ILLINOIS POLLUTION CONTROL BOARD
    October 14,
    1971
    TEXACO, INC.
    v.
    )
    #
    71—235
    (70—29)
    ENVIRONMENTAL PROTECTION AGENCY
    Philip
    R. Wimbish,
    for Texaco,
    Inc.
    Delbert
    0.
    Haschemeyer,
    for the Environmental Protection
    Agency
    Opinion of the Board
    (by Mr.
    Currie)
    Texaco
    was
    granted
    a variance February
    17,
    1971,
    to complete
    the installation
    of equipment designed to bring under control
    emissions
    of hydrogen sulfide from
    a brine lagoon at its
    oil
    production
    facility near
    Salem.
    The order required the company
    to determine ambient concentrations of the gas,
    to evaluate
    the efficiency of its
    new equipment,
    and to apply by August
    1
    for an extension if more time was needed.
    It was recognized that
    the application
    of
    the electrolytic
    technology
    then under
    consideration to oil field wastes was experimental,
    and that
    even
    if the unit worked well
    it might be necessary
    to ~insta1l
    additional
    units
    in order to achieve
    an acceptable level of air
    quality
    Texaco filed
    a timely request to extend the variance until
    December
    1
    of this
    year,
    and we held
    a second hearing.
    The
    Agency recommends we grant
    the brief extension
    on conditions,
    and we
    agree.
    The evidence established that
    the electrolytic
    installation
    was completed
    in June;
    that while it removed
    a considerable
    amount of hydrogen sulfide
    it was only 50-60
    as effective
    as
    anticipated;
    that its operation resulted
    in
    a
    low
    pH
    that required
    large quantities
    of caustic to avoid corrosion;
    that there were
    severe scaling and plugging problems imcairing dependability;
    and that
    in sum the unit proved unsatisfactory
    (R.
    19-28).
    Texaco
    immediately developed an alternative ylan
    that has been demonstrated
    successful in
    field experiments.
    The
    new system
    involves
    the oxidation
    of hydrogen sulfide to elemental sulfur by the introduction
    of
    compressed air
    in the presence
    of nickel chloride
    as
    a catalyst
    (R.
    57-60).
    Complete removal
    of the hydrogen sulfide from
    the
    water—-an estimated 7500 pounds per day
    (P.
    74)--
    is expected
    (P.
    53,
    68).
    As much
    as
    65 to 130 ~ounds
    of the gas will he
    stripped
    from the water by
    the rising air,
    but this will be collected
    in
    a closed vessel and introduced
    into
    a second nair
    of tanks

    where further oxidation will take place, and the ultimate emissions
    of hydrogen sulfide to the atmosphere from these second tanks
    are expected to be on the order of six and one half pounds per
    day
    (P.
    68-72).
    This compares extremely favorably with
    the estimated
    pre-control emissions of 3,000 pounds
    a day.
    The construction of the new system has already begun
    (P.
    113).
    The company first estimated
    that
    it would be able to complete
    this
    completely revised and much more effective program within the
    time
    allotted for finishing the single electrolytic unit, but minor
    delays have interfered that cannot be blamed upon Texaco,
    such
    as difficulties with
    the soil
    in excavation
    (P.
    114).
    Completion
    is now expected
    in the first half of November
    (P.
    150), but could
    be delayed by seasonal rains
    (P.
    151).
    We think the December
    1
    date entirely reasonable
    and commend Texaco
    for its application
    to the solution of
    this difficult problem.
    The company has provided
    a large number
    of sampling reports that demonstrate that
    in the
    meantime there should be no serious health danger,
    although at
    times. the concentrations near homes within a mile of the lagoon
    reach the level of detectible odor
    (P.
    l21).l
    Several
    of the lagoon’s
    nearest neighbors,
    stressing that odors have been something
    of
    a problem, have submitted statements
    indicating they do not
    object to this beief extension
    (E.g., Petitioner’s
    Ex.
    2).
    To
    close down production for this period could have enormous adverse
    consequences,
    as detailed
    in our earlier opinion,
    and it would
    not be warranted by the seriousness of the pollution problem.
    We shall condition
    this extension on the posting of
    further
    security,
    as required by statute,
    and on the company’s performing
    additional ambient tests after completion of the project.
    1.
    The Agency’s sampling showed that concentrations tend to be
    highest with low wind in the evening or early morning,
    with the highest two-hour concentration 0,019 ppm
    (EPA
    Ex.
    1).
    The Litton report to the federal air pollution
    authorities
    (NAPCA Publication APTD
    69-37,
    p.
    83, Petitioner’s
    Ex.
    15)
    recites
    “no reported injury
    to health”
    at levels
    up to 0.030 mom, though
    the “odor threshold”
    is said to
    be lower.
    Texaco reported
    a number of readings above 0.1
    ppm,
    ranging up
    to about 0.8, but generally for periods of
    only
    two to
    five minutes
    (Petitioner’s Exs.
    20-25).
    Litton
    reports that smell
    is “slightly perceptible”
    at 0,100 ppm
    and “definitely perceptible”
    at 0.330, while giving
    10 ppm
    as the “minimum concentration causing eye irritation.”
    2
    656

    This opinion constitutes
    the Board’s findings
    of fact and
    conclusions
    of
    law.
    ORDER
    Texaco,
    Inc.,
    is hereby granted an extension
    of the variance
    of February
    17,
    1971,
    to emit hydrogen sulfide gas
    from its
    brine lagoon near Salem,
    Illinois, until December
    1,
    1971,
    on
    the following conditions:
    1.
    Production
    at the facilities in question shall not be increased
    during the period of this variance;
    2.
    The$lO,000 security required by the February
    17 order shall
    be extended to secure compliance with
    the terms of
    this
    order;
    3.
    The nickel catalyst oxidation facility described
    in this
    opinion shall be in full operation by December
    1,
    1971;
    4.
    Monthly progress reports shall be filed with
    the Agency and
    with
    the Board, and
    a final report within thirty days after
    completion of the facility;
    5.
    Texaco shall submit to the Agency and
    to the Board
    the
    results of an independent sampling of ambient air quality
    in the lagoon area and in nearby inhabited areas within thirty
    days after completion
    of the facility.
    I,
    Regina
    E.
    Ryan, Clerk of the Pollution Control Board,
    certify
    that the Board adopted the above Opinion of the Board this
    14
    day of
    October
    1

    Back to top