ILLINOIS POLLUTION CONTROL BOARD
    March 17, 1994
    CITY OF
    HERRIN,
    )
    )
    Petitioner,
    )
    v.
    )
    PCB 93—195
    )
    (Permit Appeal)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    STEVEN
    HEDINGER, OF
    MOHAN, ALEWELT, PRILLAMAN &
    ADANI, APPEARED
    ON BEHALF OF THE PETITIONERS;
    RICHARD WARRINGTON APPEARED
    ON
    BEHALF OF
    RESPONDENT.
    OPINION
    AND ORDER OF THE BOARD (by G. T. Girard):
    On October 21, 1993, the Herrin Municipal Landfill (Herrin)
    filed a petition for review and reversal of the denial by the
    Illinois Environmental Protection Agency (Agency) of Herrin’s
    application for permit modification for Herrin’s site in
    Williamson County, Illinois. On December 17, 1993, a hearing was
    held in this matter in Marion, Williamson County, Illinois.
    Members of the public attended the hearing. Petitioner filed its
    briefs on January 18 and February 8, 1994. The Agency filed its
    brief on January 31, 1994.
    The Board’s responsibility in this matter arises from
    Section 40 of the Environmental Protection Act (Act). (415 ILCS
    5/40
    (1992). The Board is charged, by the Act, with a broad
    range of adjudicatory duties. Among these is adjudication of
    contested decisions made pursuant to the permit process. More
    generally, the Board’s functions are based on the series of
    checks and balances integral to Illinois’ environmental system:
    the Board has responsibility for rulemaking and principal
    adjudicatory functions, while the Agency is responsible for
    carrying out the principal administrative duties, inspections,
    and permitting.
    Based on review of the record, the Board affirms the
    Agency’s denial of the City of Herrin’s application for permit
    modification.
    REGULATORY FRAMEWORK
    Petition for review of permit denial is authorized by
    Section 40(a)(1) of the Act 415 ILCS 5/40 (a)(l) and 35 Ill.
    Adin. Code Section 105.102(a). The Board has long held that in
    permit appeals the burden of proof rests with the petitioner.
    The petitioner bears the burden of proving that the application,

    2
    as submitted to the Agency, would not violate the Act or the
    Board’s regulations. This standard of review was enunciated in
    Browning—Ferris Industries of Illinois, Inc. v. Pollution Control
    Board, 179 Ill. App. 3d 598, 534 N.E. 2d 616, (Second District
    1989) and reiterated in John Sexton Contractors Company v.
    Illinois (Sexton), PCB 88—139, February 23, 1989. In Sexton the
    Board held:
    ...that the sole question before the Board is whether the
    applicant proves that the application, as submitted to the
    Agency, demonstrated that no violations of the Environmental
    Protection Act would have occurred if the requested permit
    had been issued.
    Therefore, the petitioner must establish to the Board that the
    permit would not violate the Act or the Board’s rules if the
    requested permit was to be issued by the Agency. In addition,
    the Agency’s written response to the permit application frames
    the issues on appeal from that decision. (Pulitzer Community
    Newspapers, Inc. v. Illinois Environmental Protection Agency, PCB
    90-142, at 6 (December 20, 1990); Centralia Environmental
    Services, Inc. v. Illinois Environmental Protection Agency, PCB
    89—170, at 6 (May 10, 1990); City of Metropolis v. Illinois
    Environmental Protection Agency, PCB 90—8 (February 22, 1990).
    BACKGROUND
    The City of Herrin is the owner and operator of the Herrin
    Municipal Landfill located southeast of Herrin in Williamson
    County, Illinois. (Pet. at 1.)’ The site consists of
    approximately 70 acres and was originally permitted on September
    10, 1975. (Pet. at 1.) In 1988, Herrin requested a development
    permit from the Agency to move its operations from one location
    to another within the permitted boundaries of the facility. (Tr.
    at 11-12.) The Agency denied the request based upon
    informational deficiencies initially and later denied the
    resubmitted application on the grounds that Herrin had failed to
    receive siting approval. (Pet. Exh. 1, 2, 3, 4, and 5; Tr.at 14-
    18.)
    In 1988, the Illinois Attorney General on behalf of the
    People of the State of Illinois filed an amended complaint
    1
    The Agency record will be cited as “R Vol.
    at
    _“;
    the
    petition for review of permit denial will be cited as “Pet. at
    _“;
    petitioner’s brief will be cited as “Pet. Br. at
    _“;
    petitioner’s reply brief will be cited as “Pet. RBr. at
    “;
    respondent’s brief will be cited as “Res. Br. at
    _“;
    the hearing
    transcript will be cited as “Pr. at
    _“;
    petitioner’s exhibits
    will be cited as Pet. Exh.

