ILLINOIS POLLUTION CONTROL BOARD
    October 14, 1971
    ARGONNE DEVELOPMENT COMPANY
    )
    v.
    )
    PCB 71-185
    ENVIRONMENTAL PROTECTION AGENCY
    Messrs. Roger B. Harris and Henry flalikov of Aitheimer, Gray,
    Naiburg & Strasburger, Attorneys for Argonne Development Co.
    Mr. Roger Ganobcik, Attorney for Environmental Protection Agency
    Opinion of the Board (by Mr. Dumelle):
    On March 31, 1971, the Board decided an enforcement action
    initially brought by the League of Women Voters against the North
    Shore Sanitary District (NSSD). Paragraph seven of the order in
    that case imposed a ban on new sewer connections throughout the
    District.11) The petitioner in the instant case, Argonne Develop-
    ment Company (Argonne), is directly affected by the sewer connec-
    tion moratorium which forbidy~ew or additional discharges reaching
    the North Chicago Sewage Treatment Plant.
    Argonne is an Il1in~ispartnership in the business of acquiring
    and developing real estate in the City of North Chicago for urban
    renewal orojects. The ‘agreement concerninci the particular project
    involved in this proceeding was entered into by Argonne and the City
    of North Chicago on December 23, 1968. Argonne is presently actively
    involved in Phase II of the Project which calls for the construction
    of 180 units of cooperative apartments known as Manchester Knoll.
    The overall urban renewal plan also provided for the construction
    of 224 housing units which were completed in 1969 and 1970,
    U
    League of Women Voters, et al v. North Shore Sanitar Dis-
    trict, PCB7O—7, 12, 13, 14 (March 31, 1971
    The portion of the order from which the instant variance was
    sought is as follows:
    The District shall not oermit any additions to present
    sewer connections, or new sewer connections to its facilities until
    the District can demonstrate to the Board that it can adequately
    treat the wastes from those new sources so as not to violate the
    Environmental Protection Act or the Rules and Regulations promul-
    gated thereunder.
    11
    2
    -~ 645

    By its petition for variance filed on July 12, 1971, Argonne
    sought to be allowed to make sewer connections for 180 housing
    units. We grant petitioner’s request to connect 180 units of Man-
    chester inoll to the sewer system served by the North Chicago
    Plant of the North Shore Sanitary District. We do so because of
    the nature of the hardship which a denial would create.
    Variances are usually requested from regulations or statu-
    tory requirements. However, in this case a variance is sought
    from the operation of a Board Order. Such a procedure is clearly
    provided for by the Environmental Protection Act, Section 35.
    The standard to be applied in such cases is likewise provided for
    in the Statute and the Board~s Rules. In considering whether to
    grant the variance, the Board must consider all the facts and
    ultimately use its best judgment coupled with the expertise it is
    statutorily presumed to embody to determine if compliance with the
    Order from which exemption is being sought will impose an arbi-
    trary or unreasonable hardship on the petitioner. This hardship
    must then be balanced against the harm done to the environment.
    In this case petitioner has set in motion unique and irretrievable
    procedures which cannot be duplicated in any similar fashion at
    a future date. Petitioner has obtained FHA mortgage commitments
    which include interest reduction payments, loan guarantees, and
    assurance of rent reduction payments. Without such commitments
    from the federal agency,low and moderate—income housing of the
    type contemplated in the instant venture cannot possibly be realized.
    The probable loss of direct federal funds and other desirable
    federal participation in the project is the chief reason why we
    are able to grant the requested variance,
    Apart from the hardship visited on the petitioner in this
    case, we are struck by the crying need for housing presented on
    the record. Mayor Kukla testified eloquently on the dire need for
    low and moderate—income housing in North Chicago. He further
    stated that it was likely that many of the occupants of the new
    housing would be denizens of the area presently served by the NSSD,
    people who would be leaving substandard and over—occupied dwellings
    to take up residence in Manchester Knoll and, as such, the load
    on the treatment system would not be an additional one. This conclu-
    sion reached afte~ considerable speculation is believable, however,
    only if the new occupants~ former residences are abandoned and demolish~
    Thus, it is clear that this is not a case of a property owner
    who, after owning a parcel of real estate for several years, decides
    it is time to build his dreamhouse only to be confronted with the
    prohibition on sewer connections. (See e.g. Robert H. Monyek v.
    EPA, PCB 71-80, July 19, 1971). Denial of the variance here would
    2
    646

    constitute not a dream deferred but a raisin withered in the sun.
    Such substantial steps have been taken down a path which cannot
    be trod again that we are persuaded that the hardship resulting
    from not allowing the connection of the 180 units would outbalance
    the environmental harm which must result from allowing the con-
    nection to a greatly overburdened treatment plant.
    We have considered the alternative to connection to the treat-
    ment system of the NSSD presented on this record and indeed would
    surely have considered the presentation incomplete without evi-
    dence of the possible other ways of handling the wastes from the
    project. The most promising alternative in most situations would
    appear to be the package treatment plant; a portable facility
    (in the sense that it can be relocated after its period of utility)
    capable of treating up to perhaps 100,000 gallons per day and
    requiring minimal supervision, A requisite for employment of
    such alternative treatment is a receiving stream which does not
    find its way to the overloaded treatment plant. The only feasible
    portable plant outlet in this case would be to the City sewer
    system. The hydraulic burden of the effluent would then be con-
    veyed to the North Chicago plant with very little alleviation of
    the pollution problem. The other alternatives discussed were
    septic fields, storage and hauling, and storage with selective re-
    lease to the treatment plant. Use of a septic field in a high density
    population area could constitute a health hazard. (See IIEQ71—2,
    Septic Tanks and the Environment). So, too, could the storage of
    a great quantity of raw sewage be a health hazard and unaoprovable
    by health authorities. Hauling the sewage by tank truck to another
    treatment plant, involving several trips per day, would be pro-
    hibitively expensive. Of the several alternatives imaginable none
    would be feasible in this case. (R.l06-1l7).
    It has not been an easy or simple matter arriving at the deci-
    sion in this case. The strategy of imposing a sewer connection ban
    when the treatment capacity of a facility is exceeded is a severe
    one which should not be used except in exacerbated situations like
    the NSSD. The underlying rationale of the instant sewer ban is
    simply to abate the amount of untreated and inadequately treated
    waste flowing into Lake Michigan. With such a ban in effect this
    Board and other public agencies are confronted with balancing con-
    flicting but seemingly equally important oublic interests, The
    Board’s decision cannot be viewed as meaning that low-cost housing
    is of transcendent interest. This case presents unusual circum-
    stances where very substantial and non-duplicative steps were taken
    by petitioner before the imposition of the ban. In other cases
    2 — 64?

    where substantial steps were taken prior to the date of our
    decision we have allowed connection to existing sewers. See,
    e.g. Wachta
    V.
    EPA, PCB 71-77 (July 12, 1971); Wagnon v.
    EPA,
    PCB 71—85 (July l~, 1971).
    The above constitutes the Board’s findings of fact and
    conclusions of law.
    Mr. Lawton took no part in the consideration or decision of this
    case.
    ORDER
    The Variance requested by Argonne Development Company is
    granted. Permission is hereby granted to allow the inter-
    connection
    to the City of North Chicago sewer system of the
    one hundred eighty (180) housing units of Manchester Knoll.
    I, Regina E. Ryan, Clerk of the Illinois Pollution Control
    Board, certify that the Board adopted
    the above Opinion and Order
    on the 14 day
    of October, 1971.
    2
    — 648

    Back to top