ILLINOIS POLLUTION CONTROL BOARD
January
20,
1994
OLIN CORPORATION,
)
)
Petitioner,
)
v.
)
PCB 91—87
(Permit Appeal)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
ORDER OF THE BOARD
(by C.A. Manning):
On May 23,
1991,
Olin Corporation
(“Olin”)
filed a petition
for hearing to review certain conditions contained in modifications
made by the Illinois Environmental Protection Agency (“Agency”) of
Olin’s closure plans for several different hazardous waste units at
the East Alton, Illinois facility.
On December 28, 1993,
Olin and
the Agency filed a joint status report pursuant to Board order of
September 23,
1993.
On January
6,
1994,
the Board accepted the
status
report and further
requested that Olin file a
statutory
deadline waiver in this case, or it would
be set for hearing.
On
January
13,
1994,
the Board received
a waiver until
January
1,
1995.
As was stated
in our January
6th order,
we indicated we
would re—establish a status report schedule upon receipt of the
waiver.
Accordingly,
the parties are directed to file a status
report in this matter on or before April 14,
1994.
IT IS SO ORDERED.
I,
Dorothy N. Gunn,
Clerk of the Illinois Pollution Control
Board,
hereby certif
that the above order was adopted on the
~&~Z
day of
,
1994,
by a vote of
Dorothy M. ,~inn, Clerk
Illinois P~,llutionControl Board