ILLINOIS POLLUTION CONTROL BOARD
    March
    16,
    1995
    W.R. GRACE
    &
    CO.
    -
    CONN.,
    )
    Petitioner,
    )
    v.
    )
    PCB 94—328
    )
    (Variance
    -
    Air)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    KATHLEEN C.
    BASSI APPEARED ON BEHALF OF PETITIONER;
    BONNIE SAWYER APPEARED ON BEHALF OF RESPONDENT.
    OPINION
    AND
    ORDER OF THE BOARD
    (by M.
    McFawn):
    This matter is before the Board on a petition for variance
    filed by petitioner W.R. Grace
    & Co.
    -
    Conn.
    (Grace) on November
    16,
    1994.
    Grace seeks a variance from the air emission control
    requirements of 35
    Ill.
    Adm. Code 218.106(c),
    218.940(b),
    218.946,
    218.948, and the related recordkeeping requirements of
    218.Subpart UU for its facility at 6050 West 51st Street,
    Chicago, Cook County,
    Illinois.
    Grace requests that the variance
    begin March
    1,
    1995 and end March 15,
    1996.
    The Board’s responsibility in this matter arises from the
    Environmental Protection Act
    (Act)
    (415 ILCS 5/1 et seq.
    (1992).)
    The Board is charged therein with the responsibility of granting
    variance from Board regulations whenever it is found that
    compliance with the regulations would impose an arbitrary or
    unreasonable hardship upon the petitioner.
    (415 ILCS 5/35(a).)
    The Illinois Environmental Protection Agency
    (Agency)
    is required
    to appear
    in hearings on variance petitions.
    (415 ILCS 5/4(f).)
    The Agency
    is charged,
    among other matters, with the
    responsibility of investigating each variance petition and making
    a recommendation to the Board as to the disposition of the
    petition.
    (415 ILCS 5/37(a).)
    Pursuant to 35 Ill.
    Adm. Code 104.180(a), the Agency
    recommendation was originally due December 15,
    1994.
    On December
    19,
    1994, the Agency filed a motion for extension of time in
    which to file its recommendation,
    seeking an extension until
    January 12,
    1995, which the Board granted by order dated January
    11,
    1995.
    The Agency filed its variance recommendation (Rec.)
    on
    January 13,
    1995.
    Based on information contained in the petition
    for variance and information subsequently submitted to the Agency
    by Grace,
    the Agency agrees that an unreasonable hardship would
    be imposed on Grace in the absence of the requested relief, and
    recommends that the variance be granted, subject to certain
    conditions.

    2
    A hearing was held in this matter on January
    18,
    1995 before
    hearing officer June C.
    Edvenson.
    Kathleen C.
    Bassi appeared on
    behalf of Grace, and Richard N.
    Irelan,
    Environmental Health and
    Safety Manager for Grace’s Chicago facility,
    and Aaron
    G. Abbott,
    Associate Process Engineer for Grace, testified on Grace’s
    behalf.
    Bonnie Sawyer appeared on behalf of the Agency,
    and
    Christopher Romaine testified on the Agency’s behalf.
    Grace
    filed its post-hearing brief on February 6,
    1995, and the Agency
    filed its response brief on February
    10,
    1995.
    Grace filed a
    reply to the Agency response on February 16,
    1995.1
    Additionally, Grace filed a motion to correct the transcript on
    February 15,
    1995, which the Board hereby grants.
    As presented below,
    the Board finds that petitioner has met
    its burden of demonstrating that immediate compliance with the
    requirements of 35
    Ill.
    Adm. Code 218.106(c),
    218.940(b),
    218.946,
    218.948,
    and the related recordkeeping requirements of
    2l8.Subpart
    UTJ
    would impose an arbitrary or unreasonable hardship
    upon petitioner.
    The variance request
    is therefore granted,
    subject to certain conditions recommended by the Agency.
