ILLINOIS POLLUTION CONTROL BOARD
December 2, 1993
THORNTON OIL COMPANY,
)
Petitioner,
v.
)
PCB 93—241
)
(Provisional Variance)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
ORDER OF THE BOARD (by C. A. Manning):
Pursuant to Section 35(b) of the Environmental Protection
Act (Act) (415 ILCS 5/35(b)), Thornton Oil Company has requested
that the Illinois Environmental Protection Agency (Agency)
recommend that the Board grant a provisional variance to allow
several of Thornton Oil Company’s gasoline dispensing operations
(service stations) to continue operating even though they did not
install operational vapor recovery equipment by November 1, 1993.
Such request for a provisional variance and the Notification of
Recommendation was filed with the Board by the Agency on Tuesday,
November 30, 1993. Pursuant to Section 35(b) of the Act, the
Board must issue the variance within two (2) days of this filing.
Specifically, the Agency recommends that we grant Thornton
Oil Company a forty-five (45)-day provisional variance for
sixteen (16) of its facilities located in Cook, DuPage, Kane,
Lake, and Will Counties in the Chicago metropolitan statistical
area from the Stage II vapor recovery requirements, as set forth
in 35 Ill. Adm. Code 218.586, for the period beginning November
1, 1993, and continuing for forty-five (45) days or until the
required vapor recovery equipment is installed, whichever comes
first.
The Agency’s provisional variance recommendation states that
Thornton Oil Company has requested a provisional variance on
behalf of numerous of its service stations in the Chicago area,
located as follows:
County
Number of Stations
Cook
9
DuPage
4
Kane
1
Lake
1
Will
1
The addresses of those stations are listed as follows:
2
County
City or Village Street Address
Cook
Blue Island
12052 South Western Avenue
Cook
Cicero
2351 Cicero Avenue South
Cook
Forest Park
601 South Harlem Avenue
Cook
Franklin Park
2640 )‘lannheim Road
Cook
Oak Forest
14805 South Cicero Avenue
Cook
Orland Park
7600 West 159th Street
Cook
Palatine
100 East Dundee Road
Cook
Park Ridge
1118 Touhy
Cook
Streamwood
2 North Barrington Road
DuPage
Addison
800 West Lake Street
DuPage
Bensenville
1225 Devon Avenue
DuPage
Bloomingdale
190 East Lake Street
DuPage
Villa Park
250 East Roosevelt Road
Kane
North Aurora
322 South Lincoln Way
Lake
Round Lake Beach 180 East Rollins Road
Will
Joliet
1801 West Jefferson Street
Upon receipt of the request, the Agency issued its
recommendation, notifying the Board that the failure to grant thE
requested forty—five (45)—day provisional variance would impose
an arbitrary or unreasonable hardship on Petitioner. The Agency
recommendation states that installation of Stage II vapor
recovery equipment at the Thornton Oil Company facilities is not
possible by the November 1, 1993 deadline for compliance because
Thornton Oil Company has contracted for the installation of vapor
recovery equipment, but that equipment and the crews necessary tc
install it was not available before the compliance deadline.
Provisional variances are by their very nature temporary.
The responsibilities of the Agency and the Board in these short-
term provisional variances are different from the
responsibilities in standard variances.
~
415 ILCS 5/35(b) &
(C)). In provisional variances it is the responsibility of the
Agency to make the technical determinations and finding of
arbitrary or unreasonable hardship. The Board’s responsibility
is to adopt a formal Order, to assure the formal maintenance of
the record, to assure the enforceability of the variance, and to
provide notification of the action by a press release.
Having received the Agency recommendation notifying the
Board that a denial of the requested relief would impose an
arbitrary or unreasonable hardship, the Board hereby grants
Petitioner a provisional variance from 35 Ill. Adm. Code 218.586,
subject to the following conditions:
1. The term of this provisional variance shall commence on
November 1, 1993, and it shall expire on the date the
Petitioner completes the required installation of vacuum
assist stage ii vapor recovery equipment, or after forty-
five (45) days have elapsed, whichever comes first;
3
2. The Petitioner shall notify the Agency of the
installation of the vapor recovery equipment, by sending
notification addressed as follows:
Mr. Terry Sweitzer, P.E.
Manager, Air Monitoring Section
Illinois Environmental Protection Agency
Division of Air Pollution Control
P.O. Box 19276
Springfield, Illinois 62794—9276
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, do hereby certify that the above order was adopted on the
~ day of ______________________________, 1993, by a vote of
~ç.-
-~
—~
I
)
Dorothy M. ~Gunn, Clerk
Illinois Pollution Control Board