136-0075

8
removal and the
replacement satisfy
the
definition of
corrective
action. SFPI further
notes that the
reassembly
of parts was not
practical in
this matter.
SF71 argues that the
Agency made
its
determination
by
applying the standard as
described
in the
Guidance Manual which
draws a distinction
between reassembly and replacement.
SF71
notes that
the
appropriate
standard is for the Agency to
determine if the action is a
corrective
action end not base
its
determination on
“replacement” or “reassembly”.
BPPI argues
that
the
tank
system was not “upgraded” in
that
the sane type of parts
and
equipment
were installed. SF71 argUes
that sound engineering
practice required the replacement of parts nd the
testing
of
the
system. SF71
further contends that these actions wsr. necessary
for
public
health
and
safety.
The Agency
argues that
the costs associated with
replacing
the tank system were not
corrective action bet ~re costs
associated with upgrading and
replacing th ‘~nkeystem.
Agency contends that
these casts
were incurred 1n-retu~ning
the
station to operating condition and ‘were not -dit,~,ly
related
to
remediation of the
site.
The Agency as*erts~~ttbse
activities do not satisfy
the definition
of
corrective action
because these
are not
actions
to stop,
ai,4aiSS,’~s1iainate
or
clean up a release of
petroleum
or
its affe~ts.
Reimbursement was
allowed
for the coste:’assoCLated with
the
removal of the storage tanki and
the
‘rain
Ws.U~nt~fthes. costs
are. ‘not at
issue on
appeal.
There
is no
oo~t**tton~that‘the
removal of
the tanks
was
not necessary to
r~iate the
aite.
The Board does not
find
a relationship ~bs~
~~lao~nt
of
the
tanks
and corrective action related to a release. The
replacement of the tanks
is only necessary IfIPPI intends
to
càntinue operation as a service station. ~
*atiOns *elated to
reinstalling
the
system
do
not
function to
~
limbs.,
eliminate or clean up a release
of
petroleum ~r its ffscts.
• While SF71 may have followed sound engineering praCtices in
reinstalling the system, these
practices
do not
serve
to prevent
or minimize the
effects of
the detected relsale. ‘The replacement
of the tanks
was
restoration.
At
the time that the tanks were
being replaced, the contaminated soil
had
been replaced
at
the
site, remediation
of the area
had been o~leted.
The Board does
not find
that t”~ costs ssociated
with
the
replacement of
the tank system
in this case are a
corrective
action. The
Board
affirms
the Agency’s denial of reimbursement
of the
costs associated with
the replacement of
the
tanks.
Insurance Costs
The Agency denied reimbursement of $17,746.00 in insurance
coverage as non—correctIve action. This
figure
is comprised of
0138-0076

9
two separate insurance charges: $11,760.00 for MET
general
liability and
$5,700.00’
for Southern Illinois Petroleum
Maintenance Company
comprehensive and
automotive. 5171
is
only
appealing
the denial of
the
$11,760.00 for MET general liability.
This charge was originally included
as part of
overhead.
The
insurance charge was later broken out of
the overhead and
submitted to the Agency on MET
letterhead
stating the insurance
charge
for insurance coverage from 6/23/89 to
5/20/91.
(P.c.
El
at 238.)
$171 maintains
that while the
denial
letter
states that the
insurance
coverage is not
reimbursable because
it is
not
corrective action, the Agency pursued a
different t.ason
for
denial at hearing. SF71
contends that th agency denied
reimbursement
based on
the form in which
the charges
were
submitted to the Agency. SF71
note. that the Agency
did
not
request
additional
documentation
on the insurance
charges. SPPI
contends that documentation of
the charges
~as available and
Mould have
been provided to the
Agency upon request. (Tr.
at
386.)
The
Agency argues that due to the
form
of
~thS
‘submission of
the
insurance charges it is impossible to
d~teraine the type
of
insurance, the
type
of coverage and
whether
it
-was related to
this site, therefore without
the
proper ~ó~~i~ttion
it is
impossible to determine if
it is
correctivs~lbtion. The
Agency
notes that the
document declaring
the insurance’
charge does not
indicate the names of
the insurers,
the names of the insured,
the
nature of the coverage,
the
level of ooverage,~betype of
policy
or policies involved or the relationship
b~’
sit. and
the
insurance.
The
Agency
also argues
~tbatno~WoOf
‘of
payment vas
provided.
The
Agency
also argues
that the ~ObIt at imsuraflc.
coverage fails to meet the definition of
co~*eativeaction.
Mr.
Schneider described
the
insurance coverage as
follows:
Q.
The insurance, the $11,760, what kind
of
insurance was
that?
A.
We
carry general liability,
we carry errors and
omissions and pollution lability.
Q. The
commercial
general liability
policy carries
the
pollution exclusion that’s
standard in
the industry and
so that’s
why
you have the
pollution liability?
A.
That’s not the reason we
have pollution liability. We
carry
the pollution liability
because
its necessary to
do business in some states,
and
it’C also
good
business, good prudent business practice to carry it.
Tr. at 384, 385.
0138-0077

