ILLINOIS POLLUTION CONTROL BOARD
    September 1, 1994
    J. R. MEYERS COMPANY, INC.,
    )
    Petitioner,
    V.
    )
    PCB 94—236
    )
    (UST Fund)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    ORDER OF THE BOARD (by E. Dunham):
    On August 30, 1994, J. R. Meyers filed a petition to contest
    the disallowing of certain costs incurred in the removal of
    underground storage tanks by the Illinois Environmental
    Protection Agency. The Board notes that the petition lacks
    sufficient information to determine if the petition has been
    filed pursuant to Section 40 of the Illinois Environmental
    Protection Act (“Actt’). Further, the petition does not include
    proof that the Agency was served with the petition.
    The Board directs the petitioner to file an amended petition
    to correct these deficiencies. A copy of the check issued to J.
    R. Meyers should be provided with the petition. A proof of
    service should also be included with the petition pursuant to 35
    Ill. Adm. Code 101.143. Unless an amended petition is filed
    within 35 days of the date to this order, curing the above-noted
    defect(s), this matter will be subject to dismissal. The Board
    notes that for purposes of calculation of a decision deadline
    pursuant to Section 40 of the Act, the filing of an amended
    petition will restart the calculation of the Board’s 120—day
    deadline.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, do hereby certify that the above order was adopted on the
    /~T day of
    ,
    1994, by a vote of
    Dorothy N. Gu~1~,Clerk
    Illinois Pollution Control Board

    Back to top