    3
    against the City of Herrin along with a stipulation and
    settlement agreement in circuit court. (R. Vol. I at 90.) As a
    part of the settlement agreement Herrin agreed to obtain an
    operating permit for all portions of the site in which Herrin
    conducts waste disposal. (R. Vol. I at 97.)
    In March 1990 siting approval for a vertical expansion of
    the Herrin facility was granted by the Williamson County Board of
    Commissioners. (R. Vol. I at 164-167.) In August 1990 an
    application requesting a supplemental permit for the vertical
    expansion was filed with the Agency. (Pet. at 2, R. Vol. I at
    147.) The August 1990 application “anticipated that closure of
    the vertical expansion will begin in July 1992 and be closed by
    November 1992.
    . .“.
    (R. Vol. I at 177.) The Agency issued a
    permit (1990-353-SP) in November 1990 for the vertical expansion.
    (R. Vol. I at 123—126c.) The November 1990 permit (1990—353—SP)
    stated that the “facility shall initiate closure no later than
    September 18, 1992”. (R. Vol. I at 126A.) Herrin did not appeal
    that permit.
    Prior to the Agency issuing a permit in response to the
    August 1990 application the Board’s regulations governing
    landfills were adopted.
    (~
    In the Matter of: Development,
    Operating, and Reporting Requirements for Non—hazardous Waste
    Landfills, R88—7, 114 PCB 483, (August 17, 1990) (hereinafter
    cited as “R88-7 at
    “).)
    The landfill regulations apply to
    nonhazardous waste landfills including “municipal” and industrial
    landfills. (R88-7 at 2.) Existing facilities were divided into
    three general groups based on the level of compliance the
    facility could demonstrate with the new regulations. (Id.)
    Subpart C facilities may remain open for an indefinite period of
    time beyond seven years and are required to meet the most
    stringent requirements. Subpart D facilities may remain open for
    seven years and are required to meet less stringent of
    requirements, but expansion of the facilities was prohibited.
    Subpart E facilities must initiate closure within two years or
    already be scheduled to close. Subpart E facilities were not
    required to meet any of the closure requirements adopted in R88—
    7, but were required to close under existing Part 807. (Id.)
    In March 1991, Herrin filed with the Agency a PA15 form
    which is required to be filed pursuant to the Board’s regulations
    (See 35 Ill. Adm. Code 814.103). (Pet. at 3; R. Vol. II at 164—
    166.) On that form, Herrin indicated that it was a “Subpart D”
    facility and would “initiate closure by September 18, 1997”. (R.
    Vol. II at 164B.) The Agency took no action in response to the
    submission of the PA15 form. (Tr. at 116.)
    On September 16, 1992, the Agency sent a letter to Herrin
    indicating that according to Agency records the facility was
    regulated pursuant to 35 Ill. Adin. Code 814 Subpart E and was
    scheduled to close by September 18, 1992. (R. Vol II at 166B.)

