ILLINOIS POLLUTION CONTROL BOARD
    September 1, 1994
    J.M. SWEENEY CO.,
    Petitioner,
    V.
    )
    PCB 93—257
    )
    (Variance)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    ROBERT C. OSMUNDSEN APPEARED ON BEHALF OF PETITIONER;
    RACHEL L. DOCTORS APPEARED ON BEHALF OF RESPONDENT.
    OPINION AND ORDER OF THE BOARD (by R.C. Flemal):
    This matter comes before the Board upon a petition for
    variance filed by J.M. Sweeney Co. (Sweeney) on December 17,
    1993. Sweeney seeks variance from the requirement of 35 Ill.
    Adm. Code 218.586 that Stage II vapor recovery equipment be
    installed by November 1, 1993. The facility in question is
    located at 1557 S. Central Avenue, Cicero, Illinois.
    The Board’s responsibility in this matter arises from the
    Environmental Protection Act (Act) (415 ILCS 5/1 et seq. (1992).)
    The Board is charged there with the responsibility of granting
    variance from Board regulations whenever it is found that
    compliance with the regulations would impose an arbitrary or
    unreasonable hardship upon the petitioner. (415 ILCS 5/35(a).)
    The Illinois Environmental Protection Agency (Agency) is required
    to appear in hearings on variance petitions. (415 ILCS 5/4(f).)
    The Agency is also charged, among other matters, with the
    responsibility of investigating each variance petition and making
    a recommendation to the Board as to the disposition of the
    petition. (415 ILCS 5/37(a).)
    The Agency filed its variance recommendation (Rec.) on
    January 20, 1994. The Agency recommended grant of the variance
    as requested by Sweeney, but with a shorter term than proposed by
    Sweeney.
    Hearing was held on July 14, 1994 in Chicago, Illinois,
    before hearing officer Richard T. Sikes. No witnesses were
    called, although the prepared testimony of Terry A. Sweitzer,
    Manager of the Agency’s Air Monitoring Section and Administrator
    of the Illinois Stage II Vapor Recovery Program, was admitted
    into the record as respondent’s exhibit #1 (Resp. Exh. 1). No
    members of the public attended the hearing.

    —2—
    On August 11, 1994 the parties filed a joint stipulation of
    agreement (Stip.) as to the timing and conditions of termination
    of the requested variance’.
    As presented below, the Board finds that Sweeney has met its
    burden of demonstrating that immediate compliance with the
    regulation at issue would impose an arbitrary or unreasonable
    hardship. Accordingly, the variance request will be granted.
    BACKGROUND
    35 Ill. Adm. Code 218.586 establishes air emission control
    requirements applicable to motor vehicle fueling operations
    (MVFO) located in the Chicago ozone nonattainment area. Among
    these is a requirement that certain MVFOs install Stage II vapor
    recovery equipment no later than November 1, 1993. (Section
    218.586(d)(2).) It is uncontested that this provision applies to
    Sweeney’s facility at 1557 S. Central Avenue in Cicero.
    Stage II vapor recovery equipment is designed to capture
    hydrocarbon vapors during the fueling of vehicle tanks. Vehicle
    fuel emissions consist of gasoline vapors displaced from the
    motor vehicle tank by dispensed liquid gasoline as the tank is
    filled. The Stage II equipment captures vapors that exit the
    vehicle’s fuel filipipe, thereby preventing the escape of the
    vapors into the atmosphere. The captured vapors flow through a
    vapor passage in the fuel pump nozzle into a vapor hose and then
    through vapor lines to the underground storage tank.
    As such, Stage II vapor recovery equipment is part of both
    the dispensing and tanking systems of an MVFO.
    Sweeney contends that it had initiated efforts to achieve
    compliance by the November 1, 1993 compliance date. (Pet. at
    ¶10; Tr. at p. 5.) Among these efforts was a site evaluation
    conducted by a geophysical consulting firm. (Pet. at ¶11.) On
    August 30, 1993 the consulting firm informed Sweeney that
    petroleum contamination likely occurred at the site. (Pet. at
    ¶12.) On August 31, 1993 Sweeney notified the Illinois Emergency
    Management Agency (IEMA) of the suspected contamination and of
    the likely need for remediation. (Pet. at ¶13.) Subsequent on—
    site soil sampling confirmed that remediation is necessary and
    that it will require removal of both soil and some of the tanks.
    (Pet. at ¶14—16; Tr. at p. 7—10.) As of the July 14, 1994
    hearing, the full areal extent of the contamination was yet to be
    The stipulation was characterized by the parties as a
    “joint motion to extend recommendation time of the variance”. To
    the extent that this filing constitutes a motion to file an
    amended recommendation and stipulation, the motion is hereby
    granted.