10
The
insurance was general coverage that MET maintains
for all
projects in
the
general course of doing
business.
There is no
evidence
that this insurance was obtained for this
particular
site.
The
cost of the insurance is an
overhead expense for NET.
Mr. Schneider explained how MET prorated its overhead costs
to this project.
A.
The
amount
was an average
monthly
cost
that were
(sic)
attributed not only to this job
but
to several other
projects.
This
was the
portion
that this project took.
Q.
I guess I’m interested in how you actually made
that a
(sic) portion.
A. Took the total costs over a year,
divided it by 12.
Q. That’s monthly, and then what?
A.
And
then took
the
months in
terms
Of
project, in which
this client was involved in that project, and applied
it against it as a multiple against
the number
of
months.
Q.
So
if you had three jobs going
ma given
month,
then
you would
take
a third of that
monthly overhead?
Is
that——
A. Well, it wasn’t done
so
much
in a given month but over
a
period it
was
determined
it
wasn’t equally portioned.
It was
also
dependent
upon
th. size of the project,
would have been unfair for a
small project to ogepare
to
the same
— —
Tr•
at 381, 382
Mr. Stellar of the
Agency,
testified
that
site—specific
insurance would be reimbursable if it
was
documented,
reasonable
and
a corrective action. (Tr. at 148.) However, the
testimony
and billing documentation do not
support
a
finding that the,
insurance
was site-specific.
The
issue of whether insurance
charges
represent a
reimbursable óost
is not before the
Board
The
method
of prorating the
overhead
costs is also
not
at issue’
before the
Board. The
issue before
the
Board is
whether
the
documentation of ~he insurance charges support a finding
of a
corrective
action and
whether
the documentation
shows
thos
costs
•to be reasonable.
The
Board finds
that
it
is
impossible
to
determine whether the insurance coverage was a corrective action
or reasonable based
on the documentation provided.
The
documentation does not describe
the
type
of insurance, the
insurer or the insured.
0138-0076

11,
The ‘Board affirms
the Agency’s denial of reimbursement of
the charges for insurance coverage.
Undocumented Costs
Of the $6,132.53 of
undocumented costs,
SIPI
is only
appealing
the denial of $4,032.03 in costs. Tb.
amount appealed
is comprised of $1050.00 for telephone calls,
$660.00 for
telephone and fax service, $1,125.00 for
secretarial services,
$357.03 for office supplies and $840.00 for maintenance
coverage.
These charges were originally submitted an I*PA
subcontractor
forms and were included in the
amount
of $14,130
66 under
eadainistrative and
overhead
costs~. (Rec. $1 ‘~t3.) The Agency
requested a breakdown of
these costs. MET
submitted ‘a breakdown
of these
costs
into five
line
items (Manifest, Ped-ex,
UPS,
Overhead
and Profit). (Rec. Al at 55.) A
further breakdown
of
the overhead charge was provided by
listing each
charge
separately on MET letterhead.
‘(Rec.
El a~
23.7,~239
241.) ‘These
items
were prorated by MET from yearly business ~n.es
in the
same
manner
as
the
insurance charges.
SPPI argues that the Agency required that these items be
broken out of
overhead
but
did not request supporting
documentation.
In addition 8171 contends
that.
the Agency’s
denial of
these
costs were based on the erroneous
assumption that
the
hourly rates used by 8171 were
loaded rates
(i... includes
overhead and expenses).
SPPI argues
that the Agency
‘would
have
reimbursed these
costs
if
the items
had beenincluded
in the
professional service rate
SYPI further argues
that
the
additional documentation was available and
would
have been
submitted to the Agency, if requested.
The
Agency contends
that the
items were
submitted to the
Agency as direct costs
The
Agency argues that there ‘was no
support ing documentation tying the
costs
specifically to
the
site
in question,
and
thus no
substantiation
that they
represent
corrective action or are reasonable.
The
Agency determined that
the rates used by
8171
were
loaded by comparing
them
with billings
from other sites
throughout the state. (Tr. at 63.) Doug Oakley, ‘~fromthe Agency,
testified that most
submittals use loaded rates and that
the
Agency prefers to
deal with
loaded rates. (Tr.
st 63.) :‘Me
further
testified that an unloaded rate for a
t.~itici.nwould be
around $15 an hour. (Tr. at 63.) Mr
Schneider testified that
the hourly rate includes the
compensation to.
the
employee,
the
benefits to the employee,
and
matching PICA and unemployment
involvement through the employee. (Tr. at 376.) Mr
Schneider
contends that
the rates are not loaded and that if the overhead
expenses were averaged
into the hourly rates, the rate would be
within the Agency’s acceptable rates. (Tr~at 377.)
The Agency
does not contest
the hourly rates
0I38~oo79
used by 5171 but maintains that