    4
    The letter went on to indicate that Herrin could be subject to
    enforcement with resulting fines if found in violation of the
    Board’s regulations. (Id.)
    Herrin contacted the Agency upon receipt of September 16,
    1992 letter. (Tr. at 130—134.) After discussions between Herrin
    and the Agency, the Agency issued a supplemental permit (1992-
    271—SP) on September 21, 1992, allowing Herrin to accept waste
    until October 8, 1993. (R. Vol. II at 167.) However, the
    supplemental permit still stated that “this facility must begin
    closure by September 18, 1992 (Subpart E, 814), and may continue
    to accept waste during closure until October 8, 1993 (807.509)”.
    (R. Vol. II at 167.) The permit included 15 conditions (R. Vol.
    II at 167—169) and was not appealed by Herrin.
    On April 23, 1993, the Agency again wrote Herrin concerning
    its scheduled date of closure. (R. Vol II at 327.) In response
    to the April 23, 1993, letter Herrin requested that the Agency
    consider Herrin a Subpart D facility and allow Herrin to remain
    open until as late as 1997. (R. Vol. II at 347.) The Agency
    denied this request on September 16, 1993 and this appeal
    followed. (R. Vol. II at 329—330.)
    DISCUSSION
    Request to Strike Portion of Respondent’s Brief
    As a preliminary matter, the Board notes that in Herrin’s
    reply brief, Herrin asks that a portion of the Agency’s brief be
    stricken. (Pet. RBr. at 3.) Specifically, Herrin asks that the
    Agency’s argument that Herrin is estopped from seeking a change
    in the permit is not properly before the Board. (Pet. RBr. at
    3.) Because the issues in a permit appeal are established by the
    permit denial letter, Herrin maintains that the argument is an
    affirmative defense likely to take Herrin by surprise and thus
    should be stricken. (Pet. RBr. at 4.) The Agency’s estoppel
    argument merely recites facts contained in the record by pointing
    out that Herrin had not appealed previous permit decisions on the
    closure date. These facts would be before the Board even if the
    Board were to strike the portion of the Agency’s brief discussing
    estoppel. Therefore, the Board denies the request to strike.
    Herrin’s Argument
    Herrin argues that the Agency’s determination denying Herrin
    a permit modification should be reversed because the amendments
    adopted in R88-7 do not apply to Herrin on the theory that this
    case is controlled by American Fly Ash Co. v. County of Tazewell,
    (120 Ill. App. 3d 57 (3d Dist. 1983)) (American). (Pet. Br. at
    7.) In American, the company had applied for and received (July
    22, 1981) a permit to dispose of fly ash and boiler slag prior to
    the signing of the local landfill siting bill (SB 172). (Pet.

    5
    Br. at 7—8.) The specific terms of SB 172 stated that it applied
    to all facilities “initially permitted for development or
    construction after July 1, 1981”. Tazewell County took the
    position that the new law nullified the Agency issued permit and
    that American was required to seek local siting approval. (120
    Ill. App. 3d at 58; Pet. Br. at 7-8.) The court disagreed
    stating that “justice, fairness and equity require that persons
    who comply with the law not as it might be but as it is then is
    effect, and in this instance obtain the required permit after
    expenditure of funds, should not have that permit nullified by
    retroactive application of a statute subsequently enacted.” (120
    Ill. App. 3d at 59.)
    Herrin maintains that it has “fallen victim to not one, but
    in fact two changes in the law”. (Pet. Br. at 8.) Herrin argues
    that the first change in the law involved a Supreme Court of
    Illinois decision which required Herrin to seek siting approval
    in 1988 for the vertical expansion of the facility. (M.I.G.
    Investments. Inc. v. Environmental Protection Agency, 151 Ill. 2d
    122 (1988).) The second more significant change, according to
    Herrin, was the adoption of R88—7. (Pet. Br. at 9.) Herrin
    argues that “there was absolutely no means for Herrin to
    prepare for or anticipate either the effective date of the R88-7
    rules or the final content of those rules.” (Pet. Br. at 10.)
    Herrin recites at length the history of the landfill regulations
    in Illinois, pointing out that at least one docket preceded R88-7
    before the Board and that the Board had several opinions and
    orders in R88—7. (Pet. Br. at 11.) Thus, Herrin argues the
    history of R88-7 “would not have led any reasonable permit
    applicant to assume anything with respect to the final effective
    date or content of those regulations.” (Pet. Br. at 10.)
    Herrin states that it:
    had the misfortune to have sought its relief
    from the Agency during a period of regulatory
    flux. This misfortune has imposed no less
    than an injustice upon Herrin, and the words
    of the Court in American Fly Ash are directly
    applicable here-
    -
    ‘justice, fairness and
    equity require that persons who comply with
    the law not as it might be but as it is then
    in effect...should not have that permit
    (request nullified by retroactive
    application of a regulation subsequently
    enacted. 120 Ill. App. 3d at 59. (Pet. Br.
    at 12.)
    Herrin argues that “justice, fairness and equity” should
    intervene to relieve Herrin of the regulatory requirements “which
    arbitrarily impose a severe burden upon Herrin to Herrin’s
    detriment because of reliance upon the previous regulatory

