ILLINOIS POLLUTION CONTROL BOARD
    June
    2,
    1994
    EMRO
    MARKETING
    COMPANY,
    )
    Petitioner,
    v.
    )
    PCB 93—122
    )
    (UST Fund)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    KEVIN
    L. KROHN OF
    MARATHON
    OIL APPEARED ON BEHALF OF THE
    PETITIONER.’
    OPINION
    AND
    ORDER OF THE BOARD
    (by E.
    Dunham):
    This matter comes before the Board on a petition for review
    filed by Emro Marketing
    (Emro)
    on June 21,
    1993, pursuant to
    Sections 22.l8b(g)2 and 40 of the Environmental Protection Act
    (Act).
    (415 ILCS 5/22.l8b(g)
    & 40
    (1992).)
    Emro is a subsidiary
    of Marathon Oil.
    The petition seeks review of the Illinois
    Environmental Protection Agency’s (Agency) May 17,
    1993
    determination that
    Eniro
    is ineligible for reimbursement from the
    Underground Storage Tank Fund.
    Emro sought reimbursement for
    corrective action costs which resulted from a release of
    petroleum on August 14,
    1990 at
    Emro’s facility in
    Grayslake,
    Lake County,
    Illinois.
    A hearing in this matter was conducted on April
    12,
    1994,
    in
    Grayslake, Illinois before hearing officer Allen Schoenberger.
    At hearing the parties submitted the stipulated testimony of
    Howard Sloan and an affidavit from Paul D. Hancock.
    Mr.
    Sloan
    is
    an employee of Marathon Oil and serves as an engineering
    supervisor for Marathon and its subsidiaries.
    Mr. Hancock is a
    staff attorney with Marathon Oil.
    The Petro-Tite Manual
    (Pm),
    describing the tightness test performed was also placed into
    evidence at the hearing.
    Mo members of the general public
    attended the hearing.
    Emro filed its closing brief on April 21,
    1994.
    The Agency filed its response brief on April 29,
    1994.
    Emro filed a reply brief on May 4,
    1994.
    Mr. Krohn
    is
    a project engineer with Marathon Oil who
    appeared at hearing but did not make a statement.
    The attorneys
    representing Emro Marketing and the Illinois Environmental
    Protection Agency did not appear at hearing but agreed to the
    submission of stipulated testimony and exhibits at the hearing.
    2
    Section
    22.18b(g)
    of the Act was repealed in
    H.B.
    300
    effective September
    13,
    1993.

    2
    BACKGROUND
    In 1990,
    Eniro began construction for a new convenience
    store/gasoline station in Grayslake,
    Illinois.
    (Sloan at 1.)
    Gi-
    La Builders were retained to act as general contractor for
    construction of the facility including installation of the
    underground storage tank.
    (Sloan at 2.)
    Protanic Inc. was
    retained to perform tightness testing of the tank.
    (Sloan at 2.)
    The underground storage tank was installed by Gi-La Builders in
    August of 1990.
    (Sloan at 2.)
    The contractor elected to use Petro-Tite testing to test the
    integrity of the tank system.
    Petro-Tite testing requires that
    the tank system be filled to absolute capacity and that the
    system be purged of air.
    (Sloan at 3.)
    After the system is
    filled to capacity, a pump and gauging mechanism is attached to a
    tank opening creating a closed system.
    (Sloan at 3.)
    Petroleum
    is then circulated through the system.
    (Sloan at 3.)
    Any loss of
    product in the “closed” system indicates that the system is not
    secure and free of leaks.
    (Sloan at 3.)
    Prior to the arrival of Protanic to conduct the tightness
    testing, Gi—La Builders removed an automatic tank gauging device
    from one tank riser, since this device could be damaged during
    testing.
    (Sloan at 3.)
    Gi-La Builders placed a temporary loose
    fitting cap on the riser.
    (Sloan at 4.)
    Upon arrival at the
    site, Protanic noticed the loose fitting cap and determined that
    it was inappropriate for the tightness test.
    (Sloan at 4.)
    Therefore, the Protanic employees left the site to purchase the
    necessary cap.
    (Sloan at 4.)
    During the absence of the Protanic employees, the tank truck
    driver arrived to top off the underground storage tank for the
    tightness test.
    (Sloan at 4.)
    The petroleum level reached
    maximum capacity and elevated up the riser.
    (Sloan at 4.)
    The
    pressure of the gasoline through the riser pushed the loose
    fitting cap from the riser and product was released.
    (Sloan at
    4.)
    Some 755 gallons of product were released through the
    overfill of which 700 gallons were subsequently recovered.
    (Sloan
    at 4.)
    The remaining 55 gallons are unaccounted for and are the
    subject of continuing cleanup activities.
    (Sloan at 4.)
    Emro Marketing submitted the Notification of Underground
    Storage Tank form to the Illinois Office of the State Fire
    Marshal
    (OSFM)
    without the installer’s signature as Gi—La
    Builders refused to sign the form due to lack of payment by Emro
    which was being withheld due to a dispute concerning liability of
    the release.
    (Sloan at
    5.)
    OSFM rejected the form and brought an
    administrative action against Emro to force submittal of a signed
    form.
    (Sloan at
    5.)
    Gi-La Builders then agreed to sign the form
    and supplied certification that
    it has been certified or licensed
    by the OSFM.
    (Sloan at
    5.)