    BACKGROUND
    Grace operates a facility located at 6050 West 51st Street,
    Chicago, Cook County,
    Illinois.
    (Petition
    (Pet.)
    at 1—2.)
    The
    facility was established
    in 1940,
    and currently employs
    approximately 100 people.
    (~.
    at 2.)
    At this facility,
    Grace
    manufactures container sealants, automotive products,
    lubricant
    fuels,
    and concrete additives.
    The container sealants are a
    rubbery coating material used by beverage,
    food, and other can
    coaters to form
    a seal between the ends of cans and the body of
    the can where the two pieces are crimped together.
    The plant
    uses both solvent—based and water—based sealants.
    (Id)
    Production of the solvent—based can sealant results in the
    greatest amount of VOM emissions from the Grace plant.
    (u.)
    Grace asserts that the emissions from the other processes are
    insignificant, and subject to exemptions from control
    (Tr. at 14—
    15;
    see
    discussion
    infra.)
    The solvent—based can sealants are
    produced in a batch process by mixing compounded rubber and other
    materials into the solvent in a solvation mixer.
    I
    Pursuant to Section 101.241(c)
    of the Board’s procedural
    rules, parties do not have the right to file a reply without
    leave of the Board.
    (35 Ill. Adm. Code 101.241(c).)
    Petitioner
    did not file a request for leave to file a reply;
    however,
    in the
    interests of judicial economy, the Board will accept petitioner’s
    reply.

    3
    Grace’s facility has a total of
    9 solvent lining compound
    (SLC) mixers.
    (Pet.
    at 3,
    Tr. at
    15.)
    The compounded rubber and
    other materials are loaded into the mixer through access hatches
    in the mixer neck either manually by operators or by conveyor
    belts.
    Solvent and other materials are piped from storage tanks
    into the mixer.
    The compounds are subsequently pumped to
    blend/storage tanks where low speed agitation continues.
    In most
    cases, additional solvent is added,
    and the product
    is recycled
    through a homogenizer to attain proper consistency.
    The finished
    product
    is then loaded into tank trucks,
    drums,
    or other
    containers for distribution to customers.
    (Pet.
    at 3.)
    Because the VON emissions from the solvation mixers are
    flammable,
    Grace has installed a Halon 1301 fire suppression
    system.
    (Petitioner’s Post-Hearing Br.
    (Pet.
    Br.) at 4.)
    This
    system uses ultraviolet eyes to monitor the mixer necks for
    sparks or flame.
    (Tr. at 24.)
    Additionally, the solvation mixer
    room is highly humidified to reduce the potential for static
    electrical sparking.
    (Pet.
    Br.
    at
    4;
    Tr.
    at 23.)
    The majority of emissions occur at the mixers during two
    different activities:
    loading and mixing.
    The loading emissions
    are fugitive in nature, and occur through displacement when
    materials are added to the mixers through the access hatches.
    (Pet.
    Br. at 4.)
    These emissions are very “peaky”
    in nature.
    (Pet.
    Br.
    at
    5;
    Tr. at 160.)
    The emissions rate rises to its
    peak value within seconds when materials such as rubber are added
    to the mixer
    (Tr.
    at 18),
    and the maximum emissions rate is much
    larger than the emissions rate averaged over time
    (Tr. at 17).
    Grace seeks the requested variance
    in order to develop and
    implement proper controls for these emissions.
    Mixing emissions occur when the contents of the mixers are
    being stirred.
    The mixing emissions pass through vent pipes
    after the access hatches are closed.
    Material recovery devices
    condense and return to the mixers the vast majority of the
    solvent fumes generated during the mixing operation.
    (Pet.
    at
    3.)
    Grace estimates that emissions from this solvation process,
    when combined with the insignificant levels of emissions from the
    other processes,
    amount to potential VON emissions of 98 tons per
    year
    (TPY).
    (Pet.
    at 2.)