    6
    requirements.
    .
    .“.
    (Pet. Br. at 12.) Herrin further maintains
    that such an outcome is supported by a long history of Illinois
    case law. (Pet. Br. at 12.) Herrin then cites to two cases
    which Herrin asserts support its position. Herrin cites to Frank
    v. State Sanitary Water Board of Illinois, 33 Ill. App. 2d 1,
    (1st Dist. 1961) (Frank) and Wachta v. Pollution Control Board, 8
    Ill. App. 3d (2d Dist. 1972).)
    Herrin argues that the doctrine of estoppel should apply in
    this case. Herrin maintains that the Agency required Herrin to
    close its facility in 1992, while Herrin now wishes to close its
    facility in 1995. Absent the application of the R88—7
    regulations, such a requirement is not justified, according to
    Herrin. Herrin argues that it has sufficient capacity to remain
    open until 1995 and prior to that date would “deprive Herrin of
    some $430,000”. (Pet. Br. at 14.) Finally, Herrin states that
    “t)here is no justification for that deprivation, and justice,
    fairness and equity dictate that result be avoided here.” (Pet.
    Br. at 14.)
    Agency’s Argument
    The Agency maintains that Herrin should be estopped from
    seeking a different closure date. (Res. Br. at 9.) In support
    of its position the Agency states that the operating permit which
    initially called for closure of the Herrin facility by 1992 was a
    result of an enforcement action brought by the Attorney General.
    (Res. Br. at 3-4.) The Agency further states that no appeal was
    taken from that permit. (Id.) The Agency also points out that
    it issued a modification to that permit on September 21, 1992
    allowing the facility to remain open until October 1993 and no
    appeal was taken from that permit modification. (Res. Br. at 5.)
    This appeal followed yet another request for modification which
    the Agency denied. (Id.)
    The Agency further maintains that Herrin has no economic
    argument to support its position that estoppel applies. The
    Agency states that the testimony regarding costs incurred was
    specific to the proportions of time used in supervising daily
    operations and in preparing the application for expansion,
    including siting. (Res. Br. at 10 citing Tr. at 54.) The Agency
    argues that operating expenses are not an extraordinary expense
    made in expectation of future operations and closure plan
    expenses are an obligation from past landfill use. (Id.) The
    Agency cites to Land and Lakes v. EPA, PCB 91-217 to support this
    position. (Id.)
    The Agency also argues that the R88-7 regulations do apply
    to Herrin and that the Board has already settled that issue. The
    Agency cites to Ziffrin v. United States (318 U.S. 73, 63 S. Ct.
    465 (1943)) for the proposition that “the administrative agency
    must apply the changed law.” (Res. Br. at 6.) The Agency

    7
    further cites to two Illinois Appellate court cases that the law
    in effect at the time of the agency’s decision applies.
    (Illinois md. Telephone Association v. Illinois Commerce
    Commission, 183 Ill. App. 3d 220, 539 N.E.2d 717, 132 Ill. Dec.
    154 (1989); Skokie Federal Savings and Loan Assoc. v. Illinois
    Savings and Loan Board, 61 Ill. App. Ct. 977, 378 N.E. 2d 1090,
    19 Ill. Dec. 215 (1978).) The Agency states that the Board “has
    previously followed this reasoning in Gallatin National Company
    V.
    Illinois Environmental Protection Agency,” PCB 90-183. (Res.
    Br. at 7.)
    Finally, the Agency argues that the issuance of the
    requested permit would violate the Board’s regulations. (Res.
    Br. at 11.) The Agency points out that there is no prohibition
    to continued operation under the new landfill regulations as long
    as the facility can demonstrate compliance with the applicable
    regulations. (Res. Br. at 12.) However, the Agency argues
    Herrin cannot demonstrate that the 1990 permit allowing the
    expansion is in compliance with the Board prohibition on
    expansions applicable to Subpart D facilities at 35 Ill. Adm.
    Code 814.402 (b). (Id.) Thus, the Agency maintains that Herrin’ s
    activities preclude it from demonstrating compliance with the
    classification Herrin is seeking. (Id.)
    Application of R88-7
    Herrin’s argument that the R88-7 regulations should not
    apply is not persuasive. The regulations adopted by the Board in
    R88-7 specifically applied to “existing” facilities, which are
    defined as any facility or unit not defined as a new facility.
    (35 Ill. Adm. Code 810.103.) Part 814 as adopted in R88—7
    applied standards to existing facilities and established
    standards for both new and existing disposal units within the
    facilities. Section 814.101 specifically states:
    Landfill operators are required to determine the date
    on which their facilities must begin closure, which is
    dependent upon the ability of existing units to meet
    the design and performance standards of this Part.
    (35 Ill. Adm. Code. 814.101.)
    Thus, the plain language of R88-7 applies the regulations to
    existing facilities which include Herrin.
    Furthermore Herrin’s argument that the regulations were
    applied retroactively and Herrin’s reliance on American Fly Ash
    are not convincing. The R88-7 regulations became effective in
    September of 1990 and Herrin’s permit was issued by the Agency in
    November of 1990. In American Fly Ash the landfill operator had
    a permit in hand and the legislation’s effective date was

