ILLINOIS POLLUTION CONTROL BOARD
    October
    26,
    1971
    MARS DEVELOPMENT CO.
    v.
    )
    #
    71—218
    ENVIRONMENTAL PROTECTION AGENCY
    MARVIN WASSERMAN et al.
    v.
    )
    #
    71—219
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion and Order
    of the Board
    (by Mr. Currie):
    These consolidated petitions
    seek variances to allow the
    connection of thirty-three
    new homes
    and
    a department store to sewers
    tributary to the Waukegan sewage treatment plant of the North
    Shore Sanitary D:strict,
    a plant which, because
    of
    its overloaded
    condition,
    is
    subject
    to
    the prohibition
    of new sewer connections
    imposed in ~ 70—7,
    League
    of Women Voters v.
    North Shore Sanitary
    District
    (March
    31,
    1971).
    Because construction had not begun at the time the ban was
    imposed,
    the connections here sought do not come within the precedent
    of such cases as Wachta
    V.
    EPA
    #
    71—77
    (July 12,
    1971);
    we are
    not
    faced with
    bhe Drospect of finished or half—completed buildings
    standing vacant prey to vandals and vermin.
    Wachta and other cases,
    e.g.,
    Wagnon
    V.
    EPA,
    # 71-83
    (July 19,
    1971)
    ,
    have made clear
    that
    in
    the absence of other compelling circumstances
    it i~insufficient
    that such imerovements
    as sewer
    and water lines and streets have
    been constructed,
    as
    they have
    in this case,
    since the improvements
    will still be there when the treatment plant is upgraded and the
    ban
    liftecL
    The impact of expenditures
    for such improveittents
    in
    the present cases, moreover,
    is
    lessened further by the fact that
    the improvements
    are presently servicing fifty-three existing
    homes in the same
    subdivision as well as
    a National Tea store
    (R.
    129).
    Nor have we in
    the
    eresent cases
    the special hardship
    involved
    in
    interdicting
    a project that would provide housing
    for
    those of
    inacleguate
    means
    those
    oresent
    living
    conditions
    are
    intolerable
    as
    in
    McAclams
    V.
    EPA,
    #
    71-113
    (August
    5,
    1971)
    ,
    or
    Patricia
    Development
    Co.
    V.
    EPA,
    ~
    71-161
    (September
    16,
    1971).
    The
    present
    cases,
    however,
    present
    an
    ingenious
    new
    twist
    that prompted
    us
    to hold
    a hearing in the hopes that it
    could
    be
    demcn~trated
    that
    the
    connection
    would
    not
    have
    an
    adverse
    effect
    upon
    the
    environment.
    The
    petitioners
    propose
    to
    construct
    four
    10,000-gallon
    holding
    tanks,
    which
    assertecily
    will
    suffice
    to
    collect
    and
    hold
    two days
    accumulation
    of wastes not only
    from their own
    2
    -~
    689

