ILLINOIS POLLUTION CONTROL BOARD
April 20,
1995
THE FINISHING COMPANY,
)
)
Petitioner,
)
V.
)
PCB 95—132
)
(Provisional Variance-RCRA)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
ORDER OF THE BOARD (by
C.
A.
Manning):
Pursuant to Section 35(b)
of the Environmental Protection
Act
(Act)
(415 ILCS 5/35(b)), The Finishing Company has requested
that the Illinois Environmental Protection Agency
(Agency)
recommend that the Board grant a provisional variance to allow
The Finishing Company’s facility in Cook County to continue
accumulating hazardous waste for a period in excess of ninety
(90)
days.
Such request for a provisional variance and the
Notification of Recommendation were filed with the Board by the
Agency on Wednesday, April
19,
1995.
Pursuant to Section 35(b)
of the Act, the Board must issue the variance within two
(2)
days
of this filing.
Specifically, the Agency recommends that we grant a thirty—
one (31)-day provisional variance from the ninety (90)-day
limitation on the accumulation of hazardous wastes,
as set forth
in 35 Ill. Adm. Code 722.134(b), for the period from April 10,
1995 to May 10,
1995.
Upon receipt of the request, the Agency issued its
recommendation, notifying the Board that due to unforeseen,
temporary and uncontrollable circumstances, failure to grant the
requested thirty—one
(31)—day provisional variance would impose
an arbitrary or unreasonable hardship on the petitioner.
Provisional variances are by their very nature temporary.
The responsibilities of the Agency and the Board in these short-
term provisional variances are different from the
responsibilities in standard variances.
(~
415 ILCS 5/35(b)
&
36(c)).
In provisional variances it is the responsibility of the
Agency to make the technical determinations and finding of
arbitrary or unreasonable hardship.
The Board’s responsibility
is to adopt a formal order,
to assure the formal maintenance of
the record, to assure the enforceability of the variance, and to
provide notification of the action by a press release.
Having received the Agency recommendation notifying the
Board that a denial of the requested relief would impose an
arbitrary or unreasonable hardship, the Board hereby grants the
2
petitioner a provisional variance from 35 Iii. Adm. Code
722.134(b)
April 10, 1995 to May 10,
1995.
IT IS SO ORDERED.
I, Dorothy N. Gunn,
Clerk of the Illinois Pollution Control
Board,
do hereby certify that the above order was adopted on the
~~Y~2~-day of __________________________,
1995,
by a vote of
7—c
.
7L.
Dorothy M,/~unn,Clerk