ILLINOIS POLLUTION CONTROL BOARD
September
16,
1971
IOWA-ILLINOIS GAS
AND
ELECTRIC
COMPANY
#71—165
V.
ENVIRON~NTAL PROTECTION AGENCY
RO~R
GANOBCIK, ATTORNEY FOR ENVIRONMENTAL PROTECTION AGENCY
CRAMPTON
& DALEY, ATTORNEY FOR PETITIONER
OPINION OF THE BOARD
(BY MR. LAWTON):
Petitioner filed a variance application with
the Board relative
to its Moline generating
station, seeking permission to exceed the
particulate emission regu”lations governing the control of air ~ollu-
tion as
a consequence of coal burning in six stoker-fired boilers
pending completion of the Quad-Cities Nuclear Power Station.
The petition and evidence set forth that Boilers
#16,
#17
and
#18 are spreader stokers burning both coal and natural gas.
Boilers
#19,
#20
and
#21 are underfeed stokers burning coal only.
The variance
request seeks permission to burn coal in Boilers
#19,
#20
and
#21
in an emergency capacity until Quad—Cities
Unit No.
1 becomes commer-
cially available
for service,
at which time these three boilers will be
permanently retired,
The variance further asks that Boilers
#16,
#17
and
#18 be permitted to burn coal to meet load demands until
Quad—Cities Unit No.
1 is in commercial service,
and thereafter,
to
pen~itburning of coal only in emergency situations until
July
1,
1974,
at
which time coal-firing will be eliminated.
The original recommendation of the Agency recommended allowance
of the variance
for
a one-year period which is the maximum we are
authorized by statute
to allow, retirement of Boilers
#19,
#20
and
#21
upon completion of Quad-Cities Unit No.
1,
use
of the coal-burning
boilers for emergency situations only
and upon completion
of Quad—
Cities Unit No.
1,
the remaining boilers subject to the petition
be
converted to burn No.
2 oil or residual
oil of 1,8
sulphur content,
or in the alternative,
that dry mechanical collectors having
75
efficiency
be installed by that date.
At
the close of the hearing,
discussion took place
(IR,45)
indicating
the possibility of agreement between petitioner and
the Agency with
“~egardto conditions
for the continued coal burning
in
Boilers
#16,
2
—
477
#17
and
#18 subsequent to the commercial operation
of Quad-Cities
Unit No.
1.
Following the hearing,
a supplemental affidavit was
filed by Richard B. Miller, Manager of
the Electric Engineering Depart-
ment of petitioner, proposing the following conditions
for the opera-
tion of Boilers #16,
#17 and
#18 after Quad-Cities No.
1 has been
placed in operation:
“Boilers
#16,
#17
and
#18, Moline Generating Station,
shall be limited on coal burning operation to meet the
emergency power requirements only, which shall not exceed
the equivalent of 31 days
or 744 hours
of operation
(31
days
x
24 hours
=
744 hours)
per boiler, per annum
(a
period of 12 consecutive months,)
An hour of operation shall be counted as having been
fired on coal when both
of the following conditions
are
met:
(a)
coal
is fired singly or
in combinations with
gas fuel and at
a rate such that the equivalent
steam generation rate for each boiler on coal is
25,000 pounds per hour
or greater,
and
(b)
the boiler on line generating steam.
The steam generation rate
at a level less than 25,000
pounds per hour is proposed to be exempted from the hours
of operation calculations.
The maximum continuous steam
generation rate of each of these stoker-fired boilers
is
100,000 pounds per hour.
The 25,000 pounds per hour level,
or less, would be approximately equivalent
in particulate
emission to
a pulverized coal facility operating at full
capacity and equipped with high grade mechanical
dust
collectors.
The calculation of the 25,000 pounds per hour level
or
less excludes periods when the boiler
is being started,
kept on hot standby or is banked in anticipation of
an emer-
gency, or to back
for gas
fuel firing
and during periods
when boiler gas contaminant appears imminent,
At these lower levels of firing rate,
the coal firing
operation
is steady and emissions standards are achieved
or closely approached.
