ILLINOIS POLLUTION CONTROL BOARD
March 9, 1995
SHELL OIL COMPANY,
)
)
Petitioner,
V.
)
PCB 95—86
)
(Provisional Variance-Air)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
ORDER OF THE BOARD (by M. McFawn):
Pursuant to Section 35(b) of the Environmental Protection
Act (Act) (415 ILCS 5/35(b)), Shell Oil Company has requested
that the Illinois Environmental Protection Agency (Agency)
recommend that the Board grant a provisional variance allow
several of Shell Oil Company’s gasoline dispensing operations
(service stations) to continue operating even though it will not
install operational vapor recovery equipment by the expiration of
a prior provisional variance on January 29, 1995. This
provisional variance is being requested because the stations will
be demolished, and will be rebuilt and equipped with Stage II
gasoline vapor recovery equipment during the rebuild. The
Notification of Recommendation and the request for a provisional
variance were filed with the Board by the Agency on Tuesday,
March 7, 1995. Pursuant to Section 35(b) of the Act, the Board
must issue the variance within two (2) days of this filing.
Specifically, the Agency recommends that we grant Shell Oil
Company a forty—five (45)-day provisional variance for three of
its facilities located in Cook County, in the Chicago
metropolitan statistical area from the Stage II vapor recovery
requirements, as set forth in 35 Ill. Adm. Code 218.586, for the
period beginning February 8, 1995 and continuing for forty-five
(45)-days or until demolition commences at the three facilities,
whichever comes first.
This recommendation is essentially that the Board extend a
previously-granted forty-five (45)-day provisional variance that
expired January 29, 1995. The docket number of the previous
provisional variance was PCB 95-35, granted on January 11, 1995.
That prior provisional variance was itself an extension of the
forty—five (45)—day provisional variance granted on December 1,
1994 in PCB 94—319.’
Section 36(c) of the Act imposes limitations on the
Board’s ability to extend a provisional variance:
2
The Agency’s provisional variance recommendation states that
Mobil has requested a provisional variance on behalf of numerous
of its service stations in the Chicago area, located as follows:
County
City or Village Street Address
Cook
Arlington Heights 934 S. Arlington Heights Rd
Cook
Arlington Heights 3 West Algonquin Road
Cook
Glenview
2000 West Willow Road
Upon receipt of the request, the Agency issued its
recommendation, notifying the Board that the failure to grant the
requested forty—five (45)—day provisional variance would impose
an arbitrary or unreasonable hardship on the petitioner.
Provisional variances are by their very nature temporary.
The responsibilities of the Agency and the Board in these short-
term provisional variances are different from the
responsibilities in standard variances.
~
415 ILCS 5/35(b) &
36(c)). In provisional variances it is the responsibility of the
Agency to make the technical determinations and finding of
arbitrary or unreasonable hardship. The Board’s responsibility
is to adopt a formal order, to assure the formal maintenance of
the record, to assure the enforceability of the variance, and to
provide notification of the action by a press release.
Having received the Agency recommendation notifying the
Board that a denial of the requested relief would impose an
arbitrary or unreasonable hardship, the Board hereby grants the
petitioner a provisional variance from 35 Ill. Adm. Code 218.586,
subject to the following conditions:
1. The term of this provisional variance shall commence on
Any provisional variance granted by the Board pursuant
to subsection (b) of Section 35 shall be for a period
of time not to exceed 45 days. Upon receipt of a
recommendation from the Agency to extend this time
period, the Board shall grant up to an additional 45
days. The provisional variances granted to any one
person shall not exceed a total of 90 days during any
calendar year.
Since the variance granted in PCB 95-35 expired January 29, 1995,
and fewer than ninety (90) days will have elapsed in this
calendar year by the expiration of the variance requested in the
present petition, the Board interprets Section 36(c) as allowing
Shell Oil Company the Agency-recommended forty—five (45)-day
extension.
3
February 8, 1995 and continue for forty-five (45)-days or
until demolition commences at the three facilities,
whichever comes first.
2. The petitioner shall notify the Agency upon
installation of the Stage II gasoline vapor recovery
equipment, by sending notification addressed as follows:
Mr. Terry Sweitzer, P.E.
Manager, Air Monitoring Section
Illinois Environmental Protection Agency
Division of Air Pollution Control
P.O. Box 19276
Springfield, Illinois 62794—9276
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Boar4, do hereby certify that the above order was adopted on the
‘~‘~-
day of
__________________________,
1995, by a vote of
I
Control Board