    Theodore Meyer):
    On March
    1,
    1995 the parties filed a joint status report
    pursuant to a hearing officer’ order of February
    1,
    1995.
    The
    parties claim they have worked diligently toward resolution of
    all outstanding issues
    in connection with the stormwater runoff
    at petitioner’s Graham Mine,
    Galena,
    Illinois.
    In late January
    of 1995 respondent issued
    a revised draft permit which petitioner
    is currently reviewing.
    The parties are confident this matter
    will be resolved within thirty days.
    Petitioner concurrently
    filed a waiver of the Board’s Decision Deadline until July 30,
    1995.
    The Board accepts the joint status report and directs the
    parties to file
    a new joint status report on or before April
    3,
    1995. Should
    a hearing be required
    in this case,
    the Board
    requires 120 days to schedule a hearing, transmit a record to the
    Board,
    file briefs and issue an opinion and order.
    Therefore,
    if
    this matter is not resolved by April
    3,
    1995 and there is no
    further waiver of the Board’s decision deadline, the hearing
    officer shall schedule hearing in this matter.
    IT IS SO ORDERED.
    I,
    Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above order was adopted on~he
    9’~
    day of
    ‘77~
    -c~L~-
    ,
    1995, by a vote of
    ~
    Dorothy M./~unn, Clerk
    Illinois E~jSllutionControl Board
    The parties incorrectly cite to the hearing officer order
    of February
    1,
    1995 as a Board order.