The equivalent of
31 days
of coal operation,
as outlined
above, would permit one refueling of
a nuclear unit at
Quad-Cities Station
(estimated to require
21 days)
and
additionally, accommodate two one-week
(total of
10 days)
operating emergencies in any consecutive 12-month period.”
2
—
478
The Agency responded to this proposal stating
as follows:
“Petitioner has submitted
a proposal
for
such
agreement.
The Agency does not accept that oroposal,
in that
it
would authorize
the
generation
of
steam
b~coal—burning
in all three boilers
for more than
two
hours
per
day
every
day
of
the
year,
and
the
constant burning of coal
to the limited extent neces-
sary to keep these boilers on
~spinning’
standby
indefinitely,
This
would
go
well
beyond
1reserve
for
emergency
purposes’,”
The
Agency
proposes
the
following
limitation:
a)
After
Quad-Cities
Unit
#1
has
been
placed
in
commercial
operation,
coal
shall
be
burned
in
Boilers
#16,
#17
and
#18
(Moline
Generating
Station)
only
to
meet
emergency
requirements,
as
defined
in
the
Agency’s
recommendation,
such
use
to
be
limited
to
ten
days
per
year,
except
that;
b)
In
the
event
of
the
refueling
of
a
nuclear
unit
at
Quad—Citie~
#i,
which
refueling
renders
such
unit
temporarily
useless
as
a
source
of
power,
coal
may
be
burned
in
said
boilers
for
21
days,
which
days
shall
not
be
charged
against
the
ten
days
described
in
(a)
above.
c)
For
purposes
of
these
limitations,
a
day
shall
be
counted
if,
for
at
least
one
hour
during
that
day:
i.
Coal
is
fired
singly
or
in
coihbination
with
gas
fuel
at
a
rate
such
that
the
ecuivalent
steam
generation
rate
for
any
hoiter
on
coal
is
25,000
pounds
per
hour
or
preaner;
and
ii.
The
boile:
Is
“on
l~
generating
steom.
A
second
supplemental
sf1: Thavit.
was
received
from
petitioner
~ts
o
~
oroo~
~1
~Io~eter
~
do
non
acoe~t
oi.the:
proposa.
tuft
oo
grant
a
variance
for
a
one—year
Th
o~
~Et
fortn
i
tb~
~ci
~ta~
pc~:t1O~Of
:IiIi:
Grde~::
IThe
total
oaipaolty
of
all
faci.litIes
of
i~
o~r-~r
o~
~tt~
~:
r~
~i
~
i~c
~ ~
~:one
~enerates
aoon:ximat
ely
III
secrawatte
,
The
nenerating
caraci
cy
of
5
oIlers
#19,
#20
end
#21
is
10
moqawatta
and
of
toilers
#16,
f .27
end
#18
24
rnegewaf’:e.
An
stated
snore.
toilers
~19
#20
nod
#21
safle
coal—fired
and.
will
be
obased
out
complete..y
50.00
the
opera—
~von
of
Q
ad~
ion
Jolt
to
1.
BoiLers
•#15~
#17
and
#15
are
coal.
and
—~
i
~
~
~
_
m
—~
~
rr
1
Upon completion of Quad-Cities Unit No.
1, Petitioner will be en—
titled to
50
of its capacity 0r 404 megawatts which amount will re-
main the same when Unit No.
2 comes into operation; petitioner then
receiving 25
of the total capacity.
On February 7,
1969, the Air Pollution Control Board of the
State of Illinois approved an Air Contaminant Emission Reduction
Program
(Acerp)
essentially similar to that now being proposed by
the present petition for variance, although at that time it was con-
templated that Quad-Cities Unit No.