    8
    retroactively applied to a date prior to the issuance of the
    permit. Herrin did not receive a permit until after R88-7 was
    effective.
    In its argument, the Agency properly cited to Gallatin
    National Company
    V.
    IEPA, PCB 90-183, (January 18, 1992) 118 PCB
    97 (Gallatin). In Gallatin, the petitioner specifically argued
    that the R88-7 regulations should not apply retroactively to
    Gallatin. (Gallatin at 4.) Gallatin, like Herrin, was in the
    process of applying for a permit for its landfill when R88-7 was
    adopted. The Agency indicated that it would apply the provisions
    of R88-7 to Gallatin and Gallatin sought a variance from portions
    of the R88—7 regulations. (Gallatin at 2.) Gallatin argued
    against the retroactive application of R88-7 in the variance
    proceeding. The Board found that Gallatin clearly met the
    definition of a “new unit” in R88-7 and the regulations applied
    to Gallatin. (Gallatin at 5.) Thus, the Board has already ruled
    that a permit applicant who was in the process of applying for a
    permit during the pendency of R88-7 is subject to the provisions
    of R88—7 even if the permit is issued after the adoption of R88—
    7.
    The provisions of R88-7 would have applied to Herrin even if
    Herrin had not been seeking a new permit during the pendency of
    the rules. The landfill regulations were adopted to protect the
    environment of the state of Illinois and to insure the safest
    possible landfill operations. Herrin would have been required to
    meet the standards of Part 814 if it wished to remain open. The
    provisions of R88—7 apply to all existing landfills.
    Herrin is arguing that it should be allowed to close under
    Part 814 Subpart D rather than Subpart E. However, Herrin
    accepted a permit modification in November of 1990 after the
    adoption of R88-7. The Agency used the provisions of R88-7 and
    specifically Section 814.Subpart E, in establishing the closure
    date of September 1992 in the November 1990 permit. Herrin did
    not appeal that permit and in fact accepted a modification in
    September 1992 which allowed Herrin to “accept waste during
    closure until October 8, 1993”. (R. Vol. II at 167.) Herrin
    then sought to modify the November 1990 permit by applying a
    different portion of the R88-7 regulations. Therefore, the
    Board finds that Herrin has waived the argument that R88-7 should
    not apply to the Herrin facility.
    Estop~e1
    Herrin argues that “justice, fairness and equity” require
    the application of the doctrine of estoppel in this case. The
    Agency argues that Herrin should be estopped from seeking relief.
    The Board has applied the doctrine of equitable estoppel in very
    rare instances. In In the Matter of: Pielet Brothers’ Trading,
    Inc., AC 88—51, 101 PCB 131 (July 13, 1989), Pielet deposited

