ILLINOIS POLLUTION CONTROL BOARD
    March 22, 1971
    DECATUR SANITARY DISTRICT
    )
    )
    v.
    )
    PCB #71—37
    )
    ENVIRONMENTAL PROTECTION AGENCY)
    Opinion
    and
    Order of the Board (by Mr. Currie):
    The District
    asks
    a one-year extension of the SWB-l4 timetable
    for construction of tertiary treatment facilities.
    The petition does
    not contain the information required by Board Procedural Rule 401,
    and it is dismissed.
    The petition does not contain an adequate statement of the injury
    that would result to the public if the variance were granted.
    It is
    stated only that the requested extension “would not be injurious”
    and would not “reduce the present usefulness” of the receiving stream
    Mere conclusions are not adequate; facts underlying the
    conclusion
    must be alleged.
    See City of Jacksonville v. EPA, #70-30 (Jan. 27, 1971).
    If the argument is that there is no need for tertiary treatment,
    that
    is contrary to the findings of the Sanitary Water Board in
    adopting the regulation.
    The District asks that the Environmental
    rrotection Agency investigate the uses and quality of the river.
    It
    is the job of the petitioner, not of the Agency, to prove the case
    for a variance. What are needed are specific allegations as to the
    present uses and quality of the
    stream and
    any other facts the District
    believes relevant to its conclusion that a year’s delay will not harm
    the public.
    r.loreover, there is no adequate allegation as to the reason the
    District has delayed so long getting started on this project. The
    tertiary treatment requirement has been on the books since 1967, and
    the District admits it
    was informed of the requirement
    that
    same
    sprin;!, five years in advance of the scheduled date of completion.
    We have found in a related case that three years is ample
    time
    from
    conception to con~pletionof sewage treatment facilities (Mississippi
    River Seconlary Treatment Dates, $R70—3 (Feb.
    3, 1971)). The District
    says it dici not even hire a consultant to start work on the matter
    until October 1967 and that the consultant did not report until
    Decer.ber 1969. Then the District applied for a federal grant.
    rts prograz was not “fully defined” until October 1970,
    three
    and a
    half years after the regulation was adopted.
    The
    drawing of plans
    was nevertheless postponed pending the outcome of state
    and local
    bond elections, and even
    now
    the submission of complete plans is not
    anticipated before January 1972. Plans were due 30 months before
    the completion date, or in January, 1970.
    is’,

    The District alleges that the proposed time schedule is “reason-~
    able.t’ If the regulation had been adopted in 1971, we would agree;
    two years is an acceptable timetable for design and construction of
    tertiary facilities of this size. But the regulation was adopted in
    1967, and no reasons are given for the District’s inaction for nearly
    four years. One cannot qualify for a variance simply by iqnoring the
    timetable and starting late, While compliance within the remaininc
    time may be impossible, any hardship suffered as a result is,so far
    as is alleged, due to the District’s own inaction. To allow a
    variance on the basis of the present allegations would establish
    the preposterous proposition that the very existence of a violation
    is a ground for excusing it.
    The petition does not meet the requirements of Rule 401, and
    even if all allegations in the petition are true they
    do
    not entitle
    the District to a variance (Rule 405 (b) (1)). For these reasons
    no hearing will be held, and the petition is dismissed. A new
    petition correcting the above deficiencies may be filed.
    This opinion constitutes the Board’s findings of fact, conclusions
    of law, and order.
    I, Regina B. Ryan, do hereby certify that the above opinion has
    been approved this 22nd,
    day of ~-~rch
    ,
    1971,
    REGINA B.
    RYAN
    CLERK OF THE BOARD
    1
    * 360

    Back to top