    However, Grace estimates that actual
    total VON emissions are approximately 35 TPY.
    (~~)
    APPLICABLE LAW
    Subpart QQ requires sources with the potential to emit
    (PTE)
    25 tons per year or more of volatile organic material
    (VOM) to
    reduce VON emissions by 81 percent overall from each emission
    unit.
    (35 Ill. Adm. Code 218.946.)
    Compliance
    is required by
    March 15,
    1995.
    (35 Ill. Adm. Code 218.106(c).)
    Since Grace’s

    4
    facility has potential VOM emissions
    of
    98 tons per year,
    these
    restrictions apply to Grace’s facility.
    Grace asserts that exemptions apply to emissions from its
    processes other than the loading emissions from its SLC mixers.
    Section 218.940 exempts emission units included in the VOC
    storage tank category under Section 218.940(b)(l)(B).
    Grace
    estimates that its emissions in this category are approximately
    8.5 tons.
    (Tr.
    at 14.)
    Section 219.940(b) (2) (A)
    exempts from
    control requirements emissions units which are included
    in
    Subpart
    B, Organic Emissions from Storage and Loading Operations.
    Grace’s emissions in this category have been estimated at
    approximately 3.3 tons per year.
    (Tr. at 15.)
    Finally,
    Section
    218.940(d) provides an exemption which applies to the solvent
    process mixing activities,
    non—bulk packaging activities, piping
    fugitive emissions and non-bulk packaging activities of the
    Waterbased Can Sealing Compound and Can—Forming Lubricant
    processes,
    since they emit less than 2.5 tons per year per
    emission unit,
    or
    5 tons per year
    in combination. The total
    emissions from this group of emission sources
    is estimated to be
    4.6 tons per year.
    (Tr.
    at
    15.)
    Therefore the petition only
    contemplates controlling the remaining emissions,
    estimated at
    19.2 tons per year,
    which result from the loading activities at
    the mixers.
    The Agency does not dispute the application of these
    exemptions to the described emissions.
    (Agency Recommendation
    (Ag.
    Rec.)
    at Section II para.
    8-11.)
    HARDSHIP
    Grace has determined that the most appropriate method of
    control for its process
    is the installation of a thermal oxidizer
    and fume capture system.
    (Pet.
    at 4.)
    Grace estimates that the
    purchase and installation of such a system will cost
    approximately $500,000.00, with annual operating costs of
    approximately $100,000.00.
    (Pet.
    at 4-5.)
    However, Grace
    alleges that it will be unable to complete installation of the
    control device
    in a timely manner due to difficulties arising
    from the nature of its process and certain design limitations
    which must be met.
    (Pet at.
    5.)
    Grace therefore asserts that
    meeting the March 15,
    1995 compliance date would impose an
    arbitrary and unreasonable hardship on its facility.
    (See Pet.
    Br. at 12.)
    Nature of Emissions
    Grace asserts that its emissions occur in a complex and
    variable manner due to the batch nature of
    its process.
    (Pet.
    at
    4.)
    There are many variations of formulas used in the batches,
    and modelling the typical emissions profile is very difficult.
    (Tr. at 18.)
    Grace asserts that the “peaky” nature of the

    5
    emissions stream presents challenges to those designing the
    control system.
    (Pet.
    Br. at
    5;
    Tr. at
    17.)
    This emissions
    profile requires that the control unit be significantly larger
    than one sized for the average emissions of the process, and
    requires that the thermal oxidizer burn supplemental heating fuel
    during non—peak periods to maintain an efficient temperature.
    (Tr.
    at 17.)
    The actuators which control the input of additional
    fuel will also undergo more frequent mechanical cycling than
    would normally be expected in this type of control device.
    (Tr.
    at 18.)
    The Agency acknowledges that the “peaky” nature of
    petitioner’s emissions may create the need for a larger, more
    sophisticated control device, but does not believe that this
    creates any undue hardship.
