ILLINOIS POLLUTION CONTROL
    BOARD
    February 21, 1980
    ALGONQUIN
    AREA
    PUBLIC
    LIBRARY
    DISTRICT,
    )
    )
    Petitioner,
    )
    v.
    )
    PCB 79—159
    )
    ENVIRONMENTAL
    PROTECTION
    AGENCY,
    Respondent.
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    Mr.
    Goodman):
    This
    is a petition for variance from Rules 102 and 202
    of the Board’s noise regulations as they apply to Petitioner’s
    (flgonquin) air conditioning facility located behind its library
    building on 115 Eastgate, Algonquin.
    Petition was made as. a
    result of a complaint to the Illinois Environmental Protection
    Agency (Agency) in 1977 by Lori and Joseph Jasinski, whose home
    is situated approximately 50 feet behind Algonquin’s library.
    Algonquin’s engineers studied the problem and made recommenda-
    tions;
    Algonquin
    followed
    certain
    of
    these
    before
    seeking
    a
    5—dB
    variance
    for
    between the hours of 7:00 a.m. and 10:00 p.m.
    if
    and
    when
    conditions
    require
    operation
    at
    maximum
    load
    The
    technical
    reason
    given
    to
    support
    grant
    of
    variance
    is
    that
    further
    noise
    reduction
    can
    be
    achieved
    only
    by
    restricting
    air
    movement
    around
    the
    fans
    and
    coils.
    The
    hardship
    alleged
    is
    the
    already-spent
    $10,000,
    a present expenditure of uncertain
    size, and the ‘only trivial’ further reductions possible by its
    efforts.
    The
    Agency’s Recommendation was filed on October 30, 1979.
    It recommended denial for the reasons that
    (1) further noise
    reduction may not be trivial depending on the efforts expended
    by Petitioner;
    (2) Petitioner has not
    yet
    established a detailed
    noise abatement program; and (3)
    Petitioner
    to
    date
    has
    not
    followed all the recommendations of its consultant.
    The Board
    further notes that the variance petition did not specify the
    period
    for
    which
    the variance was sought and did not set forth
    a
    detailed
    compliance
    program.
    Attempts
    at
    correcting
    these
    were
    made
    at
    hearing
    (R.75—79).
    Algonquin first contacted its consultant—witness Yerges,
    a man of 41 years’ experience in sound control, on
    May
    31,
    1978
    (R.10—11).
    The problem
    was
    described as emanating from the
    air—cooled condensers during operation at maximum load, and in
    37—401

    particular from the vertical
    discharge
    of air over the
    fans
    located on the top of the unit (R,12)~ Yerges~recommendations
    one month later were to remove the tubular silencers on
    the
    top
    of the unit,
    replacing them with a lined,
    acoustic plenum and
    low pressure drop duct mufflers, and to screen the intakes to
    the unit
    (R,15)~
    Yerges further recommended constructing an
    8—foot barrier between the unit and the residential property,
    installing three-foot-long mufflers on the top of the unit
    (R,15-16),
    installing further screening,
    and adding absorptive
    material to the library wall behind the unit (R,29)~
    The system designer, Migdal, testified that the air
    con-
    ditioner could not be relocated much further away without
    sacrificing loss of refrigeration capacity (R~62—63);that two
    of
    the
    six
    fans
    could
    not
    be
    shut
    off
    without
    harming
    the
    system,
    especially for two hours during the estimated 30 days of peak
    demand annually (R~64—65),although this was possible after
    7:00
    pam.
    (R~73—74); that
    the
    system,
    installed
    at
    the
    end
    of
    1975 and having
    a 12—year life
    (R.74), was not designed with
    consideration of the noise levels
    in Rule 204
    (R,66—67);
    and
    that the manufacturer,
    Trane Co., advised him that extending
    the present 8—foot barrier by six feet or canting it would cause
    shortcycling when wind velocity was “low”
    (R.69—70).
    The library building architect, Pigozzi, testified that
    to move the 4,000-pound air conditioner would require roof
    modifications at a cost of $10,000 plus labor (R.88—90).
    The
    Librarian,
    Stahl,
    testified
    that
    the
    library
    never
    opens
    before
    10:00 a.m.
    and is closed on Sundays
    (R.92)
    (Neighbor Jasinski
    testified
    that the noise is heard on
    Sundays,
    R,110); that
    users
    have
    complained
    “vehemently”
    in
    the
    summer
    that
    the
    library
    is too
    warm
    (R.96);
    and that there has been an
    increased number of maintenance problems since the installa-
    tion of screening over
    a, year ago (R,94).
    The
    neighbor,
    Ms.
    Jaskinski,
    testified
    that
    the
    noise
    interferes
    with
    her
    family~s
    and
    friends~
    being
    outside
    in
    the yard
    (R,105,
    109),
    with
    both
    of
    her
    children~s
    falling
    asleep
    at
    night
    (R.106—107),
    and
    with
    dinnertime
    conversations
    (R.105).
    It
    sounds to her, especially in the evening hours,
    like a continual noise; when the system stops the quiet is
    noticeable
    (R,107—108),
    She did not complain directly to
    Algonquin because her builder informed her that the Agency was
    handling the problem
    (R,105—106),
    The Agency testified that it observed that Petitioner
    had
    taken the noise abatement steps of adding an exhaust
    plenum
    with silencers and constructing
    a barrier, but that the barrier
    was insufficient because it was too low (R,124—126),
    The Agency
    testified that even after the control methods were put into
    practice the noise
    level was too loud and interfered with
    living
    (R.147).
    The 60~dBsound
    level in the Jasinskis~back
    yard indicates that people must not stand more than 8-10 feet
    37—402

