ILLINOIS POLLUTION CONTROL BOARD
March 22, 1971
DECATUR SANITARY DISTRICT
)
)
v.
)
PCB #71—37
)
ENVIRONMENTAL PROTECTION AGENCY)
Opinion
and
Order of the Board (by Mr. Currie):
The District
asks
a one-year extension of the SWB-l4 timetable
for construction of tertiary treatment facilities.
The petition does
not contain the information required by Board Procedural Rule 401,
and it is dismissed.
The petition does not contain an adequate statement of the injury
that would result to the public if the variance were granted.
It is
stated only that the requested extension “would not be injurious”
and would not “reduce the present usefulness” of the receiving stream
Mere conclusions are not adequate; facts underlying the
conclusion
must be alleged.
See City of Jacksonville v. EPA, #70-30 (Jan. 27, 1971).
If the argument is that there is no need for tertiary treatment,
that
is contrary to the findings of the Sanitary Water Board in
adopting the regulation.
The District asks that the Environmental
rrotection Agency investigate the uses and quality of the river.
It
is the job of the petitioner, not of the Agency, to prove the case
for a variance. What are needed are specific allegations as to the
present uses and quality of the
stream and
any other facts the District
believes relevant to its conclusion that a year’s delay will not harm
the public.
r.loreover, there is no adequate allegation as to the reason the
District has delayed so long getting started on this project. The
tertiary treatment requirement has been on the books since 1967, and
the District admits it
was informed of the requirement
that
same
sprin;!, five years in advance of the scheduled date of completion.
We have found in a related case that three years is ample
time
from
conception to con~pletionof sewage treatment facilities (Mississippi
River Seconlary Treatment Dates, $R70—3 (Feb.
3, 1971)). The District
says it dici not even hire a consultant to start work on the matter
until October 1967 and that the consultant did not report until
Decer.ber 1969. Then the District applied for a federal grant.
rts prograz was not “fully defined” until October 1970,
three
and a
half years after the regulation was adopted.
The
drawing of plans
was nevertheless postponed pending the outcome of state
and local
bond elections, and even
now
the submission of complete plans is not
anticipated before January 1972. Plans were due 30 months before
the completion date, or in January, 1970.
is’,
The District alleges that the proposed time schedule is “reason-~
able.t’ If the regulation had been adopted in 1971, we would agree;
two years is an acceptable timetable for design and construction of
tertiary facilities of this size. But the regulation was adopted in
1967, and no reasons are given for the District’s inaction for nearly
four years. One cannot qualify for a variance simply by iqnoring the
timetable and starting late, While compliance within the remaininc
time may be impossible, any hardship suffered as a result is,so far
as is alleged, due to the District’s own inaction. To allow a
variance on the basis of the present allegations would establish
the preposterous proposition that the very existence of a violation
is a ground for excusing it.
The petition does not meet the requirements of Rule 401, and
even if all allegations in the petition are true they
do
not entitle
the District to a variance (Rule 405 (b) (1)). For these reasons
no hearing will be held, and the petition is dismissed. A new
petition correcting the above deficiencies may be filed.
This opinion constitutes the Board’s findings of fact, conclusions
of law, and order.
I, Regina B. Ryan, do hereby certify that the above opinion has
been approved this 22nd,
day of ~-~rch
,
1971,
REGINA B.
RYAN
CLERK OF THE BOARD
1
* 360