ILLINOIS POLLUTION CONTROL BOARD
    August13,
    1971
    Hardwick Brothers Company
    )
    )
    V.
    )
    PCB71-17
    )
    Environmental Protection Agency)
    Opinion of the Board.
    (by Mr. Kissel):
    Hardwi~kBrothers Company
    (“Hardwick”) originally filed
    a petition for variance from the open burning regulations and
    existing law, and this Board granted that variance, Hardwick
    Brothers COmpany’
    V.
    Environmental Protection A~ency,PCB 71-17,
    ~
    3, 1971.
    Hardwick was granted
    a variance by the
    Board to conduct burning of trees and underbrush gathered as
    a result of its work on the straightening and dredging project
    on the north fork of
    the Saline River, under specified con-
    dition~,until September
    1,
    1971.
    Further, Hardwick was
    requi~çdto submit to
    the
    Board a report on or before July
    1,
    1971
    ~detailing its investigations and conclusions on the
    following:
    “a.
    The possibilities of, and economics in,
    acquiring additional right of way on
    the
    Saline River project; and
    b.
    The possibilities of, and economics in, using
    an
    ‘air curtain’ device in the burning~”
    The purpose of this investigation was to determine whether there
    was any
    other
    economical way to dispose of the trees and under-
    brush other than to burn them in the open.
    1
    There was a discrepancy between the date
    in
    the Board
    opinion and the date
    in the Board order,
    The order required the
    report by July
    1,
    1971
    and the opinion required it by August
    1,
    1971.
    Actually, Hardwick filed two reports, one
    on
    June
    30
    and
    one on July
    30;
    so
    it
    complied with both dates.
    2
    271

    On July 30, 1971
    Hardwick, through its attorneys
    McClure and McClure, directed a letter to the Board,
    and
    sent copies of the letter to the Environmental Protection
    Agency, advising the Board and the Environmental Protec-
    tion Agency that Hardwick had made the investigations in
    the two required areas.
    Hardwick advised as follows:
    1.
    The additional ri~ght-of-way
    -
    This land would
    have to be acquired by the Saline County Conservancy District,
    and would, according to Hardwick, have to be acquired by
    condemnation proceedings.
    Since the Conservancy District
    does not have the power of “quick take”, lengthy legal pro-
    ceedings would have to be instituted.
    We know from the prior
    hearing that the land already received by the Conservancy
    District was given to them by the local land owners, and
    that the District has little,
    if any,money with which
    to
    purchase land now.
    Even if it did have the money, Hardwick
    points out that “it is extremely unlikely that such proceed-
    ings could be completed in time to be of any value to this
    contractor under the provisions of its current contract
    with the Corps of Engineers.”
    2.
    Use of the “air curtain” destructor
    In its
    report Hardwi~T~~
    “The contractor has very seriously considered
    the possibilities of, and the economics in using
    an
    ‘air curtain’ device
    in burning this material
    when weather and water level conditions permit.
    The
    contractor’s past experience with air-curtain-type
    burning involves the digging of a trench
    8 to 10
    feet deep and introducing air under pressure through
    tubes at the bottom of the ditch to the combustible
    material piled in the ditch.
    In this particular
    area this method of air-curtain burning is not
    practicable because the ground water level is so
    near the surface that a ditch of any appreciable
    depth would immediately fill with ground water.
    Further, normally a pit for air-~curtain-type
    burning must have vertical sides.
    The character
    of the soil in the project area and the moisture
    content in the project area is such that it
    would not be possible to maintain ~ vertical
    wall for the pit.
    Simply stated, any pit dug
    on the right of ways furnished by the Corps of
    Engineers for this project would constitute
    nothing but a
    ‘mud hole’.”
    2
    272

    This
    Board
    believes
    that
    HardwicJc has made a good faith.
    effort to find alternate ways of disposing of the trees and
    underbrush from the Saline River project.
    For the reasons
    stated in the original opinion, this Board agrees that the
    variance previously granted to Hardwick should be extended
    until August 13
    ,
    1972, under the same conditions
    as
    set forth in paragraphs
    1 and
    2 of the previous order of the
    Board in this case.
    Upon presentation and consideration of the documents
    submitted by Hardwick, the Board hereby extends the variance
    previously granted to Hardwick on May
    3,
    1971 under the same
    conditions
    as set forth in paragraphs
    1 and 2 of the order
    of the Board of that date.
    I, Regina E. Ryan, Clerk of the Pollution Control Board,
    certify that the Board adopted the above opinion and order this
    1~th
    day of
    Aucni~i-
    ,
    1971.
    2
    273

    Back to top