    —3—
    identified, pending Sweeney’s ability to gain access to off-site
    sampling locations. (Tr. at p. 8-9.)
    The Agency agrees that significant underground contamination
    exists at the site and remediation of this contamination is a
    prime concern. (Resp. Exh. 1 at p. 2.)
    Grant of the instant variance request would allow Sweeney to
    progress with the remediation prior to installation of the Stage
    II equipment.
    HARDSHIP
    AND ENVIRONMENTAL IMPACT
    Sweeney’s contends that requiring installation of the Stage
    II equipment prior to remediation would cause a financial
    hardship. Sweeney estimates that the Stage II equipment will
    cost $80,000. (Pet. at ¶19; Tr. at p. 10-11.) If installed
    prior to remediation, some of the Stage II equipment will have to
    be dismantled and removed during the remediation. Sweeney
    estimates the cost of the work and materials thus “wasted” during
    this short—term installation period to be $50,000 to $60,000.
    (a.)
    There are no control measures that could be temporarily
    imposed that would achieve immediate compliance in a manner less
    costly than Stage II implementation. (Pet. at ¶22.)
    Nevertheless, the parties stipulate that, unless the Stage II
    equipment is installed by March 31, 1995, the agreed upon date of
    termination of the variance, Sweeney will not dispense gasoline
    until the installation is complete. (Stip. at ¶4.)
    The Agency agrees that Sweeney would experience a hardship
    if it were required to install a Stage II system only to
    subsequently have it dismantled to allow for soil remediation.
    (Resp. Exh. 1 at p. 3.) The Agency adds that in particular it is
    likely that the underground vapor return lines to the gasoline
    storage tanks would have to be substantially redone, and that the
    costs of these lines are in agreement with the figures presented
    by Sweeney.
    (u.)
    Sweeney contends that the environmental harm that would be
    occasioned by delaying installation of the Stage II equipment
    would be negligible. In support of this position, Sweeney
    observes that according to the American Petroleum Institute
    emissions from a facility like Sweeney’s are estimated to be 11.7
    pounds of volatile organic material (VOM) per 1,000 gallons of
    fuel dispensed. (Pet. at ¶8; Pet. Exh. 1.) Sweeney dispenses an
    average of 108,000 gallons per month, and thus is estimated to
    produce VON emissions of 1,264 pounds per month or 0.2 tons per
    day. (Pet. at ¶8, ¶21.) Conversely, the total 1990 Chicago area
    VOM emissions were estimated to be 1453.69 tons per day;

    —4—
    Sweeney’s emissions are approximately .0014 percent of this
    total. (Pet. at ¶21.)
    The Agency agrees that the impact of delayed compliance
    would be small. (Resp. Exh. 1 at p. 2.) The Agency adds,
    however, that the Chicago area is still experiencing exceedences
    of the ozone ambient air quality standard, and that VOM emissions
    are a precursor to ozone formation; even small VOM emissions
    contributed to the ozone exceedences. (Id.)
    CONCLUSION
    The Board agrees with the Agency that Sweeney has
    demonstrated that installation of the Stage II equipment without
    allowing for a reasonable time to complete remediation would
    constitute a hardship for Sweeney. The Board also finds that, so
    long as the remediation is undertaken expeditiously, the
    accumulated environmental harm will be small and that the
    hardship thereby rises to the level of arbitrary or unreasonable
    hardship. On this basis, the Board will grant the requested
    relief with conditions.
    The principal condition is that Sweeney must have the
    necessary Stage II equipment installed by March 31, 1995. As the
    parties observe in their August 11, 1994 stipulation, if
    installed by March 31, 1995, Sweeney will be in compliance at the
    onset of the 1995 ozone season2. (Stip. at ¶4.) This will
    lessen the environmental harm that would otherwise occur if the
    variance extended into the 1995 ozone season.
    The Board also accepts as a necessary condition Sweeney’s
    commitment to suspend dispensing gasoline after March 31, 1995
    for any time during which “completion of installation” of Stage
    II equipment has not yet been achieved. “Completion of
    installation” is defined at 35 Ill. Adni. Code 218.586(a) (3) as
    the successful passing of at least one of several specified Stage
    II installation tests.
    ORDER
    J.M. Sweeney Co. is hereby granted variance from 35 Iii.
    Adm. Code 218.586 for its facility located at 1557 S. Central
    Avenue, Cicero, Illinois, subject to the following conditions:
    1) Variance expires on March 31, 1995;
    2 The ozone season is defined by the United States
    Environmental Protection Agency as the period from April 1
    through October 31.

    —5—
    2) Petitioner shall notify the Illinois Environmental
    Protection Agency of the installation of Stage II
    equipment by letter posted to:
    Mr. Terry Sweitzer, P.E.
    Manager, Air Monitoring Section
    Division of Air Pollution Control
    P.O. Box 19726
    Springfield, Illinois 62794—9276;
    3) Should petitioner have failed to achieve completion of
    installation of Stage II vapor collection and control
    equipment, as defined at 35 Ill. Adm. Code
    218.586 (a) (3), by April 1, 1995, petitioner shall cease
    to dispense gasoline from all affected dispensing lines
    until such time as completion of installation is
    achieved.
    IT IS SO ORDERED.
    If Petitioner chooses to accept this variance subject to the
    above order, within 45 days of the date of this order Petitioner
    shall execute and forward to
    Rachel L. Doctors
    Division of Legal Counsel
    Illinois Environmental Protection Agency
    2200 Churchill Road
    Post Office Box 19276
    Springfield, Illinois 62794—9276
    a Certification of Acceptance and Agreement to be bound to all
    terms and conditions of this variance. The 45-day period shall
    be held in abeyance during any period that this matter is being
    appealed. Failure to execute and forward the Certificate within
    45 days renders this variance void and of no force and effect as
    a shield against enforcement of rules from which variance was
    granted. The form of said Certification is as follows:
    CERTIFl CATION
    I (We),
    hereby accept and agree to be bound by all terms and conditions
    of the order of the Pollution Control Board in PCB 93-257,
    September 1, 1994.
    Petitioner
    Authorized Agent

    —6—
    Title
    Date
    Section 41 of the Environmental Protection Act (415 ILCS
    5/41 (1992)) provides for the appeal of final Board orders within
    35 days of the date of service of this order. The Rules of the
    Supreme Court of Illinois establish filing requirements. (See
    also 35 Ill.Adm.Code 101.246 “Motions for Reconsideration”.)
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opinion and order was
    adopted on the
    _________
    day of
    y-~()~tJ
    ,
    1994 by a
    vote of
    ____________-
    ~X
    /~.
    Dorothy M. ~unn, Clerk
    Illinois Pollution Control Board

    Back to top