    (Ag. Rec.
    at XX.)
    The Agency points
    out that such fluctuations occur with many processes.
    In
    response to petitioner’s assertion that the variety of
    compositions mixed in the emission units contributes to its
    hardship, the Agency acknowledges that this factor must be
    included in the control scheme,
    but does not believe that it
    creates any undue hardship.
    Design Reguirements
    Grace has encountered additional difficulties in designing a
    VON capture system that accommodates its operational needs and
    existing space constraints.
    Grace asserts that the available
    floorspace and headspace in the relevant area surrounding the
    mixers
    is very limited.
    Special care must be taken to design a
    system which allows full operator access to the mixer necks for
    dumping in materials,
    taking samples,
    and performing other
    activities,
    as well as allowing the addition of material by means
    of the conveyor belts.
    (Tr.
    at 21.)
    The system must also be
    designed so as not to interfere with the effectiveness of the
    fire suppression system.
    (Tr. at 25.)
    Grace has encountered additional design difficulties
    in
    dealing with dust generated during the dumping of solid raw
    materials into the mixers.
    (Tr.
    at 21.)
    Because dusts could
    adhere to the oxidizer’s catalysts, reducing the oxidizer’s
    efficiency,
    the system must be equipped with air filters which
    separate out these dusts and prevent them from reaching the
    thermal oxidizer.
    (Tr.
    at 22.)
    However, the installation of
    such a filter presents further design difficulties,
    since the
    filter may become caked with dust,
    reducing the flow of air into
    the capture system.
    Grace asserts that many of the materials are
    sticky in nature and will tend to coat the catalyst bed.
    (Pet.
    Br. at 5;
    Tr.
    at 22.)
    Additionally, since the room is
    intentionally humidified,
    the high humidity level may exacerbate
    the caking of dust on filters.
    (Tr. at 23.)
    Grace must verify
    the effectiveness of the capture system and its filters prior to
    finalizing design of the thermal oxidizer.

    6
    The Agency believes that these circumstances create
    significant design challenges for installing control equipment,
    and establish a sufficient hardship to allow additional time for
    compliance as requested by petitioner.
    (Ag.
    Rec.
    at XVII
    -
    XIX.)
    Testing
    Grace also asserts that there will be difficulties in
    testing with conventional methods.
    Since the emissions rate is
    variable from second to second, methods such as Method 25A may be
    inadequate to accurately quantify emissions.
    (Tr.
    at 18.)
    The
    Agency’s recommendation does not address this issue.
    COMPLIANCE
    PLAN
    In its petition,
    Grace estimates that
    it will take six
    months to define the scope of the appropriate control scheme,
    finalize design,
    specification, and process safety review for the
    control scheme, and place
    its order for the equipment.
    (Pet.
    at
    5.)
    Grace estimates that it will take four months to build the
    unit,
    and another month to install
    it.
    (Pet.
    at 5.)
    At the
    request of the Agency,
    Grace submitted to the Agency a more
    detailed compliance plan,
    which included the following compliance
    milestones:
    1.
    File a construction permit application for the control
    system with the Agency by March
    1,
    1995.
    2.
    Complete installation of the capture system and issue a
    purchase order for the thermal oxidizer by June 15,
    1995.
    3.
    Initiate installation of the thermal oxidizer by
    December 15,
    1995.
    The Agency accepted and incorporated each of these
    milestones into its recommendation,
    and recommended that they be
    included as conditions
    in the variance.
    (Ag. Rec.
    at VIII.)
    Additionally, the Agency recommended that the following condition
    be added:
    4.
    PetitiOner shall start-up the thermal oxidizer by
    February 15,
    1996.
    (Ag. Rec.
    at VIII.)
    In its recommendation,
    the Agency recommended that
    satisfying the requirements of these- milestones be conditions
    precedent to the continuing validity of the variance.
    (Ag.
    Rec.
    at IX.)
