ILLINOIS POLLUTION CONTROL BOARD
    September 2, 1971
    CHARLES N, HUGHES et al.
    V.
    )
    #
    PCB 71—151
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion and Order of the Board (by Mr. Currie)
    This petition seeks a Variance from our ban on new sewer
    connections to overloaded sewage
    treatment plants in the North Shore
    Sanitary District. As in
    Dole Construction Co. v. EPA,
    #
    71—126, (August 13, 1971), we scheduled a hearing to determine
    the facts, but the petitioners did not appear at the hearing.
    As in the Dole case, we are left with neither proof that compliance
    would create an arbitrary or unreasonable hardship nor any
    indication that the variance is still desired. We therefore
    dismiss the petition for want of prosecution, without prejudice
    to the filing of a new petition in the event the parties wish
    this matter to be pursued. We add for future guidance of the
    parties that in prior cases we have held the purchase of plans
    for a home
    not
    under
    construction at the time of the sewer ban
    is
    insufficient hardship to justify a variance. E.g., Wagnon
    v, EPA,
    4t 7l~85 (July 26, 1971).
    This opinion constitutes the Board~s findings of fact,
    conclusions of law, and order.
    I,
    Regina E. Ryan, Clerk
    of the Pollution Control Board, certify
    that
    the Board adopted
    the
    above Opinion and Order this~~
    day of~,
    1971.
    2
    367

    Back to top