    9
    waste by an area method rather than by trench method pursuant to
    its permit. Pielet argued that, under the common law principles
    of estoppel, the Agency should be estopped from punishing it for
    changing its operations from a trench fill to an area fill
    because it allowed the change. The evidence revealed that Pielet
    had several meetings with the Agency and provided documentation
    indicating that it was operating as an area fill, and that the
    Agency did not inform Pielet that its activities could be a
    violation of the Act for which an administrative citation could
    be issued. The Board found that the Agency was estopped from
    finding Pielet in violation of the Act based on its belief that
    “the record reveals that the Agency, through its representatives,
    made representations to Pielet Brothers upon which Pielet
    Brothers could reasonably have believed allowed it to deposit
    waste by the area fill method in certain portions of the landfill
    in addition to those permitted”. (Id. p. 9, 101 PCB at 140).
    Also, in IEPA v. Jack Wright, AC 89—227 (August 30, 1990), the
    Agency issued an administrative citation against Mr. Wright for
    an open dumping that resulted in litter. The Board concluded
    that statements made by an Agency field inspector led Mr. Wright
    to believe that no administrative citation would be filed if he
    took remedial action to clean up his facility and that, as a
    result, the Agency improperly issued the administrative citation
    against Mr. Wright.
    There are also court cases which are relevant to this
    argument. In Modine Manufacturing Co. v. PCB, 176 Ill. App. 3d
    1172 (1988) (an unpublished order that was discussed in Modine
    Manufacturing Co. v. PCB, 193 Ill. App. 3d 643, 549 N.E.2d 1379
    (2nd Dist. 1990)), the Appellate Court found that the Agency’s
    agreement not to institute enforcement proceedings for emission
    violations barred an enforcement action brought by the Agency,
    but that no such agreement existed with respect to certain permit
    violations cited by the Agency. It then dismissed the action for
    the emissions violations and remanded the case to the Board to
    set the penalty on the permit violations. (see Modine, 549
    N.E.2d at 1381, 140 Ill. Dec. 509).
    In this case, the Board finds that the doctrine of estoppel
    should not apply. Herrin had previously accepted a closure date
    consistent with the decision by the Agency in this case. (See
    November 1990 permit, R. Vol. I at 126A.) In fact, the date
    originally accepted by Herrin has already been extended.
    (September 1992 supplemental permit, R. Vol. II at 167.)
    Although Herrin has expended funds, the record does not indicate
    that the expenditures were greater than those necessary to
    operate and expand the facility. Herrin’s only step to notify
    the Agency that it wished to change its status was the filing of
    a PA15 form. (R. Vol. II at 164—166.) On that PA15 form, Herrin
    indicated that it desired to be classified as a Subpart D
    facility and initiate closure by September 18, 1997. (R. Vol. II
    at 164A.) The PA15 form was required by Board regulations and

    10
    the Agency was not required to respond to the filing of the form.
    The record does show that the Agency may have responded to some
    of the filings. However, the record does not indicate that the
    Agency, as a standard practice, responded to the form.
    Violation of Board regulations
    The Board finds that the record is clear that extending the
    closure date and allowing Herrin to close as a Subpart D facility
    would result in violation of the Act. Section 814.402(b) (1)
    (Subpart D) specifically prohibits expansion beyond the area
    included in a permit prior to the effective date of this part.
    Herrin received a permit to expand its facility in November 1990
    two months after the effective date of R88-7. The permit stated
    that the facility would initiate closure no later than September
    18, 1992. (R. Vol. I at 126A.) Herrin did not appeal the
    permit. Therefore, granting Herriri the modification to close
    under Subpart D would violate the Board’s regulations.
    CONCLUSION
    The Board finds that Herrin has not shown that the issuance
    of a permit modification allowing Herrin to close its facility
    pursuant to 814.Subpart D would not violate the Board’s
    regulations and the Act. The Board further finds that the
    doctrine of estoppel does not apply in this case.
    This opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    The denial by the Illinois Environmental Protection Agency
    of a permit application for amendments to existing permits
    requested by the City of Herrin is affirmed.

    1.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act (415 ILCS
    5/40.1) provides for the appeal of final Board orders within 35
    days of service of this decision. The Rules of the Supreme Court
    of Illinois establish filing requirements. (But see also, 35
    Ill. Adm. Code 101.246, Motions for Reconsideration.)
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opinion and order was
    adopted on the
    /
    day of
    7)’~
    ~L-t~i_
    1994, by a vote of ~
    Control Board

    Back to top