1 would be conmercially available
for service by June
1,
1970,
The present petition underlines the importance of placing Quad-
Cities in commercial use at the earliest possible date,
It is also
significant that Petitioner, by this variance request, is seeking
only
to
pursue
a
program
that
has
been
previously
approved
by
our
predecessor
state agency,
While the capacities
of the boilers in question are relatively
small, Petitioner asserts that it will be in
danger of not meeting
its
load ob~Ligationsor the 12
reserve requirements specified in the Iowa
Pool Agreement
if use of the boilers,
subject to the variance request,
is
denied.
A
load and capacity data
study
is in the
record.(Ex. A,
R.42),
indicating the system~s capacity including the
12
reserve
por-
tions
from other systems and petitioner’s
capacity with and without
the Quad-Cities Station in operation.
The study indicates that even
with Boilers
#19,
#20 and #21
in operation,
a
36
megawatt
deficiency
will occur in January,
1972, based upon its projected generation needs
before the operation of the Quad—Cities station,
Arrangements have
been made
for the purchase of
100 megawatts
of capacity for an 18—week
period beginning December
1,
1971, which according to petitioner will
lessen, but not eliminate,
the likelihood that coal will have to be
burned in some quantities
in the boilers in question.
The evidence
indicates the uncertainty of available gas and fuel oil as alternative
fuel
for use during the winter months,
Abatement equipment in the form of mechanical collectors will
cost in the range of $350,000
to $450,000
for Boilers
#16,
#17 and
#18
(R.37)
It is the Opinion of the Board that the circumstances demonstrated
by petition justify
a continuation of the existing Air Contaminant
Emission
Reduction
Program
(Acerp)
for
a
period
of
one
year
pending
the
commercial
operation
of
Quad—Cities
Unit
No,
I.
The consequences
of continued coal burning, subject to the emergency conditions we impose,
are less severe than
the hardship which would result to the community
in
curtailing of petitioner’s load capacities,
if use of the boilers
subject to the variance request
is denied.
Nor do the circumstances
of
the instant case warrant the expense of installation of abatement equip-
ment.
2—480
IT IS TH~
ORDER
of the Board that Petitioner be granted a
variance from the particulate emission regulations of the Rules
and
Regulations Governing the Control of Air Pollution until
September 15,
1972,
subject to the following terms and conditions:
1,
Prior to the time when Quad-Cities Station No. 1 is in
commercial operation, Petitioner shall be permitted to
burn coal in Units
#16,
#17,
#18,
#19, #20 and #21 in
order to meet its load requirements, providing it is unable
to meet such load requirements by the use of its other
facilities, is not capable of obtaining gas or oil to burn
in said boilers and is incapable of purchas~ingadditional
electric power from outside sources;
2.
Subsequent to the commercial operation of Quad-Cities Unit
No,
I,
coal burning in Boilers #16,
#17 and #18 shall
cease and coal burning in Boilers
#19, #20 and #21 shall
be permitted only in the event of severe emergency caused
by major equipment breakdown of petitioner’s
facilities,
and the inability to meet its load requirements from its
operating facilities
or by the purchase of electrical power
from outside sources.
“Coal burning” is defined
as in the
Agency recommendation quoted in this Opinion.
3.
Refueling of nuclear units shall take place when gas
supply is available unless Petitioner can demonstrate to
the Board within 30 days from the date hereof,
that such
refueling cannot be scheduled
at
a time when gas is avail-
able,
4.
Petitioner shall report to the Environmental Protection
Agency and to the Board the circumstances under which it has
been obliged to burn coal in any of the above-designated
boilers including the reasons why such coal burning was neces-
sary, the extent to which such boilers were used
and
the
unavailability of the alternatives hereinabove set forth.
5,
This variance shall not be extended beyond the date of its
expiration except upon a petition being
filed
with the
Board, hearing held thereon and further order of the Board.
This Opinion constitutes the findings of fact and conclusions of
law
of the Board,
I,
Regina E. Ryan,
Clerk of the Pollution Control Board, certify
that the above Opinion was
adopted bv~theBoard on the j~day of
September,
1971.
2
—
481