    3
    DISCUSSION
    The Agency decided that Emro was ineligible for
    reimbursement based on its determination that the tank “was not
    installed and operated in accordance with the rules adopted by
    the Office of the State Fire Marshal”
    (OSFM).
    (Ag. Rec.
    at
    2.)
    Section 22.18b(c)
    of the Act provides:
    (c)
    Notwithstanding subsection
    (a) or (b), no owner or
    operator is eligible to receive money from the Fund for
    costs of indemnification or corrective action for any
    underground storage tank installed after July 28,
    1989,
    unless the owner or operator demonstrates to the Agency
    that the tank was installed and operated in accordance
    with rules adopted by the Office of the State Fire
    Marshal.
    For purposes of this subsection,
    certification by the Office of the State Fire Marshal
    that the underground storage tanks were installed in
    accordance with those rules,
    shall be prima facie
    evidence that the owner or operator so installed such
    underground storage tanks.
    OSFM regulations allow several methods for an owner or
    operator to prove certification of compliance.
    (41 Ill.
    Adm. Code
    170.420(e).)
    Among the certifications of installation accepted
    by the OSFM is proof that the “installer has been certified by or
    licensed by the Office of the State Fire Marshall.”
    (41 Ill.
    Adm.
    170.420(e) (1).)
    In Smith Oil Company v.
    IEPA
    (July 30,
    1992),
    PCB 91—243,
    the Board found that the contractor’s certification of compliance
    and field inspection logs represented prima facie evidence that
    the tank was installed in accordance with OSFM regulations.
    Similarly,
    the Board finds that Emro’s certification of
    compliance represents prima fade evidence that the tank was
    installed in accordance with OSFM regulations.
    However, the
    Board must also consider additional evidence
    in this matter in
    rebuttal of the prima facie evidence.
    In rebuttal of the prima facie case,
    the Agency contends
    that the Petro—Tite testing was not performed in accordance with
    the manufacturer’s procedures.
    The Agency contends that the
    manual depicts a process where the tank truck operator fills the
    tank system while other personnel purge the system of air,
    determine if the system is at capacity and attach the Petro-Tite
    equipment.
    Because the tank truck operator was the only person
    on site,
    the Agency contends that the test was not conducted in
    accordance with the manufacturer’s procedures.
    Emro contends that leaving a riser open during the tightness
    test is consistent with the requirements of the test as all air

    4
    is to be purged from the system while the tank
    is being filled.
    Emro maintains that the Agency has failed to establish any
    inconsistency with OSFM regulations or which OSFM regulations
    were breached.
    The rules of the OSFM at 41 Ill.
    Adm. Code 170.420(d)
    require
    All tanks and piping must be properly installed in
    accordance with a code of practice developed by a
    nationally recognized association or independent
    testing laboratory and in accordance with the
    manufacturer’s instructions.
    When
    Emro’s contractor elected to perform a Petro—Tite test on
    the system to prove the integrity of the tank system they were
    required to perform that test in accordance with the manual.
    Failure to perform the test in accordance with the procedures
    described in the manual represents an infraction of the OSFM
    regulations.
    It is true,
    as. Emro asserts, that the Petro—Tite Manual does
    not specify the number of personnel needed to conduct tank
    filling and testing.
    It is also true that the Petro-Tite test
    requires that the riser be open during filling so that air may
    bleed out of the system.
    The Agency,
    however,
    is correct in its
    assertion that the petro—Tite test envisions close monitoring of
    the liquid level in the tank/riser system during filling.
    The
    tank filling procedure indicates that “The exact tank gage should
    be taken.”
    (PTM at 7.)
    The sample Data Chart for Tank System
    Tightness Test clearly indicates gauging of tank volumes and
    metered fills.
    (PTM at 10
    & 11.)
    In the example given in the
    manual, the filling process was stopped at least twice while the
    tank was gauged to ensure that no overfill occurred beyond the
    need to fill the Petro-Tite test equipment.
    (PTM at 11.)
    In Emro’s case,
    there is no evidence that anyone gauged the
    tank prior to filling, test personnel were not on site while the
    tank was overfilled, and no evidence was given to indicate how
    the delivery truck driver was allowed to spill 755 gallons of
    gasoline into the ground without a spill being detected.
    The
    Petro-Tite test methodology requires that UST systems be filled
    beyond their capacity,
    and the test admits the possibility that
    minor correctable leaks may be detected and cured.
    However,
    to
    lose 755 gallons of gasoline during a Petro-Tite test exceeds the
    reasonable amount of loss of product that could be justified due
    to the testing procedure.
    The stipulated
    facts in evidence indicate that the failure
    to install appropriate fittings, which would have sealed the tank
    system,
    and the failure to appropriately gauge the tank volume
    and meter gasoline delivery constituted
    a failure to conduct the

    5
    Petro-Tite test according to manufacturer’s specifications.
    This
    failure rebuts the prima fade case made by petitioners that the
    tank system was properly installed prior to the leak.
    Petition
    for access to the Underground Storage Tank Fund is therefore
    denied.
    In addition the Board notes that at the time of the spill,
    the tank was not properly installed as the contractor had not
    properly performed the tightness test to prove the integrity of
    the tank.
    That proper installation could be certified once the
    loose fitting was replaced does not alter the fact that, when the
    spill occurred, the tank installation was not certified nor was
    the installation certifiable at that moment.
    This opinion constitutes the Board’s findings of facts and
    conclusions of law in this matter.
    ORDER
    For the reasons stated herein, the Board affirms the
    Agency’s denial of eligibility for reimbursement for corrective
    action resulting from a spill from an underground storage tank at
    Emro’s
    facility in Grayslake,
    Illinois.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act,
    (415 ILCS
    5/41
    (1992)), provides for appeal of final orders of the Board
    within 35 days of the date of service of this order.
    The Rules
    of the Supreme Court of Illinois establish filing requirements.
    (See also 35
    Ill. Adm. Code 101.246, Motion for Reconsideration.)
    I, Dorothy M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opiniom and order was
    adopted on the
    ___________
    day of
    _______________
    ______
    1994, by a vote of
    ~
    .
    Ii
    Control Board

    Back to top