ILLINOIS POLLUTION CONTROL BOARD
August 24, 1995
CENTRAL ILLINOIS PUBLIC
)
SERVICE COMPANY
)
(Hutsonville Generating
)
Station),
Petitioner,
)
V.
)
PCB 96-31
)
(Permit Appeal-Water
Ninety-Day Extension)
)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
ORDER OF THE BOARD (by C.A. Manning):
On August 3, 1995, the Illinois Environmental Protection
Agency (Agency) and Central Illinois Public Service Company
(Central Illinois) filed a notice of extension of the 35—day
appeal period pursuant to Section 40 of the Act, relating to a
June 30, 1995 Agency determination. On August 7, 1995 the Agency
moved to supplement the record with a copy of the permit; this
motion is granted.
P.A. 88—690 (SB1724) effective January 24, 1995, amends
Section 40(a)(1), which governs the permit appeal process, to
provide:
the 35-day period for petitioning for a hearing may be
extended for a period of time not to exceed 90 days by
written notice provided to the Board from the applicant
and the Agency within the initial appeal period.
As the Board maintains its files by docket number only, the
Board will reserve Docket PCB 96-31 for any appeal which may be
filed by Central Illinois. In the event that Central Illinois
fails to file an appeal on or before November 2, 1995 (the 125th
day after June 30, 1995), the Board will dismiss the docket as
unnecessary. A $75.00 filing fee will, of course, be required at
such time as Central Illinois files such petition.
IT IS SO ORDERED.
2
I, Dorothy N. Gunn, Clerk of the Illinois Pollution Control
Board, here~ certify that the above order was adopted on the~V~
day of k~/-t~’1’~/
,
1995,,,~Dy a vote of 7’-~.
•
~
(.
Dorothy M. 4linn, Clerk
Illinois Po’llution Control Board