ILLINOIS POLLUTION CONTROL BOARD
November 4,
1993
BRAUN’S STANDARD SERVICE,
)
)
Petitioner,
)
v.
)
PCB 92—184
(UST Fund)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
ORDER
OF THE BOARD (by
C.
A. Manning):
This matter is before the Board on petitioner’s December 1,
1992 appeal of the Illinois Environmental Protection Agency’s
(Agency) decision to deny reimbursement of corrective action
costs.
On January
6,
1993, petitioner filed a motion to continue
the hearing and final decision pending the Board’s decision in
State Bank of Whittington v.
Illinois Environmental Protection
Agency,
(June
3,
1993), PCB 92-152. An open waiver of its right
to final Board action as provided for in Section 40 of the
Environmental Protection Act was also filed.
(415 ILCS 5/40
(1993)).
The Board granted the stay of proceedings as requested
on January 21,
1993, until June 3,
1993.
The Board decided State Bank of Whittington on June 3,
1993.
On October 7,
1993, the Board directed the petitioner to submit
to the Board and Hearing Officer a status report by October 21,
1993.
On October 25,
1993,
the petitioner filed a status report.
The status report states that the petitioner and respondent have
reached a tentative settlement agreement in this matter and that
petitioner will withdraw its Petition upon finalizing the
agreement.
The petitioner commits to submit a subsequent status
report to the Board within 90 days.
The Board accepts the status report and directs the
petitioner to file an updated status report on or before February
3,
1994.
IT IS SO ORDERED.
I, Dorothy M.
Gunn, Clerk of the Illinois Pollution Control
Board,
hereby cert~fythat the above order was adopted on the
1~
day of ______________________,
1993,
by a vote of
I2~iTO.
~iSorothyM.(c~unn,Clerk
Illinois P~L1utionControl Board