    In its response brief,
    the Agency clarified its
    position on this issue,
    stating that the Agency intends that
    failure to satisfy any milestone would mean that Grace is in

    7
    violation of the variance and no longer entitled to a shield from
    enforcement based on the variance.
    (See Agency Response Br.
    Section II.)
    Grace agrees to the inclusion of these milestones
    in the
    variance
    (Pet.
    Br.
    at 3), but objects to their satisfaction being
    conditions precedent to the continuing validity of the variance
    (Pet.
    Br.
    at 9).
    Grace asserts that the terms of the variance
    are subject to enforcement under the Act, and that it is
    unnecessary to void the variance based on failure to satisfy
    these conditions.
    While we find that it is appropriate to include the
    milestones as a means
    of assuring compliance by the expiration of
    the variance, we find it unnecessary to treat them as conditions
    precedent to the continuing validity of the variance.
    The terms
    of the variance are enforceable as a Board order,
    and violation
    of the terms
    of the variance will subject its holder to
    enforcement in accordance with Section 42 of the Environmental
    Protection Act.
    (See Section 33(d)
    of the Act.)
    Under these
    circumstances, the existence of the variance will not shield the
    holder from enforcement against such
    a violation.
    However, the
    variance itself will not be voided.
    We will therefore include
    the milestones in the variance, but will also include language
    which properly defines the enforceability of the variance terms.
    (See
    also
    Auburn,
    Divernon,
    Girard,
    Pawnee, Thaver,
    Virden Water Commission v.
    IEPA,
    PCB 94-86
    (Nay 5,
    1994).)
    Additionally, we note that the recommended March
    1,
    1995
    compliance date for milestone number
    (1), requiring that
    petitioner file a construction permit application for the control
    system, has already passed.
    In order to avoid subjecting
    petitioner to this requirement retroactively, we will extend the
    compliance date for milestone number
    (1) to March 30,
    1995.
    ENVIRONMENTAL IMPACT
    Grace asserts that the environmental impact of the requested
    variance will not exceed current levels.
    (Pet.
    at 6.)
    Grace
    indicates that the emission levels of VOM may actually decrease,
    due to additional process improvements and decreased demand for
    the solvent—based
    sealants.
    (Pet. at
    4,
    6.)
    Grace asserts that
    granting this variance will not impede the State’s ability to
    demonstrate a 15
    reduction in VOM emissions in the Chicago ozone
    non-attainment area by the end of 1996,
    as required by Section
    182(b) (1)
    of the Clean Air Act,
    42 USC 7411a(b)(l).
    (Pet.
    Br.
    at
    10—11.)
    Grace further asserts that its emissions control at the
    end of the variance will exceed the emission reduction
    requirements of Subpart QQ by
    16 tons annually.
    (Pet.
    Br.
    at 10.)

    8
    The Agency acknowledges that the requested variance will
    allow emissions during the 1995 ozone season.
    However, the
    Agency believes that the hardship Grace will suffer
    if timely
    compliance is required outweighs the environmental impact from
    allowing uncontrolled VON emissions through the 1995 ozone
    season.
    (Ag. Rec. at VII.)
    CONSISTENCY WITH
    FEDERAL
    LAW
    Section 104.122(a)
    of the Board’s procedural rules requires
    that all petitions for variance from the Board’s air pollution
    regulations indicate whether the Board can grant the requested
    relief consistent with the federal Clean Air Act and the
    regulations adopted pursuant thereto.
    Furthermore,
    Section
    218.108(a)
    of the Board’s air regulations requires that all
    exemptions, variations or alternatives to the air emission
    control requirements, emissions limitations,
    or test methods be
    approved by the United States Environmental Protection Agency
    (USEPA)
    as a SIP revision before becoming effective.
    (35 Ill.
    Adm. Code 218.108(a).)
    Grace asserts that the requested variance can be granted
    consistent with federal law.
    (Pet. at
    7.)
