ILLINOIS POLLUTION CONTROL BOARD
August13,
1971
Hardwick Brothers Company
)
)
V.
)
PCB71-17
)
Environmental Protection Agency)
Opinion of the Board.
(by Mr. Kissel):
Hardwi~kBrothers Company
(“Hardwick”) originally filed
a petition for variance from the open burning regulations and
existing law, and this Board granted that variance, Hardwick
Brothers COmpany’
V.
Environmental Protection A~ency,PCB 71-17,
~
3, 1971.
Hardwick was granted
a variance by the
Board to conduct burning of trees and underbrush gathered as
a result of its work on the straightening and dredging project
on the north fork of
the Saline River, under specified con-
dition~,until September
1,
1971.
Further, Hardwick was
requi~çdto submit to
the
Board a report on or before July
1,
1971
~detailing its investigations and conclusions on the
following:
“a.
The possibilities of, and economics in,
acquiring additional right of way on
the
Saline River project; and
b.
The possibilities of, and economics in, using
an
‘air curtain’ device in the burning~”
The purpose of this investigation was to determine whether there
was any
other
economical way to dispose of the trees and under-
brush other than to burn them in the open.
1
There was a discrepancy between the date
in
the Board
opinion and the date
in the Board order,
The order required the
report by July
1,
1971
and the opinion required it by August
1,
1971.
Actually, Hardwick filed two reports, one
on
June
30
and
one on July
30;
so
it
complied with both dates.
2
—
271
On July 30, 1971
Hardwick, through its attorneys
McClure and McClure, directed a letter to the Board,
and
sent copies of the letter to the Environmental Protection
Agency, advising the Board and the Environmental Protec-
tion Agency that Hardwick had made the investigations in
the two required areas.
Hardwick advised as follows:
1.
The additional ri~ght-of-way
-
This land would
have to be acquired by the Saline County Conservancy District,
and would, according to Hardwick, have to be acquired by
condemnation proceedings.
Since the Conservancy District
does not have the power of “quick take”, lengthy legal pro-
ceedings would have to be instituted.
We know from the prior
hearing that the land already received by the Conservancy
District was given to them by the local land owners, and
that the District has little,
if any,money with which
to
purchase land now.
Even if it did have the money, Hardwick
points out that “it is extremely unlikely that such proceed-
ings could be completed in time to be of any value to this
contractor under the provisions of its current contract
with the Corps of Engineers.”
2.
Use of the “air curtain” destructor
—
In its
report Hardwi~T~~
“The contractor has very seriously considered
the possibilities of, and the economics in using
an
‘air curtain’ device
in burning this material
when weather and water level conditions permit.
The
contractor’s past experience with air-curtain-type
burning involves the digging of a trench
8 to 10
feet deep and introducing air under pressure through
tubes at the bottom of the ditch to the combustible
material piled in the ditch.
In this particular
area this method of air-curtain burning is not
practicable because the ground water level is so
near the surface that a ditch of any appreciable
depth would immediately fill with ground water.
Further, normally a pit for air-~curtain-type
burning must have vertical sides.
The character
of the soil in the project area and the moisture
content in the project area is such that it
would not be possible to maintain ~ vertical
wall for the pit.
Simply stated, any pit dug
on the right of ways furnished by the Corps of
Engineers for this project would constitute
nothing but a
‘mud hole’.”
2
—
272
This
Board
believes
that
HardwicJc has made a good faith.
effort to find alternate ways of disposing of the trees and
underbrush from the Saline River project.
For the reasons
stated in the original opinion, this Board agrees that the
variance previously granted to Hardwick should be extended
until August 13
,
1972, under the same conditions
as
set forth in paragraphs
1 and
2 of the previous order of the
Board in this case.
Upon presentation and consideration of the documents
submitted by Hardwick, the Board hereby extends the variance
previously granted to Hardwick on May
3,
1971 under the same
conditions
as set forth in paragraphs
1 and 2 of the order
of the Board of that date.
I, Regina E. Ryan, Clerk of the Pollution Control Board,
certify that the Board adopted the above opinion and order this
1~th
day of
Aucni~i-
,
1971.
2
—
273