    from each other in order to converse normally (Recommendation,
    Ex~5).
    The Agency could not pursuant to Rule 405(a)(4) state
    what costs
    of compliance would he because Algonquin had not
    established a compliance plan (Recommendation, p~2),
    Exhibit
    5 of the Recommendation,
    an interoffice Agency
    memorandum,
    indicates that removing or relocating the unit will
    substantially reduce noise levels,
    as could barrier expansions
    The current problem is the exhaust at the top of the silencers;
    the Agency found this to be
    a major factor in the barrier~s
    ineffectiveness
    (Recommendation, Ex~5)~However,
    the barrier
    was one of the first steps which Yerges had advised Algonquin
    to take;
    if compliance wasn~tthereafter achievable Yerges
    advised various modifications to the barrier be made (Recom~
    rnendation, App~IV)~ The Agency found that these second step
    recommendations are what Algonquin must take, as
    a minimum,
    to
    reach compliance
    (Recommendation, Ex~5)~.
    Yerges and Migdal both testified that within five years,
    the period
    for which Algonquin seeks a variance possible improve~-
    ments
    or modifications can cause compliance
    but neither says
    much more except that compliance will be due to new methods of
    improvement (R~58)or to unspecified modifications (R~65~66).
    Algonquin~sattorney admits that the state of the art has since
    changed and offer~to modify or replace the unit accordingly,
    meanwhile running it on four of the six fans after 7:00 p~m.to
    ensure no operation at maximum load (R~77~78),
    Although no evidence was introduced regarding how the state
    of the art has changed,
    let alone the extent of costs involved,
    the Board will grant a limited variance for the purpose of allowing
    Algonquin to further investigate methods of complying with the
    Board~sRules~
    The Board will grant Algonquin variance
    from Rules
    102 and 202 until
    March
    1,
    1981 under certain conditions~
    These
    conditions will
    be those generally suggested by Algonquin at the
    hearing and to which the Agency refers
    in their closing arguments
    Although the Agency refers to a document dated December 27,
    1979
    supposedly submitted by Algonquin entitled uStatement of Interim
    Remedial Measures During Variance~,the Board can find neither
    the document nor any record of its having been filed before the
    Board
    This Opinion constitutes the findings of fact and conclu~~
    sions of law of the Board
    in this matters
    ORDER
    It
    is the Order of the Board that variance from Rules 102
    and 202 of the Board’s Noise Regulations be granted to Algonquin
    37-403

    —4—
    Area Public Library District until March
    1, 1981 under certain
    conditions:
    1.
    Algonquin Area Public Library District shall
    investigate and evaluate available methods
    which will allow its air conditioning equipment
    to meet limits imposed by the Board~sRules,
    including but not limited to extension of the
    noise barrier, modification of the exhaust and
    intake mufflers and/or compressor exhaust fans
    and the use of auxiliary air conditioners in
    remote locations.
    2.
    During the period of this variance Algonquin
    Area Public Library District shall modify its
    equipment operation in the following manner:
    (A)
    Algonguin shall maintain the temperature
    in the Library at the Federall~mandated
    level of 78°Fduring the cooling system.
    (B)
    Algonquin shall schedule the air conditioning
    equipment
    so that no more than two compressors
    and no more than four condenser fans are in
    operation after 7:00 p.m. Monday through
    Saturday and all day on Sunday.
    (3)
    Within 45 days of the adoption of this Order,
    the
    Algonquin Area Public Library District shall
    execute and forward to the Illinois Environmental
    Protection Agency,
    2200 Churchill Road, Springfield,
    Illinois 62706 a Certification of Acceptance and
    Agreement to be hound to all terms ~nd conditions
    of this Order,
    The 45 day period shall be held in
    abeyance during any period this matter is being
    appealed,
    The form of said certification shall be
    as follows:
    CERTIFICATION
    I
    (We),
    having read and
    fully understanding the Order of the Illinois Pollution Control
    Board in PCB 79~159,hereby accept said Order and agree to be
    bound
    by
    all of the terms and conditions thereof.
    S IGNED______
    TITLE_______
    DATE
    ______
    37—404

    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board,
    hereby certify the a~vçOpinion and Order
    were adopted on the
    A1~’
    day
    of ~
    1980
    by
    a vote of
    4~
    .
    C)
    Christan L.
    Mof
    ,
    Clerk
    Illinois Pollution Control Board
    37—405

    Back to top