ILLINOIS POLLUTION CONTROL BOARD
    September
    16,
    1971
    CENTRAL SOYA COMPANY,
    INC.
    V.
    )
    #
    PCB 71—163
    ENVIRONMENTAL PROTECTION AGENCY
    Walter
    H.
    Small
    for Central Soya Company,
    Inc.
    John
    S.
    McCreery for
    the Environmental Protection Agency
    Opinion and Order of the Board
    (by Mr.
    Currie):
    Central Soya Company,
    Inc.
    (“Petitioner”)
    owns and operated
    an agricultural processing
    plant near Gibson City,
    Illinois annually
    processing millions
    of
    bushels
    of soybeans,
    and manufacturing
    thousands
    of
    tons of livestock and poultry
    feed, and edible proteins.
    In
    its variance petition of June
    25,
    1971, Petitioner stated that
    its
    facilities were presently being served by three coal fired
    steam generating boiler units rated at 550 h.p.,
    390 h.p.
    and
    200
    h.p.
    respectively;
    that it had embarked on
    a project to re-
    place
    the smallest boiler with
    a new oil-fired boiler at
    a total
    cost of $367,500.00; that
    if there had been
    a violation of
    applicable
    air pollution regulations
    at the facility, which Petitioner
    later admitted
    (R.
    2),
    it was
    attributable
    to the excessive demand
    en the stream generating capacities
    of the three boilers and the
    age of the smallest boiler;
    that Petitioner had recognized this
    fact when it began
    to “increase the capacity
    of its manufacturing
    facilities”
    in
    1970;
    and that installation
    of the new boiler would
    be completed by October
    15,
    1971, but that Petitioner was requesting
    a variance from Section 9(a)
    of the Environmental Protection Act
    and Rule 2~-2.53of the
    Rules
    and Regulations Governing the Control
    of Air Pollution until November
    1,
    1971
    to cover unforeseen delays.
    The Agency brought out
    the fact that although Petitioner had
    submitted
    a Letter of Intent
    as early
    as October
    30,
    1967,
    and al—
    though Petitioner had been requested on several occasions to submit
    an Air Contaminant Emission Reduction Program
    (“ACERP”)
    ,
    as re—
    quired by
    law,
    it had never done
    so.
    The company admitted that it
    had no ACERP
    (R.
    2),
    Furthermore,
    the Agency
    stated in
    its
    recommendation that
    the pollution problems
    at Petitioner~s
    plant were not merely confined to the smallest boiler but were also
    attributable
    to Petitioner~swaste treatment lagoons
    as
    well as to
    the other two boilers,~that there were,
    in addition, dust
    and odor
    problems
    and apparent Ringelmann violations on
    numerous
    occasions;
    that,
    in general, Petitioner had delayed almost three years
    in
    taking any steps whatsoever to begin controlling particulate emissions
    2
    473

    from its stacks
    and was,
    even now, only attempting
    to correct the
    problems related to its smallest stack.
    The Agency recommended
    that the petition for Variance be denied or,
    in the alternative,
    that if granted,
    it be subject to certain conditions enumerated
    in the Recommendation.
    Prior
    to the hearing on the merits, Petitioner
    and
    the Agency stipulated
    to and
    agreed upon most of
    the conditions
    recommended by
    the Agency
    (B.
    12),
    including the submission of
    programs
    to control other pollution sources at the plant.
    Such
    programs should take
    the form of variance petitions,
    and additional
    hearings will be scheduled
    as necessary upon their receipt.
    As
    a result of the stipulation no witnesses were called,
    and little
    evidence was adduced
    at the hearing.
    Our order herein substantially
    approves
    the stipulation of the parties but contains additional
    measures deemed appropriate by the Board in light of the facts
    of this
    case.
    A denial of
    the requested variance might result in
    a severe
    disruption to Petitioner~s operations
    and might cause
    the layoff
    of some or all of the Petitioner~s 250 employees.
    We do not believe
    the
    facts
    of this case warrant such drastic action,
    However,
    the
    Petitioner~s admitted and unexcused failure to file the required
    ACERP and its long and unexplained delay
    in beginning
    its cleanup
    operation cannot be overlooked.
    As
    in similar past cases we
    condition the variance on payment of
    a penalty in the amount of
    $5000.
    See,
    e.g., M~rquetteCement
    Co.
    v.
    EPA,
    #
    70—23
    (Jan.
    6,
    1971)
    .
    Because less than one month remains until expiration of the
    variance, we think it likely no bond could be filed in time
    to do
    any good and therefore will not require security.
    ORDER
    It
    is
    the order of the Pollution Control Board that:
    Petitioner~s request for
    a variance from Section
    9(a)
    of the
    Environmental Protection Act and
    Rules 2~-2.53and 3~-3.l22
    of the Rules and Regulations Governing the Control of Air
    Pollution
    to operate the 200
    h.p.
    boiler presently in use
    at
    Petitioner~s Gibson City facilities
    is hereby granted until
    October 15,
    1971 under the following
    terms
    and conditions.
    1.
    Petitioner shall pay to the State of Illinois, within
    35 days
    of the receipt of this order,
    a monetary penalty of $5,000.00;
    2.
    Petitioner shall perform stack tests
    on the two larger boilers
    under
    full load conditions when the
    new oil~firedboiler
    is
    in
    operation but
    in no event later
    than November
    1,
    1971,
    and
    if the stack tests reveal that emissions from said boilers
    are in violation of law, Petitioner shall,
    by
    no later than
    December
    1,
    1971 submit to the Pollution Control Board and
    the Environmental Protection Agency, detailed plans
    to control
    particulate emissions
    and to bring emissions from such boilers
    into compliance with
    law;

    3.
    On or before February
    1,
    1972, Petitioner
    shall submit to
    the Pollution Control Board
    and the Environmental Protection
    Agency
    a program for
    the control of sulfur dioxide including
    a detailed explanation of the program and timetables for the
    completion
    of the program which shall be implemented by
    no
    later than June
    1,
    1974;
    4.
    Within thirty
    (30)
    days
    of the receipt of this order,
    Petitioner
    shall submit to the Pollution Control Board and
    the Environmental Protection Agency plans
    for the control of
    odors from its waste treatment plant,
    including
    a detailed
    description and timetable
    for
    the installation of
    any aerating
    equipment
    it proposes
    to use
    and control of hydrogen sulfide
    emissions from the waste treatment lagoons,
    all of said plans
    to be implemented and completed by Petitioner within six
    (6)
    months after
    the receipt of this order.
    5.
    Petitioner
    shall submit to the Pollution Control Board
    and
    the Environmental Protection Agency
    a detailed report
    concerning the levels of emissions and plans
    for the control
    of excessive emissions from the following processes:
    a)
    Ingredient Hammermill Grinding.
    b)
    Calflac Equipment Aspiration.
    Said reports and plans,
    including specifications,
    shall be
    submitted within thirty
    (30)
    days of the receipt of this order
    and shall be implemented and completed within six months
    of the date hereof,
    I, Regina
    E.
    Ryan, Clerk
    of the Pollution Control Board,
    certify
    that the Board adopted the above Opinion
    and Order this~
    day of September
    ,
    1971.
    2—475

    Back to top