12
the rates are consistent with loaded rates.
In its )Iay 14,
1992 letter to SF71
reviewing
the
claim,
the
Agency adjusted the
amount
reimbursed to SF71 to reflect a
deduction in the amount
of handling
charges. (Rec.
Al at 81.)
The Agency adjusted the
‘handling charges
to 15,
the rate
considered reasonable by
the Agency.2 (Tr.
at 46.)
The Agency’s request for a breakdown of
overhead and
administration costs was reasonable
considering
the
am,unts
involved and
the
related
charges. Tb. Board
finds
that the
Agency’s determination
was reasonable
that
the
rates used by
SF71
were loaded, based on the testimony of Agen~cy
personnel
concerning similar billings.
The costs at issue could have been
averaged into
several other cost items without .zc..ding
the
allowable
amount
As a result of the cost breakdown, the items
were presented to the
Agency
as
direct costs. ‘Therefore
it was
reasonable for
the Agency
to
require .uppcrtthg4oaua.ntation
to
verify the costs and to conclude
that vithout’auffici.nt
documentation the costs were
not
reimbursable.
-
The Board finds that the costs as
submitted lacked
supporting documentation.
The costs, were submitted on”IIET
letterhead stating the general
category,
the
ti.
period and
the
cost.
The
record provides no
proof’
that these items were
actually billed to MET,
there
is also
no
description
of
the type
of services provided or
the relationship to thep.cific
site.
There is also no
supporting
.docuaentation On
the method used to
prorate these
expenses
to
this
project.
-
The’3Osrd affirms the
Agency’s denial of reimbursement for
these costs for lacking
supporting~documentation.
This opinion constitutes the
Board’s
finding
of
tact’ and
conclusion of law -in this
matter.
ORDER
The Board affirms
the Agency denial of reimbursement of
costs associated with
the replacement of
concrete,,
the
reinstallation of ‘the tank system, insurance coverage
and
undocumented
costs.
IT IS SO
ORDERED.
2
P.A. 87—1171, effective September 18, 1992,
established
maximum amounts for handling charges
eligible for payment from
the
fund.
The maximum allowable
amount
is based on a percentage of the
subcontract or field purchase cost. The
maximum
percentage is 12,
where purchase costs are less
than
$5,000.
o
I 38-0090

13
Section 41 of
the Environmental Protection Act (Ill.
Rev.Stat.
1991, ch. 111 1/2, par
1041) provides for
appeal
of
final orders of the Board within 35 days.
The
Rules
of the
Supreme Court
of Illinois establish filing requirements.
(But see
also
35 Ill. Ads. Code 101.246,
Motions for Reconsideration, and
Castenada v. Illinois
Human
Rights Commission (1989), 132
lU.
3d
304, 547 NE.2d 437)
I, Dorothy M.
Gunn,
Clerk of
the Illinois Pollution Control
Board, hereby cer~4~y..that the
ye opinion and
order
was
adopted on the
/7~
day of
,
3992,.by a
vote of 7—c~2
Ill~
~A.
Control
L~
Board
0138 -008.1

Back to top