ILLINOIS POLLUTION CONTROL BOARD
September
16,
1971
CENTRAL SOYA COMPANY,
INC.
V.
)
#
PCB 71—163
ENVIRONMENTAL PROTECTION AGENCY
Walter
H.
Small
for Central Soya Company,
Inc.
John
S.
McCreery for
the Environmental Protection Agency
Opinion and Order of the Board
(by Mr.
Currie):
Central Soya Company,
Inc.
(“Petitioner”)
owns and operated
an agricultural processing
plant near Gibson City,
Illinois annually
processing millions
of
bushels
of soybeans,
and manufacturing
thousands
of
tons of livestock and poultry
feed, and edible proteins.
In
its variance petition of June
25,
1971, Petitioner stated that
its
facilities were presently being served by three coal fired
steam generating boiler units rated at 550 h.p.,
390 h.p.
and
200
h.p.
respectively;
that it had embarked on
a project to re-
place
the smallest boiler with
a new oil-fired boiler at
a total
cost of $367,500.00; that
if there had been
a violation of
applicable
air pollution regulations
at the facility, which Petitioner
later admitted
(R.
2),
it was
attributable
to the excessive demand
en the stream generating capacities
of the three boilers and the
age of the smallest boiler;
that Petitioner had recognized this
fact when it began
to “increase the capacity
of its manufacturing
facilities”
in
1970;
and that installation
of the new boiler would
be completed by October
15,
1971, but that Petitioner was requesting
a variance from Section 9(a)
of the Environmental Protection Act
and Rule 2~-2.53of the
Rules
and Regulations Governing the Control
of Air Pollution until November
1,
1971
to cover unforeseen delays.
The Agency brought out
the fact that although Petitioner had
submitted
a Letter of Intent
as early
as October
30,
1967,
and al—
though Petitioner had been requested on several occasions to submit
an Air Contaminant Emission Reduction Program
(“ACERP”)
,
as re—
quired by
law,
it had never done
so.
The company admitted that it
had no ACERP
(R.
2),
Furthermore,
the Agency
stated in
its
recommendation that
the pollution problems
at Petitioner~s
plant were not merely confined to the smallest boiler but were also
attributable
to Petitioner~swaste treatment lagoons
as
well as to
the other two boilers,~that there were,
in addition, dust
and odor
problems
and apparent Ringelmann violations on
numerous
occasions;
that,
in general, Petitioner had delayed almost three years
in
taking any steps whatsoever to begin controlling particulate emissions
2
—
473
from its stacks
and was,
even now, only attempting
to correct the
problems related to its smallest stack.
The Agency recommended
that the petition for Variance be denied or,
in the alternative,
that if granted,
it be subject to certain conditions enumerated
in the Recommendation.
Prior
to the hearing on the merits, Petitioner
and
the Agency stipulated
to and
agreed upon most of
the conditions
recommended by
the Agency
(B.
12),
including the submission of
programs
to control other pollution sources at the plant.
Such
programs should take
the form of variance petitions,
and additional
hearings will be scheduled
as necessary upon their receipt.
As
a result of the stipulation no witnesses were called,
and little
evidence was adduced
at the hearing.
Our order herein substantially
approves
the stipulation of the parties but contains additional
measures deemed appropriate by the Board in light of the facts
of this
case.
A denial of
the requested variance might result in
a severe
disruption to Petitioner~s operations
and might cause
the layoff
of some or all of the Petitioner~s 250 employees.
We do not believe
the
facts
of this case warrant such drastic action,
However,
the
Petitioner~s admitted and unexcused failure to file the required
ACERP and its long and unexplained delay
in beginning
its cleanup
operation cannot be overlooked.
As
in similar past cases we
condition the variance on payment of
a penalty in the amount of
$5000.
See,
e.g., M~rquetteCement
Co.
v.
EPA,
#
70—23
(Jan.
6,
1971)
.
Because less than one month remains until expiration of the
variance, we think it likely no bond could be filed in time
to do
any good and therefore will not require security.
ORDER
It
is
the order of the Pollution Control Board that:
Petitioner~s request for
a variance from Section
9(a)
of the
Environmental Protection Act and
Rules 2~-2.53and 3~-3.l22
of the Rules and Regulations Governing the Control of Air
Pollution
to operate the 200
h.p.
boiler presently in use
at
Petitioner~s Gibson City facilities
is hereby granted until
October 15,
1971 under the following
terms
and conditions.
1.
Petitioner shall pay to the State of Illinois, within
35 days
of the receipt of this order,
a monetary penalty of $5,000.00;
2.
Petitioner shall perform stack tests
on the two larger boilers
under
full load conditions when the
new oil~firedboiler
is
in
operation but
in no event later
than November
1,
1971,
and
if the stack tests reveal that emissions from said boilers
are in violation of law, Petitioner shall,
by
no later than
December
1,
1971 submit to the Pollution Control Board and
the Environmental Protection Agency, detailed plans
to control
particulate emissions
and to bring emissions from such boilers
into compliance with
law;
3.
On or before February
1,
1972, Petitioner
shall submit to
the Pollution Control Board
and the Environmental Protection
Agency
a program for
the control of sulfur dioxide including
a detailed explanation of the program and timetables for the
completion
of the program which shall be implemented by
no
later than June
1,
1974;
4.
Within thirty
(30)
days
of the receipt of this order,
Petitioner
shall submit to the Pollution Control Board and
the Environmental Protection Agency plans
for the control of
odors from its waste treatment plant,
including
a detailed
description and timetable
for
the installation of
any aerating
equipment
it proposes
to use
and control of hydrogen sulfide
emissions from the waste treatment lagoons,
all of said plans
to be implemented and completed by Petitioner within six
(6)
months after
the receipt of this order.
5.
Petitioner
shall submit to the Pollution Control Board
and
the Environmental Protection Agency
a detailed report
concerning the levels of emissions and plans
for the control
of excessive emissions from the following processes:
a)
Ingredient Hammermill Grinding.
b)
Calflac Equipment Aspiration.
Said reports and plans,
including specifications,
shall be
submitted within thirty
(30)
days of the receipt of this order
and shall be implemented and completed within six months
of the date hereof,
I, Regina
E.
Ryan, Clerk
of the Pollution Control Board,
certify
that the Board adopted the above Opinion
and Order this~
day of September
,
1971.
2—475