    Grace states that
    under the currently applicable Federal Implementation Plan (FIP),
    only facilities which emit more than 100 TPY are subject to
    regulation.
    (Pet~at 8.)
    Furthermore, USEPA has not yet
    approved Subpart QQ of the State Implementation Plan
    (SIP).
    However, Grace concedes that the variance will ultimately have to
    be submitted to USEPA as a SIP revision, and Grace has requested
    that the Agency submit the requested variance as an amendment to
    the SIP once the SIP is approved.
    (Pet.
    at 8.)
    Furthermore,
    the
    hearing held in this matter satisfies the federal public
    participation requirements under the
    CAA
    and related regulations.
    (Pet.
    at 9.)
    In its recommendation,
    the Agency does not dispute that the
    requested variance can be granted consistent with federal law.
    The Agency notes that granting this variance would allow Grace,
    as a major source in the Chicago non—attainment area,
    to emit
    uncontrolled VON emissions beyond the May 31,
    1995 deadline for
    implementation of reasonably available control technology
    (RACT).
    However, the Agency acknowledges that these emissions will only
    be significant during the ozone season.
    The Board finds that petitioner has satisfied the necessary
    conditions for granting the requested variance consistent with
    federal law.
    The public hearing satisfies the applicable notice
    requirements, and Grace has properly requested the Agency to
    submit the requested variance to USEPA as a SIP revision.

    9
    CONCLUSION
    In determining whether any variance
    is to be granted, the
    Act requires the Board to determine whether the petitioner has
    presented adequate proof that immediate compliance with the Board
    regulations at issue would impose an arbitrary or reasonable
    hardship upon the petitioner
    (415 ILCS 5/35(a)
    (1992)).
    The
    burden
    is on the petitioner to demonstrate that the claimed
    hardship outweighs the public interest in attaining compliance
    with regulations designed to preserve the environment and protect
    human health.
    (Willowbrook Motel v.
    IPCB
    (1985),
    135 Ill.App.3d
    343,
    481 N.E.2d 1032.)
    The Board hereby finds that immediate compliance with the
    requirements of 35 Ill.
    Adm. Code 218.106(c),
    218.940(b),
    218.946,
    218.948, and the related recordkeeping requirements of
    218.Subpart UU would constitute an arbitrary and unreasonable
    hardship for petitioner.
    Petitioner has made such demonstration
    based on the difficulties encountered in designing an appropriate
    control system under the existing space and process constraints.
    While there will be some impact to the environment from the
    uncontrolled emissions of VON during the 1995 ozone season, the
    emissions will be no greater than those currently emitted, and
    there will ultimately be an environmental benefit due to Grace’s
    over—compliance with the emissions reduction requirements of
    Subpart QQ.
    We therefore find that the environmental impact
    is
    outweighed by the hardship that would be imposed on petitioner by
    immediate compliance.
    We also find that petitioner has
    demonstrated that the requested variance can be granted
    consistent with federal
    law.
    The Board therefore grants the requested variance, subject
    to the conditions contained in the order below.
    Language has
    been added to the variance order which clarifies that the terms
    of the variance are enforceable as a Board order in accordance
    with Section 42 of the Act.
    However, failure to satisfy the
    terms of the variance does not void the continuing validity of
    the variance.
    While petitioner has requested and the Agency has
    recommended that the variance be effective starting March
    1,
    1995,
    the Board’s well established practice is that the term of a
    variance begins on the date the Board renders its decision,
    unless unusual or extraordinary circumstances are shown.
    (See,
    e.g. DM1.
    Inc.
    v.
    IEPA,
    PCB 90-227,
    128 PCB 245
    -
    249, December
    19,
    1991.)
    Given the complexity of factors which Grace must
    consider
    in designing its control system, and the fact that the
    regulations- from which Grace
    is seeking a variance became
    effective March 15,
    1995, the Board finds that the instant
    circumstances warrant a one—day retroactive start of the
    variance.
