ILLINOIS POLLUTION CONTROL BOARD
    March 25,
    1993
    INDIAN REFINING LIMITED
    )
    PARTNERSHIP and INDIAN REFINING
    )
    COMPANY,
    Petitioner,
    v.
    )
    PCB 91—84
    )
    (Permit Appeal)
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD
    (by R. C. Flemal):
    On February 4,
    1992,
    the Board ordered the parties to file
    status reports to be received on or before March 16,
    1993.
    The
    petitioner filed its status report on March 16,
    1993.
    Respondent
    filed its status report on March 19,
    1993.
    The parties state that respondent continues to review the
    work plan for the column leach test which addresses alleged soil
    contamination around certain of petitioner’s tanks.
    Respondent
    states that it expects to complete its review of the column leach
    test by April
    30,
    1993,
    and that after that date the parties
    would be in a better position to determine if the matter can be
    concluded without a hearing.
    Petitioner reports that respondent
    has now approved the closure certification statements for five of
    the six remaining RCRA storage tanks.
    Petitioner states that it
    remains hopeful that the issues will be resolved, and grants a
    waiver of the decision deadline until March 31,
    1994 to
    accommodate amicable resolution.
    The parties are ordered to provide written status reports to
    be received by the Board no later than May 21,
    1993.
    IT IS SO ORDERED.
    Board Member B. Forcade abstained.
    I, Dorothy N.
    Gunn, Clerk of the Illinois Pollution Control
    Board,
    hereby certify that the above order was adopted on the
    6CZ
    day of
    ______________________,
    1993,
    by a vote of
    Dorothy M. ~1tin,Clerk
    Illinois Po9~utionControl Board