    On February 1, 1993, the Board received a status report
    filed by the petitioner. The status report indicates that the
    petitioner has spoken with the Illinois Environmental Protection
    Agency (Agency) and the Agency intends to file its recommendation
    on or before March 1. The petitioner indicates that it has no
    objection to this schedule.
    On February 3, 1993, the Board received a status report from
    the Agency. The Agency i~ndicatedthat it has reviewed the filing
    by petitioner and will file its recommendation within 30 days.
    Therefore, the Board directs the Agency to file its
    recommendation to be received by the Board not later than March
    3, 1993.
    This petition for variance was filed on June 15, 1992 and
    the matter was set for hearing. In the Board’s order setting the
    matter for hearing the Board asked the Agency to specifically
    address the issue as to whether this variance was a request for a
    RCRA variance. In response to the Board’s inquiry, the Agency
    states that it “is uncertain about the answer to this question
    and asks the Board for direction on whether the Agency should
    treat this variance as a RCRA variance”. The Board will continue
    to treat this as a RCRA variance request.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Boar4,~fiohereby cer~.kfythat the above order was adopted on the
    -~i~’--’
    day of
    -~a~i ,
    1993, by ~ vote of
    _________
    H
    Dorothy M. ~nn, Clerk
    Illinois Po’flution Control Board
    0139-0025