    proposed new buildings but from the existing homes and store
    in
    the subdivision
    as well.
    This waste would then be discharged at
    night, when present flows
    to the treatment plant are
    at their
    lowest
    (R.
    206—07, 219—21,
    253,
    255).
    The intention is to take
    advantage of
    the fact that, although
    the plant is badly overloaded
    in the daytime,
    it
    is
    in much better condition at night.
    Flow records from the North Shore Sanitary District corroborated
    this important
    fact insofar
    as dry weather flow is concerned,
    Raymond
    Anderson,
    General Manager of the District,
    testified that additional
    flows up to the rate of one quarter
    to one half million gallons per
    day could be given secondary treatment and chlorination, within
    the design capacity
    of the
    plan.t,
    on dry nights
    (R.
    172-73,
    177,
    184—85).
    If this were
    the whole of
    the matter, we should happily
    grant the variance.
    Unfortunately, however,
    the proposed program does not provide
    adequately
    fcr avoiding an adverse impact during wet weather, which
    is when the plant is most drastically overloaded
    already.
    Mr.
    Anderson ~testified
    that,
    in order
    to avoid
    an additional overload
    in
    wet
    weather
    that
    cou’d
    not
    be
    adequately
    treated,
    a
    five-day
    holding
    capacity
    should
    be
    provided
    CR.
    174).
    According
    to
    the
    petitioners’
    own
    computations1
    the
    most
    that
    will
    be
    provided
    is
    two days,
    at the end
    of which sewage must be
    and is to be discharged
    without regard
    to the condition of the tre~tinentplantr
    in order
    tb
    avoid
    the backup of sewage into
    the buildings
    (R.
    231,
    239-41).
    1.
    A question was raised as to the adequacy
    of the tanks to hold
    even two days’
    sewage,
    since
    the design figure used,
    taken
    from secondary studies, was
    51 gallons per capita per day, while
    the customary figure,
    as testified to by
    Mr. Anderson,
    is
    100
    to 125
    CR.
    178).
    The petitioners’ witness testified that
    the
    higher figure was based upon
    the assumption that domestic dis-
    charges will be augmented by industrial discharges
    and that
    it represented not
    a house discharge. but the input
    to
    a treat-
    ment plant
    CR.
    244-25),
    This position is largely confirmed
    by
    a leading text
    in the
    field,
    of which we
    take official
    notice.
    Fair,
    Geyer,
    &
    Okun, Water Supply
    and Wastewater Removal,
    vol.
    I,
    pp.
    2—2,
    3—9
    (1966),
    indicating that
    150 gpcd
    is
    a
    “useful
    guide
    to normal requirements”
    for community needs
    in designing
    water—supply systems;
    that about
    70
    of the water supplied
    becomes wastewater;
    and that therefore
    “the average flow in
    sanitary sewers
    is about
    100 gpcd.”
    This estimate seems to in—
    -
    dude
    not only the discharge from individual homes but
    the
    entire dry—weather flow of the
    sewers.
    We are of course open
    to
    more specific proof
    in future cases.
    2
    690

    Moreover,
    the petitioners’
    testimony suggests that during wet
    weather there may be discharges
    even before the two days are up
    because of infiltration:
    A.
    (Mr. Villa) A storm occurring
    in the area
    at the
    time
    this
    constant sewage generation
    is occurring, we would pick
    up infiltration here.
    .
    Q.
    Under such circumstances,
    I take it
    it would be necessary
    then to operate the bypasses or weirs,
    as you have called
    them,
    continuously?
    A.
    Yes,
    so that
    it operates essentially
    as the system operates
    right now.
    CR.
    255).
    In short, while
    the
    idea of the holding tank to equalize
    flows
    and take advantage
    of excess night treatment capacity is excellent,
    we
    find
    the holding tanks proposed
    are insufficient
    to protect
    against increased
    loads to
    the Waukegan plant at the
    time
    it
    is
    least
    able to handle them,
    namely, during wet weather.
    We must there-
    fore deny
    the variance on this record,
    leaving the door open to
    a
    further petition that will give assurance
    of adequate capacity to
    do
    the intended job.
    We call attention to one further difficulty that should be
    addressed
    if
    an amended petition
    is filed.
    There was no evidence
    to show that the holding tanks themselves would be adequ~tely
    protected against dangers of corrosion, explosion,
    or odor nuisance.
    We raise these issues not
    idly but in response to testimony presented
    by
    the Agency and by others
    in regard to
    a holding
    tank proposal
    in the recently decided case of School Building Commission v.
    EPA,
    ~ 71-247
    (October
    18,
    1971).
    The burden will
    be on the petitioners
    to establish this point.
    For
    the reasons given the variances are denied without prejudice
    to the filing of an amended petition satisfying the questions
    raised
    in this opinion.
    I,
    Regina E.
    Ryan, Clerk
    of the Pollution Control Board,
    certify
    that the Board adopted the above Opinion
    and Order this
    26
    day of
    October
    ,
    1971
    2
    691

    Back to top