ILLINOIS POLLUTION CONTROL BOARD
    October
    14,
    1971
    SPARTAN PRINTING
    CO.
    v,
    )
    #
    71—19
    ENVIRONMENTAL PROTECTION AGENCY
    Supplemental Opinion and Order of the Board
    (by Mr.
    Currie)
    Spartan was given until July
    1,
    1971 to complete Phase
    I
    of
    its wastewater treatment
    facilities
    (Spartan Printing Co.
    v.
    EPA,
    #
    71-19, June
    23,
    1971).
    On June
    29, however,
    the
    company requested
    a brief extension because of delays caused by
    unanticipated
    foundation conditions, unusually wet weather,
    and
    failure of equipment
    to meet specifications.
    We asked for the
    Agency~srecommendation,
    which was
    that
    the $200,000 bond we
    required posted be forfeited and that
    a hearing be held.
    Spartan has
    also
    filed
    a proceeding for judicial review of
    our decision,
    and,
    under Supreme Court Rule
    335, has asked us
    to modify and to stay our order in certain respects.
    The Agency
    has not responded
    to this latest motion.
    We agree with
    the company that
    a $200,000 forfeiture would
    be
    an excessive imposition
    for the brief and unintentional set-
    back suffered
    in attempting
    to meet the Board~s order.
    The first
    stage was completed August
    4,
    scarcely a month behind schedule;
    the second stage has
    not been delayed at all;
    it
    is not the
    cornpany~sfault the delay occurred.
    We
    see
    no need for
    a hearing;
    the
    delay
    was
    trivial
    and
    the
    facts
    have
    not been disputed.
    We
    grant
    the
    extension
    to
    August
    4,
    1971,
    and
    since
    that
    date
    is
    past
    we
    remove
    the
    provision
    requiring
    that
    the bond cover the
    installation or operation
    of Phase
    I.
    We will not, however,
    lift the requirement of
    a bond to secure Phase
    II,
    as that’the
    statute flatly requires.
    We are also asked to stay enforcement
    of our
    order, pending
    review, with respect both to the bond
    and to the penalty we imposed
    as
    a condition of the variance.
    We agree a~to the penalty,
    for
    we
    see
    no
    point
    in requiring
    the money
    to be paid now if it may
    have to be repaid after judicial review.
    The purposes
    of the
    order
    will
    be
    as
    well
    served
    by
    later
    payment
    if
    the
    appeal
    fails.
    But
    this
    is
    not
    the
    case
    with
    the
    bond,
    for
    a
    bond
    will
    do
    no
    good if
    it
    is
    filed after the
    date
    of
    compliance;
    it
    must
    be
    filed now
    if it is
    to serve
    its
    purpose.
    2
    589

    Accordingly the June
    23 order is hereby modified by extending
    the Phase
    I date to August
    4,
    1971,
    and by eliminating the re-
    quirement that the bond cover Phase
    I;
    and the penalty
    provision.
    in paragraph
    3
    of that order is hereby stayed pending judicial
    review, on condition that
    a bond to secure payment of
    the penalty
    in the event of an adverse judicial decision is filed with the
    Environmental Protection Agency within 15 days after receipt
    of this
    order.
    In other respects
    the motion for modification
    and stay
    is
    denied.
    I, Regina
    E.
    Ryan, Clerk of the Pollution Control Board,
    certify
    that the Board adopted the above Supplemental Opinion of the
    Board
    this
    14
    day of
    October
    ,
    1971.

    Back to top