    The variance will therefore become effective March
    15,
    1995.

    10
    This opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    A.
    W.R. Grace
    & Co.
    Conn.
    is hereby granted a variance from
    the air emission control requirements of 35
    Ill.
    Adm. Code
    218.106(c),
    218.940(b),
    218.946, 218.948, and the related
    recordkeeping requirements of 218.Subpart UU for its
    facility at 6050 West 51st Street,
    Chicago, Cook County,
    Illinois, subject to the following conditions:
    1.
    The variance begins on March 15,
    1995 and ends March 15,
    1996.
    2.
    Petitioner shall meet the following compliance milestones:
    a.
    Petitioner shall file its construction permit
    application for the control system with the Illinois
    Environmental Protection Agency
    (Agency)
    by March 30,
    1995.
    b.
    Petitioner shall complete installation of the capture
    system and issue a purchase order for the thermal
    oxidizer by June 15,
    1995.
    c.
    Petitioner shall initiate installation of the thermal
    oxidizer by December 15,
    1995.
    d.
    Petitioner shall start-up the thermal oxidizer by
    February 15,
    1996.
    3.
    The catalytic oxidizer shall be fully operational by March
    15,
    1996, and in conjunction with the capture system,
    shall
    reduce VON emissions by 81 percent overall,
    as required by
    35
    Ill. Adm. Code 218.946.
    4.
    Petitioner shall conduct any tests requested by the Agency
    in the construction permit to establish compliance with
    Subpart QQ and submit the results of all such tests to the
    Agency as required in such permit but in no case later than
    March 15,
    1996.
    5.
    Petitioner shall not exceed its current level of VON
    emissions during the variance period.
    6.
    Petitioner shall promptly notify the Agency of attainment of
    each compliance milestone provided above.
    Notification
    shall be sent to:

    11
    Compliance Unit
    Illinois Environmental Protection Agency
    Bureau of Air
    P.O. Box 19276
    Springfield, Illinois 62794—9276
    7.
    Failure to comply with the conditions of this Board order
    shall constitute a violation of this Board order and subject
    petitioner to the enforcement and penalty provisions of the
    Environmental Protection Act.
    IT IS SO ORDERED.
    If W.R. Grace
    & Co.
    -
    Conn. chooses to accept this variance
    subject to the above order, within 45 days of the date of this
    order, W.R. Grace
    & Co.
    -
    Corin.
    shall execute and forward the
    attached Certificate of Acceptance and Agreement to:
    Bonnie Sawyer
    Division of Legal Counsel
    Illinois Environmental Protection Agency
    2200 Churchill Road
    Post Office Box 19276
    Springfield, Illinois 62794—9276
    Once executed and received, the Certificate of Acceptance
    and Agreement shall bind petitioner to all the terms and
    conditions of this variance.
    The 45-day period shall be held in
    abeyance during any period that this matter is being appealed.
    Failure to execute and forward the Certificate within the 45 days
    renders this variance void.
    The form of said Certification shall
    be as follows:

    12
    CERTIFICATION
    I
    (We),
    hereby accept and agree to be bound by all terms and conditions
    of the order of the Pollution Control Board in PCB 94-328,
    March
    16,
    1995.
    Petitioner
    Authorized Agent
    Title
    Date
    Section 41 of the Environmental Protection Act
    (415 ILCS
    5/41
    (1992) provides for the appeal of final Board orders within
    35 days of the date of service of this order.
    The Rules of the
    Supreme Court of Illinois establish filing requirements.
    (See
    also 35 Ill.
    Adm. Code 101.246, Motions for Reconsideration)
    I, Dorothy N. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opinion and order was
    adopted on the
    ~
    day of
    ~
    ,
    1995,
    by a vote
    of
    7-c~3
    Dorothy M. ~nn,
    Clerk
    Illinois Pollution Control Board

    Back to top